Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 29

RCCPL Kundangunj

Grinding with VRM system

1 1
VERTICAL ROLLER MILL

Confidential Slide 2
Transport
Exhaust gases
Raw meal

1. Separation  Drying Separation

Feed
Material

Grinding

2. Grinding  Hot
gases

Drive
Energy

3. Drive 

Confidential Slide
Confidential Slide 4
Typical Grinding Principle

Confidential Slide 5
Separator: Gas & Product Material
Removes fine
material Feed Material
Rejects coarse
material

Internal gas Separator Rejects


flow
Internal Circulation
Large Material falls through
to scraper
Material
Material & Gas
Gas
How does a vertical mil work?
• The raw materials are fed directly to the centre of the grinding plate, from
centrifugal forces and the pushing effect of the incoming materials
themselves (both fresh and separator coarse material), are distributed
evenly under the grinding rollers.

• The turning speed of the grinding plate, together with the pressure of the
grinding rollers, create the necessary friction for grinding the materials.

• The grinding process starts with the preparation of grinding bed, where the
coarse material is crushed. Then the material in compressed and ground by
the grinding rollers.

• After being ground, the material is transported to the dynamic separator by


the (more or less hot) gas flow, where the selection of the material takes
place.

• The coarse material coming from the separator is directed back to the center
of the grinding plate in order to be ground again.

Confidential Slide
Confidential Slide 9
Parameters to be monitored during Operation

Confidential Slide 10
Grinding force =Roller weight + (pressure) Force

Roller rolls
freely with table
Material bed

Feed material Table moves with drive

Confidential Slide
TROUBLE SHOOTING

Confidential Slide 12
Common aspects of operation with regard to the grinding process and generally
exhibits the following characteristics.

Trouble Probable cause

Excessive vibration
• Sudden change to high moisture feed
• Improper feed distribution
• Sudden change to fine product
• Sudden change to oversize feed
• Dam ring height not uniform

• Excessive air flow sweeping the table


• Rollers contacting the stoppers
• Excessive feed

Confidential Slide 13
Confidential Slide 14
Confidential Slide 15
Confidential Slide 16
Confidential Slide 17
 Mill feed size
 Preferably wide distribution of particle sizes. The largest particle size to
be maximum 3 - 4% of the roller diameter. Typical feed size distribution :
 100% passing 100mm
 95% passing 60 mm
 Maximum 10% passing 1 mm

 Impact of Incorrect Feed Size


 Abnormal feed size and/or distribution may increase the level of vibration
and destabilise the mill.
 Large feed size in any case will reduce the mill production rate.
 Excessive fines in the feed material or recirculated from the separator
can make the rollers slip and adversely affect the stability of the grinding
bed.

Confidential Slide 18
 Controlling Vibration and control measures

 Match grinding pressure to mill throughput – establish relationship between


feed rate and hydraulic pressure.
 Maintain an even bed, avoid excessive fines in mill feed, avoid uncontrolled feed
variations, even distribution of material to each of the rollers, feed to the centre of
the table, adjustment of feed chute and or use of guide vanes.
 Apply stable water spray to the control bed, normally fed to the feed side of each
roller, check flow consistency on each spray
 Know the critical level of gas flow and pressure drop for your mill
 Maintain stable mill gas flow to keep internal circulation consistent.

Confidential Slide 19
Trouble Probable cause

High Mill DP
• Low grinding pressure

• Feed rate too high

• High internal circulating load

• High air flow

• Excessive water spray

• High inlet temp

• Low exit temp

Confidential Slide 20
Trouble Probable cause

Low Mill DP • Feed rate too low

• Product too coarse

• Dam ring height too high

Confidential Slide 21
Trouble Probable cause

Product too course • Classifier speed too low

• Air flow too high

• Louver ring velocity too high

Confidential Slide 22
Trouble Probable cause
High rejects
• Mill air flow too low

• Sudden increase in feed rate

• Grinding pressure too low

• Low dam ring height

• Louver ring velocity too low

Confidential Slide 23
Trouble Probable cause

Feed material • Lower exit temperature


too wet
• Material agglomeration on the grinding bed

High roller vibration

• High Dp

• High drive motor amps

Confidential Slide 24
Trouble Probable cause

High internal
• Higher Dp
Circulating load
• Product fineness too high
• Classifier choked
• Lower grinding pressure
• Low air flow

Confidential Slide 25
Confidential Slide 26
Operational Measures and their utilization in process.
 Air flow measurement through Pitot Tube.
• To find out material to air ratio.
• To calculate fan efficiency .
• To calculate False air in circuit.
• To measure Nozzle velocity

 Mill Outlet Temperature.


 DP across Mill.

Confidential Slide 27
Maintenance Of VRM

You might also like