Professional Documents
Culture Documents
Pat Iii: Project Scheduling
Pat Iii: Project Scheduling
Pat Iii: Project Scheduling
Project Scheduling
What is project scheduling?
Scheduling may be defined as :
Forming a network of activities and event relationships
that portrays the sequential relations between the tasks
in a project.
Placing the project and its activities in a workable
sequenced timetable.
Detailed outline of activities/tasks with respect to time
The process of converting a general plan for a project
into a time-based graphic presentation using
information on available resources and time constraints
or no answer.
Tips in Milestone goal setting: In setting
The length of the critical path is 16 months.
Since the critical path variance is 1.0 and hence path σ too
is 1 month.
We can now calculate the probability of completing the
project within above specified time limits as follows. The
probability of getting the job done:
A. Within 17 months is 50% + (1⁄2) × (68.27%), or
84.135%.
B. Within 18 months is50% + (1⁄2) × (95.45%), or 97.725%.
C. Within 15 months is 50% - (1⁄2) × (68.27%), or 15.865%.
Time-cost trade-offs (Crashing)
In some situations project organizations or
managers, may, want to reduce the length of
project by injecting additional resources. This
may be done:
To avoid late penalties
cortical path.
4. Crash critical activities, in order of
increasing costs, as long as crashing costs do
not exceed benefits
Note that two or more paths may become
critical as the original critical path becomes
shorter, so that subsequent improvements will
require simultaneous shortening of two or more
path.
In some cases it will be most economical to
300+600+800=$2700
Total indirect cost savings due to crashing=