Professional Documents
Culture Documents
HP2
HP2
HP2
Jerry Banks
Case Study: HP
Founded in 1939 Corporate headquarters in Palo Alto, Calif. 88,000 employees worldwide (as of October 31, 2001) More than 540 sales and support offices and distributorships worldwide in more than 120 countries.
2
DFM
Manufacturing engineering used to be the last stop in the product engineering process On one side were the researchers and designers who developed products that worked On the other side were the manufacturing engineers that had to determine how to manufacture the design inexpensively
5
DFM
In the 1980s, it was finally realized that product and process design were cost drivers That was the beginning of design for manufacturing
SCM
In the past few years, it has been further recognized that taking logistics and supply chain management concerns into the product and process design could result in even more efficiencies We will discuss ways to accomplish this
DFL
Design for logistics considers the following
Economic packaging and transportation Concurrent and parallel processing Postponement/delayed differentiation
10
Parallel Processing
Modularity is the key
11
Parallel Processing
Serial Processing Process A Process B Parallel Processing Process A Process C Process B
12
Process C
Postponement
Delayed differentiation Aggregate demand information is more accurate than disaggregate data
Better information for shoes than a specific style of shoe But, aggregate information is usually not of much use
13
Postponement
However, using postponement, aggregate data can be useful Design the product so that decisions can be delayed until after manufacturing is under way Delayed product differentiation
14
Postponement
First discussed in 1950 Only since 1990 have logistics researchers been defining and studying the concept Since 1995 many industries have adopted postponement as a strategy
15
Wal-Mart Version
16
17
Labeling
What type of firm might be interested in labeling as a postponement type?
A firm selling a product under several brand names
19
Packaging
What type of firm might be interested in packaging as a postponement type?
A firm selling a product under several package sizes
20
Assembly
What type of firm might be interested in assembly as a postponement type?
A firm selling a product whose cube is greatly reduced if shipped unassembled
21
Manufacturing
What type of firm might be interested in manufacturing as a postponement type?
A firm selling a product that has high sales fluctuations
22
Time
What type of firm might be interested in time as a postponement type?
Firms with high value products
23
24
Resequencing
Modifying the order of product manufacturing steps postponing those that differentiate the product as much as possible
25
Commonality
It may be necessary to redesign product lines or families to achieve commonality in order to implement a postponement strategy
26
Completion at the DC
In some cases, the final manufacturing steps can be completed at the DC instead of at the factory Advantage is that DCs are much closer to the demand than the factories
Products can be differentiated closer to the demand Increases the firms ability to respond to rapidly changing markets
27
Modularity
Differentiation takes place at the retailer after the sale Examples
Color printer is a B/W printer with an added color kit Dealer installed options when a car is purchased
Running boards and luggage racks on a SUV
28
Standardization
Replace a family of products by a standard product
Build in possible options
Example
Laptop power supply can accept 110 or 220 volts So, it can be used in Europe with a plug adapter
29
30
31
32
33
Push-pull boundary
Push systems
Production is based on long-term forecasts
Pull systems
Production is demand driven Usually reduce supply chain lead times, inventory levels, and system cost
34
Pull systems
Not always possible to implement pull system throughout the entire supply chain
Lead times may be too long May be necessary to take advantage of economies of scale
Prior to product differentiation the system is push based Then, it becomes pull based
35
Case Analysis
Inventory problem in the European DC HP faces long delivery lead times of 4 to 5 weeks from its production facility in Vancouver, WA Manufacturing takes about one week in Vancouver
36
Case Analysis
HP is concerned about inventory levels and inventory imbalance in Europe Problem is customization for local markets Localization Addition of labeling and documentation in the correct language Customizing the power supply Customization takes place in Vancouver many weeks before the products arrive in Europe
37
Case Analysis
Imbalance
The European DC often finds that it has too many PCs customized for certain markets, and too few for other markets
38
Case Analysis
Causes
Significant uncertainty about how to set the correct inventory level The many different localization options make inventory difficult to manage Long lead times lead to difficulty in forecasting and safety stock
39
Case Analysis
Causes
Uncertainty in the many local markets makes forecasting difficult Maintaining cooperation between the various HP divisions is challenging
40
Case Analysis
Cause
Significant uncertainty about how to set the correct inventory level
Possible solutions
Air shipments from Vancouver Build a European factory Hold more inventory at the European DC Improve forecasting capabilities
41
Case Analysis
Significant problems with these solutions
Air shipments
Expensive
European factory
Volume is too low to justify it
Case Analysis
Significant problems with these solutions
Improve forecasts
How?
