Fabrication Method:

Day 1-2
• Casing Fabrication Marking,cutting,

1 Boring, forming
And griding

Day 3-5
• Installation of negative ionizer, - Welding parts
odor sensor system, afan, air and assembly of

2 quality indicator and fan controller. other parts

Day 6
-Finishing and
• Wheel assembly and painting painting
3
Key Parts, Sourcing and Cost Estimates
Total
No. Item Description Quantity Unit Unit Cost Cost
1 Silver Plain GI 2 pcs 1900 3800
sheet (1.2 mm)(10
  by 20 ft)        
2 Cold Catalyst Filter 3 pcs 514 1542
3 Negative Ionizer 1 pcs 257.64 257.64
Odor Sensor
4 System 1 pcs 564.26 564.26
5 Fan 4 pcs 359.56 1438.24

6 Air Quality Indicator 1 pcs 650 650


  and Fan controller        
7 Caster Wheel 4 pcs 40 160
8 Steel screw 30 pcs 15 450
Material
Cost         8862.14
WORK FORCE

Welder-perform all welding work such as forming, cutting,


joining and reshaping the metal casing of air purifier. Fabricates
metal casing of the machine. 20243.25/month

Electronics Technician assembles and fabricates sensors


and other electronic equipment. It inspects and test sensors
to ensure conformance to the standards. 19900/month

Mechanics assembles all the component of the machine and


performs repairs. 15,600/ month
FABRICATION EQUIPMENT
PRODUCTION FACILITY
COSTING SUMMARY