EARTHWORKS : Measurement
Breadth (m/ft.)
Length (m/ft)
In Case of Filling
When it is inconvenient to make measurements from cutting the filling or banking,
measurement is done through deduction for shrinkage or voids (“settlement
allowances”) from actual measured cubic contents depending on the nature of the soil
and methods of consolidation.
Deductions: 5%- by Heavy machinery, 10%- Ordinary Fill Consolidation
Lead/30m Top width
Width Length
Return, fill & ram : Returning, filling and ramming
excavated earth calculated in cu.m/cu.ft as separate 20cm(8”) depth
items. It includes spreading in layers of 20cm(8”) depth
for watering, ramming and leveling.
15cm(6”) depth
Surface Dressing : Trimming and dressing of
natural ground to remove vegetation and small
irregularities not more than 15cm (6”) deep
shall be calculated as “Surface Dressing” in
sq.m/sq.ft .
Surface Dressing : Cutting down trees more than 30
cm(12”) girth shall be enumerated stating the girth at 1m(3’) Girth>30cm(12”)
above ground and paid separately.
1m(3’) height
Pumping : When spring water requires pumping, the work of pumping and
dewatering shall be mentioned as separate items .