Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 45

FINAL YEAR PROJECT REPORT

ON
UPGRADATION AND ESTIMATION OF RURAL ROAD OF BAGMARA FROM SHIPLINGTARA TO
CHISAPANI OF POKHARA METROPOLITAN CITY

IOE, Pashchimanchal Campus, Lamachaur-16, Pokhara

Submitted By: Submitted To: Supervisor:

Nischal Pokhrel (PAS074BCE070) Department of Civil Engineering Er. Sabina Poudel


Nitesh Risal (PAS074BCE071) Pashchimanchal Campus Department of Civil
Pratik K.C. (PAS074BCE083) Lamachaur-16, Pokhara Engineering
Pravin Singh Thakuri (PAS074BCE086)
TABLE OF CONTENTS
1 INTRODUCTION
2 STATEMENT OF PROBLEM
3 OBJECTIVES
4 SCOPE OF PROJECT
5 SALIENT FEATURES OF THE PROJECT
6 WORKING METHODOLOGY
7 DESIGN
8 COST ESTIMATION
9 LIMITATIONS OF THE PROJECT
10 CONCLUSION
INTRODUCTION

 Road lies in Pokhara metropolitan ward no.33 connecting


shiplingtara to chisapani.

 Earthen road with poor driving surface.

 Poor drainage system of storms and hindrance in transportation


during monsoon.

3
STATEMENT OF PROBLEM

 Poor geometric designs of road like super elevation, camber


slope, gradient and so on.
 Products are not getting proper market.
 Narrow road causes difficulty in traffic crossings.
 Lags development.
 Travelling gets laborious during monsoon.

4
CONDITION OF ROAD

5
OBJECTIVES

1. To conduct detailed survey of the road.

2. To prepare detailed design and cost estimation of the road.

6
SCOPE OF THE PROJECT

• Geometrical designs like longitudinal section and cross section.


• Design of drainage and curve of the road.
• Earthwork calculation
• Estimation and costing
• Detailed Project Report (DPR)

7
PROJECT LOCATION

 Located in Pokhara Metropolitan- 33, Bagmara. Gandaki, Nepal.

8
HYDROLOGY AND METEOROLOGY

 Sub-tropical climate.

 Almost 80% rainfall during monsoon.

 Temperature varies from 7 degree Celsius to 37 degree Celsius.

9
SALIENT FEATURES OF ROAD

• Classification of Road by NRRS-2071: District Road(Hill)


• Length: 3094m
• Terrain: Hilly (Rolling) and Terai mixed.
• Climate: Moderate(Sub-tropical)
• Geology: Loose and Boulder mixed soil
• Hydrology: Precipitation controlled by monsoon.
• Meteorology: Precipitation controlled by monsoon.
• Soil Type: Sandy, Silty and Clayey

10
CONTINUE…

 Right of Way: 20m (10m on each side)


 Formation Width:
Road width: 8.5m
Carriage Width: 7m
Shoulder width:0.75m on each side.
 Side drain shape and size: Rectangular (0.3*0.6)m
 Design speed: 25 Km/hr
 Minimum Gradient: 0.55%
 Maximum Gradient: 10.89%

11
WORKING METHODOLOGY

Consultation
Study area Site visit With
supervisor

Preparation Data collection,


Preparation of
of Analysis and
Detail project
Drawing Design
Report

12
SOFTWARES USED

 Smart Road 2018

 AutoCAD

 MS-Excel

 MS-Word

 MS-PowerPoint.

13
HORIZONTAL ALIGNMENT OF ROAD

14
PROFILE OF THE ROAD

15
DESIGN OF HORIZONTAL ALIGNMENT

Design is based on Nepal Rural Road Standards 2nd Revision, 2071.

 Horizontal curve should assist safe change in direction of


vehicles.

  Radius below absolute minimum should not be provided.

 Super-elevation is provided to balance centrifugal force along the


road.

16
CONTINUE…

 The minimum radius of horizontal curve is calculated by ;

or,

Sample calculation:

V = Vehicle Design Speed = 25 km/hr.

R = Radius, m

e = super elevation = 0.1%

f = coefficient of lateral friction = 0.15

17
CONTINUE…

 Rmin= 25²/{127(0.1+0.15)} =19.68 m

which is below minimum permissible value 20m. Thus 20 m is


adopted for the design.

The recommended minimum radius value is tabulated below:

18
SIGHT DISTANCE

According to NRRS-2055, 2071 2nd edition,

Safe stopping sight distance(SSSD):

We have,

Design speed= 25kmph


Perception time=2.5 secs
Co-efficient of friction(f)=0.4 for 20 kmph
=0.35 for 100 kmph

19
CONTINUE…

From above,

SSD= 23.52m<25 m for given speed.

Thus the design is ok.

 Intermediate Sight Distance

Intermediate sight distance is twice the safe stopping sight


distance.

 i.e.    ISD = 2 × 25=50 m

20
CROSS SECTIONAL ELEMENTS
 CAMBER

 Camber provided in the road helps in draining surface water.

 Camber % used in different types of roads are given by NRRS-2071,


shown in table below.

21
SUPERELEVATION:

 Super-elevation is provided in horizontal curve to compensate centrifugal


force.

