Professional Documents
Culture Documents
Earned Value..2021
Earned Value..2021
• Formula: CV=EV- AC
Schedule variance (SV)
• SV equals earned value (EV) minus planned
value (PV).
• Schedule variance will ultimately equal zero
when the project is completed because all of
the planned values will have been earned.
• Formula: SV=EV-PV
Cost variance (CV) & Schedule variance (SV) is used in efficiency
indicators
• 1) EAC = BAC/CPI
• 2) EAC = AC+(BAC-EV)
• (If current cost variances will not continue for the entire project)
• This is why this formula includes the Actual Cost of the work
done until now plus the cost for the remaining work.
• Money Spent to Date + Budgeted Cost for the Remaining Work
3. EAC=AC+ ETC
• Cost variance
• Schedule variance
• Cost performance index
• Schedule performance index
• To-complete performance index
• Variance at completion
• Cost forecasts as an output
• CPI = EV / AC
•CPI = Rs40 Crs/Rs 50 Crs
•CPI = 0.8
• Now to calculate EAC
•BAC = Rs200 Crs •CPI = 0.8
•EAC = BAC/CPI
• Question:
• You're managing a project which has a total cost of Rs200 Crs.
• An incident occurs during the execution of the project which
requires a lot of money to resolve.
• However, since this was an isolated incident, it is not
expected to occur in the future and the project is expected to
continue with the same performance as before.
• Till now, you have spent Rs110 Crs on the project, and the
value of the work so far completed is Rs90 Crs
• What is the Estimate at Completion ?
• Answer
• As you'll notice, the rise in costs was temporary and the
project can be continued as per the original plan.
• EAC = AC+(BAC-EV)
• Actual Cost (AC) = Rs110 Crs
• Budget at Completion (BAC) = Rs 200 Crs
• Earned Value (EV) = Rs90 Crs
• EAC = 110 + (200- 90)
• = 110 + 110
• EAC = Rs220 Crs
AC + bottom up estimate to complete