MICRO-SCHEDULE FOR

KHATAU BUNGALOW
REPAIR WORKS

k
C
D E

F
B

NOTE: NOMENCLATURE AS PER SCHEDULED SEQUENCE OF ACIVITIES


SR. NO. ACTIVITY FACE A FACE B FACE C FACE D FACE E FACE F

1 ERECTION OF DOUBLE BAMBOO DONE DONE DONE DONE DONE DONE

SCAFFOLDING
100% 100% 100% 100% 100% 100%

2 BREAKING OF PLASTER DONE DONE DONE DONE DONE DONE

100% 100% 100% 100% 100% 100%

3 RCC POLYMER TREATMENT DONE DONE DONE DONE DONE DONE

100% 100% 100% 100% 100% 100%

4 PLASTER WORKS

a) DASH COAT PLASTER DONE DONE DONE DONE DONE DONE

100% 100% 100% 100% 100% 100%

b) PLASTER FIRST COAT DONE DONE DONE DONE DONE DONE

100% 100% 100% 100% 100% 100%

c) PLASTER SECOND (FINAL) COAT 28-MAY TO


30-MAY
29-MAY TO
30-MAY
28-MAY TO
30-MAY
29-MAY TO
30-MAY
29-MAY TO
30-MAY
29-MAY TO
30-MAY

0% 50% 0% 0% 0% 0%
SR. NO. ACTIVITY FACE A FACE B FACE C FACE D FACE E FACE F

5 APPLICATION OF SYNTHETIC 31-MAY TO 3-JUNE TO 31-MAY TO 3-JUNE TO 3-JUNE TO 3-JUNE TO


2-JUNE 5-JUNE 2-JUNE 5-JUNE 5-JUNE 5-JUNE
TEXTURE
0% 0% 0% 0% 0% 0%

6 APPLICATION OF 6-JUNE TO 6-JUNE TO 6-JUNE TO 6-JUNE TO 6-JUNE TO 6-JUNE TO


10-JUNE 10-JUNE 10-JUNE 10-JUNE 10-JUNE 10-JUNE
ELASTOMERIC PAINT

7 FIXING OF FRP CHAJJA 11-JUNE TO NA NA NA NA NA


15-JUNE
SITE PROGRESS PHOTOGRAPHS

FACE C FIRST COAT OF PLASTER (1/2)


SITE PROGRESS PHOTOGRAPHS

FACE D FIRST COAT OF PLASTER(2/2)