 Value of Super-Elevation is given by

As per NRRS,
Max Super-elevation for Terai=7%
Max Super-elevation for Hill= 10%

22
CONTINUE…
Sample Design calculation of Super elevation:

Let us consider,
Radius(R ) = 40 m,
Design speed = 25 kmph,
f = 0.15
traffic condition= mix
We know,
Superelevation (e)= ( 𝑉²/127R)-f
= (25²/127*40) – 0.15
= 0.0695
23
CONTINUE…

Here e < 0.1 (max. Superelevation for Hill=10%)


Hence, provided Super-Elevation is 10% is ok

24
EXTRA WIDENING

Extra widening is calculated by

Where,

n = number of lanes

W = Widening, m

L = length of wheel base of longest vehicle (m) = 6.1m

R = Radius of horizontal curve, m


25
CONTINUE…

Sample design calculation:


For R = 20m,
n=2
V = 25 km/hr
We get,
W = 2.45m
We can provide Extra-widening of minimum 1.5m and above for given
design radius.

26
VERTICAL ALIGNMENT DESIGN

• Vertical curves are provided at the intersection of two longitudinal grade lines for safe and
smooth flow of traffic.

• It may be either Valley or Summit curve.

• All vertical curves are parabolic in nature.

Algebraic difference between the gradients (N) = L 1-L2

Where, N = Total change in grade

r = rate of change of grade

L1 and L2 = Gradient of first line and second line.


27
CONTINUE…

Since, the parabolic curve is considered, minimum radius of vertical


curve may be calculated as,

28
CONTINUE…

Gradient :

• Maximum gradient provided is 12% and minimum gradient is 0.5% (1% max).

Summit Curve:

 Summit curves are usually designed to provide adequate stopping sight distance.

The minimum radius of summit curve is (𝑅𝑚𝑖𝑛 ):

29
CONTINUE…

Valley Curve:

 Vertical curve is designed considering the night visibility condition.

Length of vertical curve considering night visibility condition is ,

Where,

Height of headlight of vehicle (h) =0.75 m

Angle of head light beam (α) =1°

30
CONTINUE…
Elements of vertical curve

The formulae used for the calculation of elements of vertical curves are:

1. Tangent length

2. Length of curve

3. Apex distance

4. The formula for setting the offset of the curve

31
DESIGN OF DRAINAGE

• The peak run off is calculated by rational formula;

Where,

Q=Runoff in m3/s

A=Area of the catchment (160 ha)

C=Impermeability factor (0.25)

I=Rainfall intensity ( 6.6 mm/hr)

32
CONTINUE…

Thus,

The design discharge in the drain is 0.75 m3/s.

33
CONTINUE…
 The discharge calculated before is used in Manning’s formula
given as,

where,
n=Manning’s roughness coefficient (0.014)
A=Area of flow
R=Hydraulic radius
P=Wetted perimeter
S=Slope of bed (7%)

34
CONTINUE…
For the most economical section, we take
where,
B=Width of Section
D=Depth of flow
On solving, we get
0.75

Hence,
Depth of 0.3m is adopted.
Therefore,
width of drain= 2*0.3 = 0.6m

35
DESIGN OF PAVEMENT

Pavement is designed using DOR method for which the formula for number of
standard axles for design period is,

where,

r=Traffic growth rate

=Traffic in the year of project completion

VDF=Vehicle Damage Factor

LDF=Lane Distribution Factor


36
CONTINUE…

Calculation:

Type of road = Two lane

Heavy truck two axle = 80 * 4 = 320

Mini truck = 60 * 3 = 180

Motorcycle = 200 * 0.5 = 100

Car and light van = 80 * 1 = 80

Bus = 80 * 3 = 240
Thus,
Initial traffic in the year of commencement of construction, P=500 37
CONTINUE…

Traffic growth rate = 7%

Design life = 15 years

So,

LDF= 0.75 (for two lane road)

Now,

38
CONTINUE…
Pavement Composition
Total Pavement
Cumulative traffic Bituminous Surfacing Granular Granular
Thickness
(msa) Base Sub-base
(mm)
Wearing course Binder Course (mm) (mm)
1 430 20 PC 225 205
2 490 20 PC 50 BM 225 215
3 530 20 PC 50 BM 250 230
5 580 25 SD BC 55 BM 250 250
10 660 40 BC 70 BM 250 300

39
CONTINUE…

From figure given above,

Total pavement thickness with CBR of 5% and 6.33msa = 600mm

Pavement composition :

I. Bituminous wearing course: BC 30 mm.

II. Bituminous Binder course: DBM 60 mm

III. Base course: Granular base 250 mm

IV. Sub-base: Granular sub-base 260 mm

40
CONTINUE…

BC 30 mm

DBM 60 mm

Granular Base Course


250 mm

Granular Sub-base
260 mm

Sub Soil

41
COST ESTIMATION

S.N. Description Amount (Rs.)


1. Earthwork cutting 448329.389

2. Earthwork Filling 87988.166

3. Pavement 51332079.8
4. Structural Works 11989382.8

Sub-Total 63857780.1
VAT @13% 8301511.42
Total including VAT 72159291.6

Cost per Km 23329871.2


42
LIMITATIONS OF PROJECT

 Hydrological data is considered from nearest station at Pokhara


International Airport.
 Soil testing is not conducted for the project.
 Large cross drainage structures like bridges are not designed.
 Structural analysis is not done for retaining structure.
 Traffic survey was conducted for one day only.

43
CONCLUSION

 Completed survey of 3094 m long road within 4 days.


 According to the district rate and norms, estimation and costing
for the road were done and found to be financially feasible with
cost per km to be Rs. 2,33,29,871.2
 At some cross sections, masonry walls are required for slope
stability.
 With use of this DPR, geometric designs of the road can be
improved for better accessibility, safe crossings and so on.

44
THANK
YOU 45

You might also like