Professional Documents
Culture Documents
03 - 3 Network Analysis - CPM
03 - 3 Network Analysis - CPM
Outputs:
Project completion time
Start and end times for each activity
Critical path: activities that must be finished on time so that
the project will be completed on time
Critical Path Analysis – Simple Example 1
LS= LF – t
f, 15
g, 17 h, 9
a, 6
i, 6
b, 8
d, 13 j, 12
c, 5
e, 9
CPM Network example 1
ES and EF Times f, 15
g, 17 h, 9
a, 6
0 6 i, 6
b, 8
0 8 d, 13 j, 12
0 5 c, 5
e, 9
CPM Network example 1
ES and EF Times f, 15
6 21
g, 17 h, 9
a, 6
6 23 i, 6
0 6
b, 8
0 8 d, 13 j, 12
8 21
0 5 c, 5
e, 9
5 14
CPM Network example 1
ES and EF Times f, 15
6 21
g, 17 h, 9
a, 6
6 23 i, 6 21 30
0 6
b, 8 23 29
0 8 d, 13 j, 12
8 21 21 33
0 5 c, 5
e, 9
5 14 Project’s EF = 33
CPM Network example 1
6 21
21
LS and LF Times f, 15
g, 17 h, 9
a, 6 0 6 21
21 6 23
21 i, 6 21 30
24 33
21
21 29
b, 8 27 33
0 8
21 j, 12
d, 13
8 21 21
21 33
21 21 33
c, 5
0 5 e, 9 5 14
21 21
CPM Network example 1
6 21
21
LS and LF Times f, 15 9 24
g, 17 h, 9
a, 6 0 6 21
21 6 23
21 i, 6 21 30
10 27 24 33
21
21 29
b, 8 27 33
0 8
21 j, 12
d, 13
8 21 21
21 33
21 21 33
c, 5 8 21
0 5 e, 9 5 14
21 21
12 21
CPM Network example 1
6 21
21
LS and LF Times f, 15 9 24
g, 17 h, 9
a, 6 0 6 21
21 6 23
21 i, 6 21 30
3 9 10 27 24 33
21
21 29
b, 8 27 33
0 8
21 j, 12
d, 13
0 8 21
8 21
21 21 33
c, 5 8 21 21 33
0 5 e, 9 5 14
21 21
7 12 12 21
CPM Network example 1
6 21
3 21
LS and LF Times f, 15 9 24
g, 17 h, 9
a, 6 0 6
3 21 6 23
4 21 i, 6 3 2121 30
3 9 10 27 24 33
23
21 29
b, 8 4 27 33
0 8
0 21 j, 12
d, 13
0 8
8 21
0 21 0 2121 33
c, 5 8 21 21 33
0 5 e, 9 5 14
7 21 21
7 12 7 12 21
CPM Network example 1
f, 15
g, 17 h, 9
a, 6
i, 6
b, 8
d, 13 j, 12
c, 5
e, 9
CPM Network example 2
te =7
te =12 2 5
te =13
te =4 te =11
4 te =8 7
1
te =7
te =11 6 te =10
3
te =10
CPM Network example 2
Legend: ES/EF
12/19 te =7
2 5
te =12
12/16 18/31 31/42
0/12 te =4
te =13 te =11
4 te =8 7
1
11/18 18/26 42/52
0/11
te =7
te =11 11/21 te =10
6
3
te =10
Example Flow Diagram with Critical Path
ES|LS|EF|LF
t2-5=7
12|24|19|31
2 5
t1-2=12
t4-5=13
0|2|12|14 t2-4=4 t5-6=11
18|18|31|31
12|14|16|18 31|31|42|42
4 t4-6=8 7
1
18|34 |26|42
t3-4=7
t1-3=11 11|11|18|18 t6-7=10
6
0|0|11|11 3 42|42|52|52
t3-6=10
11|32|21|42
CPM - Exercise 1
Consider the following network diagram. Applying
CPM, find:
the project period
activities ES and EF, LS and LF
float for each activity
the critical path
CPM - Exercise 2