WP2 SGO Concentrator Project

2210 - GRINDING CONSTRUCTION SEQUENCE


GV20160942-001.pptx

© 2016 Fluor Corporation. All Rights


Reserved.
4

Tower Crane
Tower Crane
2

1 – Lean Concrete - Ball Mill # 1 Description Date


2 – Lean Concrete – Sag Mill RAS Date 17-May
3 – Lean Concrete – Ball Mill # 2 Release for Bending 17-Apr
4 – MUD Catch Basin
IFC / Release for Detailing 18-Mar
5 – Start Tower Crane Erection
6– Rev.A 25-Feb
7–
8–

JUNE 2018
2210-04-10

6 2210-03-10

2210-05-10

2 2000-02-00
2210-29-10

1 – Ball Mill #1 Mat FDN Description Date


2 – U/G Excavation RAS Date 17-May
3 – Sag Mill – Mat FDN Release for Bending 17-Apr
4 – N/A
5 – Ball Bin FDN IFC / Release for Detailing 18-Mar
6 – Ball Mill #2 – Lean Concrete Rev.A 25-Feb
7–
8–

JULY 2018
2210-01-10

8
2210-01-10

2210-01-10

5 6
3

2210-04-10

2210-03-10

2
2210-05-10

7
2210-29-10
1
2000-05-50

1.- Underground Piping/ Sewage


Description Date
2.- Ball Mill # 2 Mat
3.- Ball Mill #1 Walls (Under Slab) RAS Date 17-Jun
4.- Sag Mill Walls (Under Slab) Release for Bending 18-May
5.- Bldg FDN (H-G) / (1-6) IFC / Release for Detailing 18-Apr
6.- Bldg FDN (A-A1) / (1-6)
Rev.A 28-Mar
7.- Ball Bin FDN Walls
8.- Mud Collection Box

AUGUST 2018
2210-01-10
2210-01-10

2210-39-10
5 6
7 8
2
2210-01-10 2210-01-10
2210-04-10

1 2210-40-10

2210-05-10 4
3

2210-01-10

1.- Ball Mill #2 Walls (1st Half)


Description Date
2.- Ball Mill #1 Slab
3.- Bldg. FDN (H-G)/ (6-11) RAS Date 18-Jul
4.- Bldg. FDN (A-A1) /(6-11) Release for Bending 18-Jun
5.- Bldg. FDN (F-F1) /(1-6) IFC / Release for Detailing 19-May
6.- Bldg. FDN (B-A2)/1-6)
Rev.A 28-Apr
7.- Transformer Walls (H-G)/(1-6)
8.- Transformer Walls (H-G)/(1-6)

SEPTEMBER 2018
2210-01-10 2210-01-10
2210-01-10
2210-01-10
4 10
10
9
9
3

2210-04-10
2210-01-10
1

2210-03-10
2
5
2210-05-10 6 8
7 2210-01-10
2210-01-10
2210-01-10
2210-01-10

1.- Sag Mill Slab


Description Date
2.- Ball Mill#2- Slab
3.- Ball Mill #1 – Walls Under Bolts RAS Date 17-Aug
4.- Backfill Bldg. B. Release for Bending 18-Jul
5.- Bldg. FDN (F-F1) /(6-11) IFC / Release for Detailing 18-Jun
6.- Bldg. FDN (B-A2)/(6-11)
Rev.A 28-May
7.- Transformer Walls (H-G)/(6-11)
8..- Transformer Walls (H-G)/(6-11) & Ret Walls
9. - Transformer Slab (North)
10.Lube Rooms FDN
OCTOBER 2018
6 6

2210-01-10
1
2210-34-40
2210-04-10

5
2
2210-41-10
10
2210-03-10
2220-21-9M 2210-37-40 3
7 87
2210-05-10
2210-01-10

2210-01-10 Crane Area


EL 1678.800

1.- Ball Mill #1 – Pedestal Insert


Description Date
2.- Sag Mill – Wall / Pedestal Inserts
3.- Ball Mill #2 – Walls Under Bolts (1st Part) RAS Date 17-Sep
4.- Build Crane Area Release for Bending 18-Aug
5.Cyclone Feed Box Walls IFC / Release for Detailing 19-Jul
6.- Set Lube Rooms
Rev.A 28-Jun
7.- Transformer Slabs (South)
8.- NA
9. Structural Steel (H-F) 1st Stage
10.Set Grinding Pipe - Racks
NOVEMBER 2018
2230-03-20

