Replacement of Rail Bearers
Replacement of Rail Bearers
Replacement of Rail Bearers
bridge
• Work execution
General Details
Name of bridge: Bhiwandi pipeline Bridge
Br. No: 55/2
Km: 55/35-29
Section: DW-BSR Section
B/W Station: BIRD to KOPR
Type of bridge: OWG Through span
Span : 2x45.7m
Put on Road: 1979
Work: Replacement of rail Bearers
Line- UP line
Purpose : pipeline crossing
Contractor: SP Steel Maritech Pvt. Ltd.
SR-45
Inspection outcomes
• On the basis of detailed inspection of the bridge, following major outcome has been
point out:
• As the bridge lies in the coastal region , falls under severe category of environment. Due
to this corrosion has been started in cross girder, stringer and other secondary members.
• There is loss of section found in stringer , and cross girder. Flange thickness has been
found 4-12mm & originally it is 12mm & badly corroded.
• Water pocket area has been pitted and also perforation started in some area of cross
girder and stringer.
• Diaphragm plate and batten plates of bottom chord have been badly corroded.
• As there might of chances of loss of camber in OWG , so it is decided to replace the
stringer and other member which does not affect camber , and to strengthen the cross
girder.
On condition basis , works has been started to provide overall stability
and ensure to safe passage of traffic on Bridge.
Corrosion of members
Perforation in diaphragm
Corroded rail bearers
Corroded bracing
PUT ON RD :- 1979
M
65*65*8
M
00
63
2400mm
1500mm
• Connection rivets
of rail bearers and
X- girders is to be
replaced with
turned bolts by
cutting existing
rivets for one
panel.
During block time
• Removing dog bolts
and lifting the track
with the help of jack
40 to 50 mm in the
presence of P. way
staff.
• Fixing of portal beams, chain pully blocks with slings for lifting of
girder.
ISMB 200
2 TONNE
5.6 M
W=135.52 KG
• New both side
rail bearers to
be placed on
trolly with the
help of hydra
& shift at
working site.
• Dismantling of
existing old one
side corroded rail
bearer by
removing turned
bolts from
connection of X-
girder and
removing from
bridge site by
trolly.
• Left side new rail
bearer placed in
its position with
the help of chain
pully block and
complete filled
hole with turned
bolts.
• Dismantling of existing old right side corroded rail bearer by removing
turned bolts from connection of X- girder with the help of chain pully
block and removing from bridge site by trolly.
• Right side new rail bearers placed in its position with the help of chain
pully block and complete filled hole with turned bolts.
• Fixing of bottom lateral
bracing and X-frame angles
with gussets.
• Lowering the track and fixing
the dog bolts (by p.way staff).
• Removing the
erection
derrics, portal
beams, chain
pully blocks
and block to
be cleared.
Post block activities
• Turned bolts is replaced
with rivets.
• Wooden plank staging to
be laid for the third
panel which is required
for repairing work.
Register maintained on site
• Technical register
• Safety register
• Hinderance register
• Material passing register
• Site order book
• Progress register
Technical register
Safety register
Hinderance register
Material passing register
Site order book
Progress register