Khulna Mongla Port Rail Line Project Bangladesh
Khulna Mongla Port Rail Line Project Bangladesh
Welcomes
Dr.Sumeet Jerath , Additional Secretary Finance, MEA/GOI
HE. Harsh Vardhan Shringla, HCI in Bangladesh
Mr. Subrota Roy Moitra, DG/PMO/GOB
11.12.2017
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT
BANGLADESH
PROJECT INFORMATION – Key Plan
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT
BANGLADESH
BRIEF ABOUT THE PROJECT
Name of the Project - Construction of Khulna –Mongla Port Rail Line Including Implementation
of EMP
Client - Bangladesh Railway
Contractor - IRCON INTERNATIONAL LTD.
Client Consultant - NIPPON KOEI India Pvt. Ltd. & CONSULTING Engineering Group Ltd.
Source of fund - Indian Dollar Credit Line (LOC) and Government of the People's Republic
of Bangladesh
Development partner - Government of India through EXIM Bank of India
Contract Value - Taka 1149,89,22,907.14
- USD 14,78,01,065.64
Type of Contract - Item Rate Contract, based on Client Consultant Design
Duration of Project - 42 Months from the date of commencement
Date of Award - 23rd Sep 2015
Date of commencement - 23th Mar 2016
Date of completion - 42 months from the date of commencement i.e. 22rd Sept 2019
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT
BANGLADESH
PROJECT INFORMATION – Broad Scope of Work
• Project Length : 64.750 Kms main & 24 Kms Loop Line and
Siding (including track of Rupsa Bridge)
• Project Limits : Take off point at Phultola (-) 0+468.062
End point at Mongla = 64+750 Kms
• Track Length : 88.75 Kms BG Track including Loop Line & Siding
• Embankment Length : 64.750 KM
• Bridges on Pile
• Major Bridges (Span > 12.20 M) : 28 Nos.
• Minor Bridge (5.50 M>Span< 12.20 M) : 3 Nos.
• RCC Cast-in-Situ Box Culverts : 111 Nos.
• Level Crossings : 22 Nos
• Manned : 9 Nos
• Unmanned : 13 Nos.
•Station Buildings :8 Nos.
•Foot Over Bridges : 3 No.s
•Total Volume of Earthwork Involved : 38,13,879 Cum.
•Total Concrete Volume : 75, 000 Cum.
•Numbers of Pile in Bridges : 1168 Nos.
• 900 mm Ø Piles : 986 Nos.
• 1000 mm Ø Piles : 182 Nos.
• Structural Steel Girders : 1751 MT
• Required Rail Length : 2,00,186 Rm
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT
BANGLADESH
PROJECT INFORMATION – Present Status
Remarks: Most hindrances are between Rupsha to Digraj ( 30 km) .Here , 30 % compensation is balance
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT
BANGLADESH
EXECUTION PLAN – SECTIONAL COMMISSIONING
Construction of Railway Line between Phultola to Mohammad Nagar (18.5 km)
by December 2018
Major Bridges : 15
Steel Girders
of 12.93m to 31.5m span : 19
Details
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT, BANGLADESH
STATUS OF WORKS
Sl. Description Original Present status Remarks
No. Planned DOC
A. PREREQUISITES
1 HAND OVER OF By 08.09.2016 Complete land is theoretically Handed over land have
HINDRANCE FREE LAND handed over on 03.11.16. several encumbrances like
Discrepancies found between structures, electrical poles,
CH 42 to 58Km. Redesign of water/ gas pipe lines, land
alignment & shifting of BR dispute etc.
ROW pillars required.
2 HAND OVER OF INITIAL By 23.03.2016 No reference pillars found at IRCON had to re establish
REFERENCE SURVEY site. the reference pillars.
PILLARS
3 ISSUANCE OF GFC By 31.03.2017 L-section for railway Multiple revisions in
DRAWINGS embankment, finalized on drawings and delay in
09.12.17. Part GFC drawings finalization of L-section
for bridges issued on hampered the earthwork
08.12.17. GFC drgs. of culverts progress.
(A2 to Mongla) not issued yet.
4 CONSULTANT’S Adequate for No one present to attend Any drawing/ design issue
MANPOWER day to day work various drawing/ design issues have to refer CEG Jaipur HQ.
monitoring & arising during execution. Consumes lot of time
attending RFIs. Manpower augmented on which otherwise could be
13.11.17. solved on spot.
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT, BANGLADESH
STATUS OF WORKS
Sl. No. Description Original Present status Remarks
Planned Date of
Completion
4a EARTHWORK FOR by 30.03.18 This 19.20Km section have Multiple revisions and
RAILWAY been divided in to two work delay in finalization of L-
EMBANKMENT Packages, Pa-8 & 7 and section hampered the
(Phultala to M.Nagar) revised planned DOC is earthwork progress.
31.10.18 Final approved L-section
for Pht-Mohd is issued on
09.11.17 & for Rupsha to
4b EARTHWORK FOR by 30.06.19 Rest (46Km + 4.9Km) section Digraj on 09.12.17
RAILWAY have been divided in to six
EMBANKMENT work Packages, Pkg- 1 to & 6 Method statement for
(M.Nagar to Mongla) and revised planned DOC is earthwork submitted on
30.09.19 14.05.17 approved on
23.11.17 .
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT, BANGLADESH
STATUS OF WORKS
Sl. Description Planned/ DOC Present status Remarks
No.
B. EXECUTION
5 Major & Minor Bridges
5a Casting of Test piles --- Out of 31 test piles, drawings Drawings for 20 bridges not
of 11 test piles issued. Latest issued yet.
issued on 18.11.17.
Casting of test pile for Br no. 8
& 13 completed. Rest 9 test
piles casting by 10.01.18.
5b Load test of test piles --- 02 test piles cast and load Approval awaited for
(Vertical & Lateral test) testing awaited. Vertical load test submitted
on 09.12.17 .Lateral load
test is not a BOQ item.
5c Foundation & sub --- GFC drawings not issued yet.
structure
5d Super structure Part GFC drawings of 04
girders issued on 08.12.17
without any General Notes.
Balance drawings of 13
girders not issued yet.
7 Culverts
7a GFC Drawings By 31.03.17 Ground Improvement drawing Now, Plate load test has been
issued on 10.08.18. & asked by CEG after sand filling to
Approved working drawing ascertain bearing capacity which
received on 08.10.17. is delaying the works further.
Foundation Ground improvement method As per given method , Min. 03
in Box culverts is required to months are required for Ground
be change as the given Improvement for box culvert in
method will delay the project. formation heights above 4 m.
8 Track/ P-way works
8a Supply of Rails By 30.10.17 Completed on 20.11.17
Supply of Sleepers By 30.03.18 Not commenced yet likely to Work was awarded by IRCON to
be commenced by 15.02.18 manufacture in June 2017 &
revised DOC 31.07.18 approval was given by BR on
15.11.17
Supply of P-way By 30.03.18 No provision for these item in BR has to urgently arrange these
Fittings IRCON’s Scope of work. items to commence track linking
revised DOC 30.06.18 works.
IRCON INTERNATIONAL LIMITED
KHULNA MONGLA PORT RAIL LINE PROJECT, BANGLADESH
REASONS FOR DELAY IN PROGRESS
EARTHWORK A number of revisions issued for L- section. Status of issuance of L-section
drawing is as below. L-Section could be freezed on 31.03.17.
Re
Issued on Item Description Drg. date Status
v.
26-12-2016 Plan & Profile CH 59.100 to 64.640Km GFC
Mongla/front of residence)
(electrical utility/water pipe
line)
THANK YOU