E-House 6

2210-08-40
5 4
4
2210-26-60 2
2210-01-10 2210-43-20 2210-01-10
E-House

2210-05-10

Crane Area
EL 1678.800

1.-BM #1 Sole Plates and Bearing House


Description Date
2.- Structure (A-B) 1st Stage
3.- Ball Mill #2 – Wall / Pedestals / Inserts / AB RAS Date 17-Oct
4.- Transformer Slab (H-G)/ (A-B) Release for Bending 17-Sep
5.- Set E-Rooms (Ball Mill) IFC / Release for Detailing 18-Aug
6.- Structural Steel For Pebbles Conveyor
Rev.A 28-Jul
7.- Transformer Foundations (HG)
8.- Transformer Foundations (A-A1)

DECEMBER 2018
5
E-Rooms

2210-45-60
1
6
2210-08-40
2210-06-20

7
2210-07-40
2210-18-60
E-Rooms

2210-09-40

2220-15-60

Crane Area
EL 1678.800

2210-45-60

1.- Ball Mill # 1 Shell Installation


2.- Sag Mill Sole Plate / Bearing House
3.- Ball Mill # 2 Sole Plate / Bearing House
4.- N/A
5. - Flotation E-Rooms
6.- Structural Steel (B-F) North
7.- Set Transformers
8.-

JANUARY 2019
1
2210-08-40
4

E-House
2
2210-42-20

2210-07-40
2210-26-60
3
2210-09-40

Crane Area
EL 1678.800

1.- Ball Mill #1 – Leveling and Grouting


2.- Sag Mill – Shell Assembly Installation
3.- Ball Mill #2 – Shell Assembly Installation
4.- E-House (Sag Mill)
5.- (2nd Stage) Structural Steel (H-F)
6.-
7.-
8.-

FEBRUARY 2019
3
2210-08-40

6 1 2210-43-20

2210-42-20 2210-07-40

2210-09-40
2210-44-20
2210-06-20 5
7

Crane Area
EL 1678.800

1.- Sag Mill - Leveling / Grouting / Torquing


2.- Ball Mill #2 – Leveling / Grouting / Torquing
3.- Ball Mill #1– Shells Torqued
4.- (2nd Stage) Structural Steel (A-B)
5.- Access Bridge Pre-Assembly
6.- Cyclone Building
7.- Structural Steel (B-F) South
8.-

MARCH 2019
4 2210-10-40
8 1
7

2210-08-40
2210-11-40 5 2210-43-20
2210-33-40 9
2210-42-20 5 2210-25-60 2
2210-07-40

2210-09-40
2210-11-40 4 2210-10-40
2210-14-40

Crane Area
EL 1678.800
2210-06-20 6

1.- Ball Mill # 1 – Rotation Test / Brakes


2.- Sag Mill Rotation Test
3.- Ball Mill #2 Bolt Torquing
4.- Cuclone Feed Pump
5.- Remaining Steel (Sag Feed / Flotation Dist.)
6.- Balls Feed System
7.- GMD – Ball Mill #2
8.- Hydrocyclone Clusters
9. - Gantry Crane

APRIL 2019
1 2210-30-40
5
2210-24-60

6
2210-07-40

2210-36-40 2210-09-40
2210-25-60
2210-14-40

Crane Area
EL 1678.800

1.-NA
2.- Sag Mill Brakes
3.- Ball Mill #2 – Rotation and Brakes
4.-Balls Feed Systems
5.- GMD Sag Mill
6.- GMD Ball #2
7.- Gantry Crane Operational
8.-

MAY 2019
7

1.- Ball Mill #2 - Final Poles Torque


2. Sag Mill – GMD Rotor Poles
3.- Ball Mill #2- GMD Motor Poles
4.- Gantry Crane Operational
5.-
6.-
7.-
8.-
9.-
JUNE 2019
1 – Ball Mill #1 – GMD Welding Poles
2 – Sag Mill - GMD Pole Torquing / Welding Poles
3 – Ball Mill #2- GMD Pole Torquing / Welding Poles
4–
5–
6
7–
8–

JULY 2019
1 – Ball Mill #1 – Stator Ventilation System
2 – Sag Mill – Check Slip Ring Sections & Air Gaps
3 – Ball Mill #2 –GMD Welding Poles
4 –)
5–
6–
7–
8–

AUGUST 2019
2210 - GRINDING

Construction Sequence

1
2
1.-
2.- 3
3.- 4
4.- 5
5.-
6.- 6
7.-
7
8.-
8