Professional Documents
Culture Documents
Preparing A Project Timeline: A Seven Step Process
Preparing A Project Timeline: A Seven Step Process
Timeline
A Seven Step Process
Some Basic Definitions
Time management and scheduling involve certain terms that need to
be understand.
Here are some basic definitions:
Critical Activity
An activity that has no latitude in start time and finish time. In other
words, if a critical activity does not finish by the prescribed time, the
overall project timeline will be impacted.
Critical Path
The longest path through the network (logic) diagram.
All activities on the critical path are critical activities.
Duration
The window of time within which an activity is expected to be completed.
Effort
The number of labor hours to be spent on an activity.
Float (or Slack)
Flexibility, or latitude, with regard to when a specific activity can
(or must) be worked on.
Forward Pass/Backward Pass
Techniques for analyzing the amount of float in the execution of
individual activities.
Activities with no float are referred to as critical activities.
Milestone
A point in time, typically marking an important event, usually the
completion of a project phase, a decision point, or the completion
of a major project deliverable.
Milestones are not activities; they don’t take time or consume
resources.
Network (or Logic) Diagram
The model of the proper sequence of activities.
It graphically depicts which activities must be completed
before others can begin.
Parallel Activities
Activities that can be done during the same period of
time.
Predecessor Activity
An activity that must be completed before the activity
under consideration can begin.
Series Relationship
Two activities that must be done in a particular order, that
is, one must be done before the other.
Preparing a Project Timeline: A Seven-Step
Process
There are countless ways to prepare a project schedule.
A very systematic approach is outlined in this seven-step process.
Step 1: Prepare for scheduling by identifying schedule
activities on the WBS.
Step 2. Develop the network diagram.
Step 3. Estimate preliminary activity durations.
Step 4. Calculate specific calendar dates and times.
Step 5. Identify resources, accommodate resource
limitations, and estimate final durations.
Step 6. Identify and accommodate any external constraints.
Step 7. Compare the estimated end date and the required
end date.
Creating A Network Diagram
The network diagramming process begins by defining the
relationships that exist among activities.
Some people try to skip this step and attempt to execute their
project directly from an activity list.
This is the “To do list approach.”
Although this may work for extremely small projects (20-30
activities with one or two people), it will not work on projects that
involve dozens of tasks with multiple players.
In most projects, several people are working on different activities
at the same time and many activities are dependent upon one
another, so it’s virtually impossible to manage a project from a list.
A network diagram is required.
Creating A Network Diagram
The most common graphical convention for drawing
network diagrams is the Precedence Diagramming
Method (PDM).
PDM diagrams consist of boxes that represent
activities.
The relationship between activities is indicated with
arrows.
PDM Series Relationship
Finish-to-Start relationship indicates
an activity must be completed before
another activity can begin.