Professional Documents
Culture Documents
Project Scheduling: (Critical Path Method-CPM)
Project Scheduling: (Critical Path Method-CPM)
Project Scheduling: (Critical Path Method-CPM)
Dr. L. N. Pattanaik
EXAMPLE 1
EXAMPLE 2
EXAMPLE 3
Independent Float: It is excess time available if the preceding activity ends
as late as possible and the succeeding activity starts as early as possible. It
is refers to that the amount of time by which the start of an activity can be
delayed, without affecting earliest start time of any immediately following
activities.
A 0 0 0
B 3 0 0
C 2 2 2
D 0 0 0
E 3 3 0
F 5 5 2
G 0 0 0
Forward/Backward computation for AON type networks
Example:
For the project data in Table, answer the following questions:
a) Draw an AOA and AON network of the project?
b) Perform forward path and backward path calculations?
c) What is the effect of delaying activity D by 3 days?
AoN
Construct AoN and find critical path and floats for all activities