43
Case Analysis
Another option
Postponement
Ship unlocalized printers to the European DC Localize them after observing demand
44
Case Analysis
How much savings can occur? Compute required safety stock for each of the customized products
45
Case Analysis
For Product A
For a 98% service level, z = 2.05 Safety Stock = z * STD * SQRT(L) STD = 15.6 Assume L = 5 weeks Safety Stock = 2.05 * 15.6 * SQRT(5) = 71.5 Weeks of Safety Stock = 71.5/9.8 = 7.4
46
Case Analysis
For Generic
Avg Monthly Demand = 42.3 ++306.8 = 23108.6 Std Dev Week Dem = SQRT(71.52++227.82) Compute Safety Stock and Weeks of Safety Stock as previous Illustrates that aggregate demand has a smaller variance than sum of individual demands
47
Case Analysis
Computation of savings
Carrying cost = 30% Item value is $400 Savings = .30 x (20640.0-13802.6) x $400 = $820,488
48
Case Analysis
Other savings
Value of inventory in transit is reduced, thereby reducing insurance Localization materials can be locally sourced reducing costs and meeting local content requirements
49
Case Analysis
Other costs
Product and packaging have to be redesigned so that localization can be delayed
50
Case Analysis
HP did implement such a strategy with great success
51
Supplier integration
Selection of appropriate suppliers for components of a new product Previously after completion of design
52
Supplier integration
Firms can receive benefits from involving suppliers in the design process
Reduced material cost Increased materials quality Decline in development time and cost Decline in manufacturing cost
53
Supplier integration
To reduce cycle time, focus on core competency
Outsource other business requirements
54
55
56
57
58
59
60
61
62
63
64
65
Development time
20%
67
Functionality/Features/Technology
10.0%
68
Mass customization
Evolved from two concepts
Craft production Mass production
69
Mass customization
Craft production
Highly skilled and flexible workers Highly differentiated goods Organic organizations
Trained through apprenticeships and experience Very difficult to control quality
Mass production
Efficient production of a large quantity of goods Mechanistic firms
Management places a high priority on automating and measuring tasks
70
Mass customization
Involves the delivery of a wide variety of customized goods or services quickly and efficiently at low cost Captures advantages of both mass production and craft production
71
Doing it right
Needed
Highly skilled and autonomous workers, processes, and modular units, so that managers can coordinate and reconfigure these modules to meet specific customer requests and demands
72
Doing it right
Needed
Each module must continually strive to upgrade its capabilities
A modules success depends on how effectively, quickly, and efficiently it completes its task, and how good it is at expanding its capabilities
73
Doing it right
Managements success
Depends on how effectively it can develop, maintain, and creatively combine the links between modules in different ways to meet different customers requests Depends on the creation of a work environment that encourages the development of a variety of different modules
74
Key attributes
Instantaneous
Modules and processes must be linked together very quickly This allows for rapid response to various customer demands
75
Key attributes
Costless
The linkages must add little if any cost to the process This allows mass customization to be a low cost alternative
76
Doing it right
Seamless
The linkages and individual modules should be invisible to the customer So customer service doesnt suffer
77
Doing it right
Frictionless
Networks or collections of modules must be formed with little overhead Communication must work instantly
Without taking time for team building which is so necessary in many environments
78