“PREVIOUS SUCCESSES”
OLYMPIAD XXIII - 1984
Projections of Huge Traffic Jams /
Evaluate District compliance with Guidelines
Evaluate Typical Measures of Effectiveness
Determine Most Effective Strategies
Evaluate Cost versus Benefit
Establish Lessons Learned
Formulate Recommendations to Improve
TMP Process / Modify Guidelines
To Improve Mobility
Caltrans’ Mission Across California
8 of 15 of the Most
Congested Cities
are in California
• P ublic Information
• M otorist Information
•I
ncident Management
•C
onstruction Strategies
•D
emand Management
•A
lternate Routes
How Would You Measure the
Effectiveness of TMP Strategies?
Traffic Volume Counts,
Floating Car Runs,
Queue Lengths,
Transit Ridership,
Overall Corridor Video Surveillance ..
Personal or Mail-in
Surveys, No. of Calls or
Website Hits, Public
Public Awareness Meeting Attendance ..
Personal or Mail-in
Motorist Information
Surveys, Traffic
Observations ..
Accident Response /
Incident Management Removal Time,
Pre- / Post- Accident
Rates ..
Measurement of Effectiveness
(Cont.)
Pre-Const. Estimate
Vehicle Delay = 1,000,000 veh-hrs
Actual Delay
= 16,000 veh-hrs
Traffic Volumes Traffic Demand on
Interstate 10 was
reduced by 57% (from
112,000 to 56,000 veh)
Length of Queues Initial Estimate
= 44 miles
Actual Queue Length
= 1.9 miles
Safety
No collisions or
Employee injuries
occurred in the
Work Zone Project Characteristics
- Fast-setting Hydraulic Concrete
- Closed 2 of 4 Lanes
- Extended 55-Hour Closures
District 07 Actual Delay in Work Zone
I-10 Long-Life Pavement Project With TMP Strategies
3500
(Delay in minutes) Sat. Sun.
Projected 3000
Rte 30/Foothill Blvd. 9 2
Delay Arrow Highway 7 2
Holt Ave. 6 5 2500
Delay
1000
500
0
Mid-1 AM
Mid-1 AM
Mid-1 AM
2-3 AM
6-7 AM
8-9 AM
2-3 AM
4-5 AM
6-7 AM
8-9 AM
2-3 AM
4-5 AM
4-5 AM
10-11 AM
10-11 AM
2-3 PM
4-5 PM
6-7 PM
8-9 P M
2-3 PM
6-7 P M
8-9 P M
10-11P M
4-5 PM
10-11 P M
Noon-1 P M
10-11 P M
Noon-1 P M
TIME
511
But..
WHICH strategies
led to these
Great Results??
MOST EFFECTIVE STRATEGIES
- PUBLIC AWARENESS
“If you drive I-80, you
might want to consider
an alternate route
this morning..” “Which way
should we
go today..?”
Telecommute ..
Leave Earlier
or Later ..
Instead of saying
“Bridge Replacement
Project” --... Slogans AND Maps
are Good and
Easy to Remember..
“Improve Your Dr
ive
on the Five!”
District 04 Project Characteristics
- Full-freeway Closure
Central Freeway Replacement Project - On- and Off-Ramps Closed
- Extensive Public Info Campaign
Advance
WhatAwareness
Did theof Central
PublicFreeway Closure
Notice?
News p aper Articles 78%
TV News 63%
Freeway Sig ns 50%
Radio Traffic Rep orts 42%
Rad io News Rep orts 40% Metro Traffic
Wo rd o f Mo uth 37%
Fo ld -Out Bro chures 32%
News p aper Ad s 15%
News letters 11%
Billb oard s 10%
One--Page Flyers 7%
Banners 6%
Radio "Man in the Street" 5%
511
Other 4%
Public Meeting s 2%
Percentage
Percent Remembering
Effective Construction Strategies
- Comparative Safety? 4 Provide at least four adjacent through freeway lanes open in direction of travel
5 Provide at least five adjacent through freeway lanes open in direction of travel
S No lane closure permitted; work permitted anywhere that does not require lane closure
Remarks:
Effective Construction
Strategies (Cont.)
• CONSTRUCTION STAGING
• MOVEABLE BARRIERS
• CONTRAFLOW (“Crossovers”)
Schedule
Construction Comparison Cost Comparison ($Millions) Max.
Scenario Delay
Total Closure User Traffic (Min)
Construction Total
Closures Hours Delay Handling
72-Hour
Weekday
8 512 5.6 10.5 2.1 18.2 75
55-Hour
Weekend
10 550 14.2 12.5 2.6 29.3 196
1 Roadbed
Continuous
2 400 6.9 8.9 1.0 16.8 196
10-Hour
Night-time 220 2,200 4.9 19.1 1.3 25.3 36
District 05
Cuesta Grade Project Effective Strategies
Project Characteristics -- Demand Management
- Addition of NB / SB Truck-Climbing Lanes
- Addition of Eight-foot Shoulders
- Construction of massive Retaining Walls
313% Increase
• BUS TRIPS
City Streets
Only - 11% No Longer
Made Trip - 3%
Public Transit - 2%
Other - 2%
Freeway /
Transit - 3%
Freeway /
Streets - 2%
Different Freeway
or Ramp Route - 76% Freeway /
Fewer Trips - 1%
District 11
I-5 / I-805 Widening Project BENEFITS VS. COSTS??
Project Characteristics
“Bang for the Buck...”
