Professional Documents
Culture Documents
Contract Changes Management 8. Claim and Dispute Management System
Contract Changes Management 8. Claim and Dispute Management System
By Habtamu.A 1
Introduction
The two most important issues considered in
contract change management are Uncertainties
and Changes.
Uncertainties are issues that can either be
difficult to reasonably predict or unknown during
the planning phase of Procurement and Contract
Management.
Changes are issues requiring alterations during
the implementation of Procurement and Contract
Management.
By Habtamu.A 2
Uncertainty
Uncertainty is the difference between the amount
of information required to perform the task and
the information already available by the planning
team.
One can clearly understand that uncertainty is the
major factor that conflicts with prediction or
planning.
By Habtamu.A 3
Uncertainty & changes
As projects are planned under a certain level of
uncertainty, it implies that all projects take over
risks during implementations.
This can be one of the major reasons why changes
occur during implementations.
A quantitative estimate of a risk and the
subsequent pricing for it is a difficult task
particularly in developing countries
By Habtamu.A 4
Mitigation of Uncertainties/Risk
Absorbing/retention: Provisions in the
form of Contingencies, Alterations, etc are
made and used to absorb changes caused by
uncertainties.
Dividing or Splitting: When a project
uncertainty is high or there is less past
experience, dividing projects into packages
or different phases or to make them smaller
sizes, etc is to divide or split to minimize
the uncertainties.
By Habtamu.A 5
Postponing: When Contracts could not
clearly state specifications, quantities and
estimates, they often place Provisional
quantity or provisional Sum to postpone
uncertainties.
Transferring: Lump Sum Contracts, DB
and BOT delivery systems are some form
of contractual approaches to transfer
uncertainties from Owners to Providers.
By Habtamu.A 6
Quantifying Risks
Once the likelihood of occurrence of risk is
established, the next step is to predict what
impact that occurrence will have on:
◦ The construction cost,
◦ Schedule,
◦ Quality,
◦ Safety,
◦ Client relationship, or
◦ Contractor’s ability to fulfill the
obligations of the contract.
By Habtamu.A 7
Quantifying Risks …
By Habtamu.A 11
Determining impact potential …
By Habtamu.A 12
Quantifying Risks example
Confusing, contradictory, or
2 1 2
incomplete plans and specs
Differing subsurface
2 2 4
conditions
Adverse weather 1 1 1
Community protests 2 3 6
Once risks are rated, it can be determined which ones to
focus on and how best to mitigate them.
By Habtamu.A 13
Risk Mitigation Strategies
The risks that pose the greatest threat are the ones
that you want to focus your risk mitigation
strategy on.
It is often helpful to chart risk ratings to establish
a visual display of where the greatest danger is as
you plan your project and strategize to mitigate
negative influences.
By Habtamu.A 14
Simple Risk Diagram
By Habtamu.A 15
Requirement Changes Management Systems
By Habtamu.A 16
Rights & Obligations of the parties
Requirement changes can cause review of designs
and/or create additional or changes in designs
and/or just work orders to instruct contractors to
carryout the requirement changes.
While project owners retain the right to
requirement changes, the contractor is obliged to
accept as per the conditions of the contract.
The contractor is entitled to request and agree
upon new or existing rates for such changes.
By Habtamu.A 17
Change Orders
Written instructions, agreed by the Project Owner
or His Representative, directing the Project Doer
to make changes with or without the Consent of
Regulatory Bodies.
There are three kinds of Change Orders:
1. Unilateral Change Order: provides the right
to any of the parties to make changes without
causing any effect
2. Bilateral Change Order: require the
agreement and/or consent of the two
contracting parties
3. Multilateral Change Order: require the
agreement and/or consent of the three or more
contracting parties
By Habtamu.A 18
Effect of Requirement changes
By Habtamu.A 19
Time Changes Management System
By Habtamu.A 20
Construction Time Competitions
By Habtamu.A 21
Time Delays and Overruns
Time delays can occur in components of a project
or trades of works, but when their cumulative
effect makes the actual completion time beyond
the contract completion time, it is called time
overrun.
Generally, time delays can be classified into:
Concurrent and Serial Delays
By Habtamu.A 22
Time Delays and Overruns …
Concurrent delays are delays that occur simultaneously
when they were carried out parallel.
