Professional Documents
Culture Documents
SWMS Surface Condenser Welding
SWMS Surface Condenser Welding
SWMS Surface Condenser Welding
This document describes the methodology for the Surface condensers Flash tank, Flash Box, Stand pipe installation, Welding and Garb Spring
Installation activity and to ensure that all concerned persons are familiar with the sequence of activities, utilization of resources and execution of the
works in compliance with applicable safety and quality procedures, reference documents and specification
2. SCOPE:
This method statement describes the Surface Condenser Flash tank, Flash Box, Stand Pipe Installation and welding and garb Spring Installation activities.
The activities involved such as movement of the material inside the construction site, unloading of the material at lay down area, shifting of material to
installation designated area, Flash Tank, Flash Box, Stand Pipe installation with the general safety and necessary control measures are described in detail.
3. REFERENCE DOCUMENTS:
DESCRIPTION
1.General Arrangement Drawing
2.Equipment's Foundation Drawing
3.P&I Drawing
4.Risk assessment sheet
1. The Flash Tank, Flash Box, Stand Pipe, And fittings to be stored on hard surface in the open yard.
2. The light fixtures and material to be stored in the closed store on flat surface above the ground.
3. The outside stacking must be lower than 2 metres.
4. The inside stacking must not be overloaded and protected from climatic effects.
5.3 Inspection
f) Before starting of the Flash Tank, Flash Box and Stand Pipe installation, the specification must be checked and ensured.
g) The PPEs and other tools tackles of the workers to be inspected for healthiness before starting of the job.
1. Lift the stand pipe with the help of lifting aid (Chain Pulley Block).
2. Align the stand pipe with upward measuring Standpipe connection provided in shell & downward measuring
Standpipe connection in Hotwell.
3. Check the dimensions given in the G.A Drawing .Record the same. Fit stand pipes with all valves and instruments
to the condenser shell and hotwell. Refer the condenser GA drawing for orientation/ position of the component.
4. Please refer below sketch for arrangement of stand pipe.
Access
1. Clear all obstructions (if any) in the way to 1. Clear all obstructions (if any) in the way to the work location.
the work location. 2. Scaffolding gang will construct required length of Scaffolding platform depending on
2. Clean the nearby area before starting of the Flash Tank and Stand Pipe.
the job. 3. Working platform will be certified by the Scaffolder and all authorized persons will be
allowed to access the working platform.
4. Wherever Required, lifeline must be used.
Lifting
1. The Flash Tank and Stand Pipe materials 1. The Flash Tank, Stand Pipe and all other accessories are generally to be carried
are generally to be carried manually. manually.
2. In case of higher elevations, Flash Tank 2. In case of higher elevations, Flash Tank And Stand Pipe can be lifted by using pulley’s
And Stand Pipe can be lifted by using arrangement and a guide rope.
pulley’s arrangement and a guide rope. 3. All materials must be lifted to the installation point by using proper rope with bag
arrangement for carrying the small parts.
Installation Fabrication
Marking shall be done according to drawing requirement and the same shall be checked by concerned supervisor prior to cutting.
The cutting shall be generally done as following:
a) Carbon Steel pipes - By gas cutting & grinding.
1. End preparation and fit-up shall be done at shop as per the approved Specification and WPS.
2. Care shall be taken to make sure that longitudinal seams on the joining pipes will not come in one line in a butt joint. Seams will be
staggered at least 100mm apart and also will clear the branch connections. Care shall be taken to make sure that longitudinal seams
are not resting on the steel structure.
3. Welding of the joint will be done after getting QC fit-up Inspection clearance and the same shall be offered for Client inspection
randomly.
2. Start the work on proper and valid PTW and availability of competent manpower and supervisor.
3. Measure the route and distribution of the Flash Tank and Stand Pipe installation.
5. Make proper bends and angles in the cut pieces as per requirement.
6. Take proper power connection from safe source and using proper cables and DBs.
Procedure:
1) Refer the condenser GA drawing for orientation/ position of the component.
2) Before welding match the Neck & dome edge with marked / painted welding line on shell.
Sequence:
3) Tack-weld the Neck & Dome to the Condenser shell assembly (without cut the shell) and check the dimension/orientation/levels
once again and record the same, weld the assembly from outside.
4) All around fillet argon root [GTAW_Gas tungsten-arc welding (TIG) ASME SFA 5.18 AWS ER70S-2].
5) 100% DP test.
6) Fillet welding with 3.15mm (SMAW_Sheild Metal-Arc welding ASME SFA 5.1 AWS ER 7018).
7) Subsequent; fillet welding (SMAW) with 3.15 OR 4 mm should be up to 12 mm.
8) 100% DP OR water filled test (min 300mm above the welding joint line).
Caution: Before fill the water please lock the spring support
Note: Actual Resource Plan both Tools & tackle and manpower will be review & finalized by Site in- charge .
List of resources and material to be prepared at site.