- Const. Separate Freeway Bypass
- Const. of new Interchange / Auxiliary Lanes
Strategy Cost
• P ublic Information $607,500
• M otorist Information $835,000
•I
ncident Management $2,767,000
COZEEP Cost = $1,700,000
•C
onstruction Strategies ---
•D
emand Management $400,000
• A Goal - Increase Van, Carpools, Bus by 5% / Change worktime by 2%
lternate Routes $10,000
COMPARE COST VS. DELAY SAVINGS
LESSONS LEARNED
• PUBLIC AWARENESS
• Newspapers PUBLIC
• TV News Spots AWARENESS: MOST
Effective Strategies
facilitate Decision-
• ADVANCE SIGNAGE Making by Driving
Public to avoid Work
• Before Decision Points Zone
• On Preceding Weeks / Weekends
• OTHER ISSUES
• Truck Restrictions / Closures on Parallel Routes
• Cumulative Impacts due to Multiple Projects
(Combine closures when advantageous)
RECOMMENDATIONS
• PROPOSED STUDIES
• Detailed TMP Effectiveness - Costs vs. Benefits
• Full-Freeway vs. Night Closures
• Enforcement Practices (Placement, etc.)
• TMP Process
• Relationship between Project
Characteristics and TMP Strategies
• Sample Unit Costs for TMP Strategies
• TMP Strategies -- Unit cost Info
• Sample Worksheet -- Blanket TMP
• Sample Delay Calculations
Relationship between Project Characteristics
and Appropriate TMP Strategies
Motorist Information
Permanent CMS $300,000
Portable CMS $10,000
Portable CMS (Rental) $350/day, $1,500/week,
$3,500/month
Portable Highway Advisory Radio $60,000/unit
Highway Advisory Radio (Super) $70,000/unit
Ground Mounted Signs $300 each
Sample Unit Costs for TMP Strategies (Cont.)
Incident Management
K-Rail $10-15/lf
Movable Concrete Barrier (Rental) $30/lf
Movable Concrete Barrier- Transport Machine (Rental) $100,000/6 months
Gawk Screen (optional) $3/lf
Temporary Signal $30,000 each
Demand Management
Park & Ride $50/hr
Ramp Metering $50,000/location
Alternate Route
PUBLIC INFORMATION
Brochures and Mailers Cost could range between $.40 to $ .50/ brochure Variable depending on the text, graphics and presentation quality
for a large quantity. of the materials produced, numbers printed and distribution
Media Releases methods.
Cost varies with labor up to a few hours of labor/
Labor cost associated with TMP personnel interacting with media,
month. as well as time developing press releases. Cost varies with labor
up to a few hours of labor/ month.
Public Info. Center Basic cost would range from zero to $1.50 per Basic cost would range from zero to $1.50 per square foot per
square foot per month depending on the location. month depending on the location. Additional costs could include
staffing, equipment, furnishings and operating costs.
Paid Advertising The cost depends on newspaper rates in the
area, but can range between $100 to $600 for 3
column inches, one time only.
Visual Information Variable
Telephone Hotline Installation: In the range of $100 - $110 for one Installation: This does not include having the actual line installed
line (local access only). into the location).
Additional Lines: Approximately $75.00 each. Additional Lines: Approximately $75.00 each.
Monthly Fee: $20.00 plus usage (rates are
discounted if over
MOTORIST INFORMATION
CMS $35,000 to $50,000 to purchase depending upon
whether installation is permanent or portable;
$1,900 to $2,400/ month to lease in 1993 dollars.
Annual operating costs can range from $13,000 to
$22,000 (1989 dollars) per unit.
Signing and Striping Variable
CONSTRUCTION STRATEGIES
Variable Lanes Temporary concrete barriers: $15 per linear foot
Traffic cones: $10 each
Channelizers: $35 each
Lane/Ramp Closures $2,800 per direction per count location Counts may already be available in District's inventory section
TMP STRATEGIES -- UNIT COST INFO (cont.) Source: TMP Effectiveness Study (Wilbur Smith, 1993)
DEMAND MANAGEMENT
Rideshare Incentives Vanpooling incentives range from $.19 to $ .62
per vehicle using the corridor (based on ADT).
Rideshare Marketing Unknown. TMP costs do not differentiate between overall marketing costs
and rideshare marketing costs.
Park-and Ride Lots Temporary at- grade parking would cost $1,000 Variable, depending whether new lots must be acquired or built.
per space with $50/ space with annual
maintenance cost.
Transit Service $5.00/ vehicle mile.
Improvements
Transit Incentives Depends on level of incentive, up to $60/ month is
not tax- free
District County
Route Postmile(s)
No. of Lanes Affected Length of Segment
Location Description
Work Description
Initial Date / Time Ending Date / Time
Expected Duration Expected Delay (minutes)
ADDITIONAL INFORMATION
Did you prepare Lane Closure Charts? Yes No
Was “Zero delay” goal accomplished? (If not, be Yes No
sure to specify the expected delay above.)
Are there adjacent Lane Closures in the same corridor? Yes No
If Yes, what is the spacing?
Sample Delay Calculations
RTE
Location: De m and vs . Capacity
Operation: Multilane Closure 14000
ULATIVEVEHICLES
8000
Count Date: 5-3-2001
Cumulative Cumulative Queue Individual 6000
Demand Difference Area
Time Demand Capacity Length Delay
(Veh) (Veh) (Veh-Hr)
(Veh) (Veh) (mile) (minutes)
CUM
4000
6 AM 0 0 0 0 0 0.0
7 AM 5309 5309 3000 2309 1154.5 2.7 46 2000
8 AM 6945 12254 6000 6254 4281.5 7.4 125
0
6 AM
7 AM
8 AM
TIME
Max. Individual Delay: 125 minutes 0.0
Vehicle Delay Hours: 5,436 ve h-hr
De mand Capacity
Total Cost of Delay: $48,924
Delay Cost/10min: $4,077