Their effect for the project can be assessed using that part
of the work which causes longest delay and its
consideration are made as such
For instance, if a project owner agreed to supply material
and irrespective of its delay, if the project faced adverse
weather condition; the project can not be executed.
Therefore, both delays could not be counted as serial
delay but concurrent and the one that causes longer
delay is considered for time delay computations.
By Habtamu.A 23
Serial Delays
Justifiable and Non - Justifiable Delay
• Justifiable delays are delays that occurred due to causes
which are beyond the control of project doer.
If delays are caused by project owners, the contractor or the
consultant or the supplier is directly justified for the effects
on delay of the project.
Force Majeure will also be one of the causes for justifiable
delay.
By Habtamu.A 24
Claim and Dispute
Management System
By Habtamu.A 25
Introduction …
Claim is mostly concerned with entitlements
and liabilities arising under, or as a result of,
a legally valid contract.
A construction claim is therefore can be a
demand for payment of additional
compensation, adjustment of the parties'
respective contractual obligations, Extension
of Time or compensating delay damages, or
any other change with regard to the
contractual conditions or terms
By Habtamu.A 26
Introduction …
Claim in practice can also be understood in
different ways based on the perceptions held by
contractual stakeholders.
◦ A claim is an assertion to a contractual
right.
By Habtamu.A 27
Types of claims
1.Time Related Claims: Claims associated
with delay or in time completion of
projects where either of the following six
entitlements or Penalties are subjected to:
◦Time Extension only
◦Liquidated Damages only
◦Time Extension and Cost Compensation
◦Concurrent Compensations
◦Bonus
By Habtamu.A 28
2. Cost Related Claims: Claims associated with
monetary compensation where either of the
following entitlements or penalties are
entertained:
◦Additions requiring rate adjustments
◦Price Changes
◦Provisional sum adjustments
3. Default by Contracting Parties: Claims
associated with non performances of contractual
obligations such as:
◦Delay in Payment Certificates
◦Suspensions and Terminations
By Habtamu.A 29
Claim Administration Processes (CAP)
Claim administration process is understood as
the process for the compensation of any damage,
and/or changes resulted during the
implementation of Construction projects
The CAP is then understood as the process
starting from a willful act of the claimant
through claim notification by either of the
contracting parties up to and including claims
approval and acceptance by both the contracting
parties for agreed or enforced compensations or
otherwise called claim enforcement.
By Habtamu.A 30
CAP …
•Claim Notification
•Claim Preparation •Claim Enforcement
•Claim Submittal •Claim Closure
•Claim Handling
•Dispute Resolution
•Claim Approval
By Habtamu.A 31
Claim Submittal
This is a process by which the claimant is
obliged to claim within a reasonable period of
time (28 – 30 days in most contracts)
followed by her/his preparation for all
substantial documents.
This constituted that a claim has been filed for
its consideration if all these three sub
processes called Claim Notification, Claim
Preparation and Claim Submittal are fully
undertaken by the claimant.
By Habtamu.A 32
Claim Processing
This process initiates checking of the claim whether:
◦ Legally or contractually supported or not;
◦ documents provided are valid and reliable to substantiate
the claim for consideration or not; and
◦ overall procedural requirements have been followed or not
After verifying, proper computations and evaluations will be
carried out to present the proposed compensation Claim
Handling.
The contractual parties will pass through different dispute
resolution system depending on their acceptance over the
proposed compensation varying from the simplest mediation
by the consulting engineer to the final court ruling in the
form of litigation
By Habtamu.A 33
Dispute resolution (DR) systems
1. Preventive: Partnering, Use of DR advisors and Use of
Facilitators for early neutral evaluation and advise to
prevent the happening of claims.
2. Amicable: Negotiation, Mediation, Conciliation and use
of Mini-Trials to administer the claim in a less formal,
simple procedure, more flexible, less adversarial and
strictly confidential mode so as to avoid the time and
cost implication of claim processing.
3. Judgmental: Adjucation or use of Dispute review board,
Arbitration and Litigation where the formal adjucatory
or common law system is applicable to bring the closure
of claim processing.
By Habtamu.A 34
Stages in DR
Mediation Mini-trial
Arbitration
By Habtamu.A 35
Claim Enforcement
This is a stage where the approved claim is
enforced and finally becomes a closure
therefore two sub processes are included
The claim enforcement process will
entertain the inclusion of the approved
claim into payment certificates where their
enforcement is due
By Habtamu.A 36
The End
By Habtamu.A 37