Planning Concepts
Construction Planning
Setting Milestones for overall completion
Organizing activities for Individual area completion, duly
acknowledging their inter dependence
Providing various Resources
Directing the Planning for execution
Review and Redirection
Planning in total….
Planning is assembling total inputs
Men, Machine, Materials
Tools / Small Tools
Lay down area
Clearances
Apply productivity while planning
Break job into activities
Quantify each activity
Find out unit quantum of the job, may be a joint, major
or minor lift
Study rate of achieving unit quantum
Pace the job by setting tougher norms every day
Sequencing Activity
Interdependence to each other
Gang Movement
Resource Leveling
Review and Redirect
Planning once done, is not done for ever
Periodical review sets the rhythm
More looks on planning throw more clarity on the path
of our progress
You need to set new dates, reschedule resources
Planning Levels
Term Objectives Periodicity
Res
ou rce
Re Bud
Re
sou g etin
rce g
so
M
ur
ob
ce
ilis
atio
Di
n
re
nth
ct
3rd Mo
io
n
nth
2nd Mo
M
sto nth
1
t Mo nth
n
Prese
CONSTRUCTION PROGRAMME FOR PIPE RACK
WORK
PERIOD IN MONTH
SL NO ACTIVITY UNIT SCOPE DURATION
1 2 3 4 5 6 7 8
1 MOBILIZATION LS - 15 DAYS
215 261
3 FOUNDATION WORK CUM 476 60 DAYS
295 148
4 PAINTING & BACKFILLING CUM 443 45 DAYS
NSH
NSH
NSH
2 DUMP TRUCK NOS 2 75 DAYS
3 LOADER NO 1 60 DAYS
8 TRAILER NO 1 90 DAYS
6 10 6
2 MASON EA 7 60 DAYS
6 8 12 NSH
NSH
NSH
3 STEEL FIXER EA 9 75 DAYS
12 18
4 CARPENTER EA 15 60 DAYS
8 20 30 25 25 18 12 10
5 LABOUR EA 19 225 DAYS
15 25 25 25 15
6 SCAFFOLDER EA 21 150 DAYS
1 2 2 2
7 STRUCTURAL FOREMAN EA 2 60 DAYS
8 16 16 12
8 STRUCTURAL FITTER EA 13 60 DAYS
1 2 2 2 2 1
9 PIPING FOREMAN EA 2 135 DAYS
8 14 18 16 8 6
10 PIPE FITTER EA 12 135 DAYS
4 8 10 10 8 6 2
11 WELDER EA 7 135 DAYS
WORK
SL PERIOD IN MONT H
ACTIVIT Y UNIT SCOPE DURAT ION REMARKS
NO 1 2 3 4 5 6 7 8
495 985 NS
N
NSH
2 EXCAVAT ION CUM 1480 45 DAYS
215 261
3 FOUNDATION WORK CUM 476 60 DAYS
295 148
4 PAINT ING & BACKFILLING CUM 443 45 DAYS
SL PERIOD IN MONT H
EQUIPMENT DESCRIPTION UNIT QTY DURAT ION REMARKS
NO
1 2 3 4 5 6 7 8
NSH
NS
N
2 DUMP T RUCK # NOS 2 60 DAYS
3 LOADER NO 1 60 DAYS
PERIOD IN MONT H
SL
T RADE UNIT QTY DURAT ION REMARKS
NO
1 2 3 4 5 6 7 8
1 1 2 1
1 CIVIL FOREMAN EA 1 90 DAYS
6 10 6
2 MASON EA 7 60 DAYS
6 8 12 NS
N
NSH
3 STEEL FIXER EA 9 75 DAYS
12 18
4 CARPENT ER EA 15 60 DAYS
8 20 30 25 25 18 12 10
5 LABOUR EA 19 225 DAYS
15 25 25 25 15
6 SCAFFOLDER EA 21 150 DAYS
1 2 2 2
7 STRUCT URAL FOREMAN EA 2 60 DAYS
8 16 16 12
8 STRUCT URAL FITT ER EA 13 60 DAYS
1 2 2 2 2 1
9 PIPING FOREMAN # EA 2 135 DAYS
8 14 18 16 8 6
10 PIPE FIT T ER # EA 12 135 DAYS
4 8 10 10 8 6 2
11 WELDER # EA 7 135 DAYS