Professional Documents
Culture Documents
Operational Readiness Report Lush Residences As of March 30, 2022
Operational Readiness Report Lush Residences As of March 30, 2022
Lush Residences
as of March 30, 2022
General Profile
A. General Information
Property Name : Lush Residences
Owner / Developer : SM Prime Holdings, Inc.
Property Address : Bagtikan cor kamagong, Brgy San Antonio, Makati City
Legend:
Ready On-going Not Ready
4
Basic Life & Safety
Basic Life Support Area Served / Status as of
Remarks
Systems Location 03-30-2022
Fire Exit 1 Testing and • Functionality of the panic door, endurance test of emergency
Inspection light, no obstruction of fire exit stairs. Close out of punchlist.
(All Floors) Requirements • On going construction
Fire Exits
Fire Exit 2 Testing and • Functionality of the panic door, endurance test of emergency
Inspection light, no obstruction of fire exit stairs. Close out of punchlist.
(All Floors) Requirements • On going construction TCD April 15, 2022
• Detectors for units are partially installed from 8th to 22nd floor
complete installation for units, partial 19th to 24th floor
Fire Detection and
• Detectors for common area are installed on ground and from
Alarm System
8th floor to 18th floor.
(Conventional with
• Functional Test of Devices (Smoke, Heat Bell, MPS,
Indicating Lights for
Testing and Annunciators, Fireman’s Telephone, Flow and tamper
units) All Floors
Inspection Switches) - not yet conducted
• Simulation Test of Interfaced System - not yet conducted
Addressable for
• FDAS Sequencing - not yet conducted
common areas except
• 2 floors up and 1 down simulation - not yet conducted
residential hallways
• General alarm automatic and manual - not yet conducted
• TCD May 6, 2020 overall completion with testing
Legend:
Ready On-going Not Ready
5
Building Equipment
Building Facilities / Area Served / Status as of
Remarks
Equipment Location 03-30-2022
Testing and
Fire Exit 1 Inspection
Requirements
• Fire exit 1- Cannot be tested due to open area on
ground to 6th floor
Testing and • Fire exit 2 - on going coordination with AB for
Pressurization Blowers Fire Exit 2 Inspection closure of all open area(7th and RD) TCD 2nd
Requirements
week of April. TCD of testing of blowers will be
Testing and
scheduled after close out of open area.
Fireman’s Lift Inspection • Elevator PB ready with minor punchlist
Requirements
Legend:
Ready On-going Not Ready
6
Building Equipment
Building Facilities / Area Served / Status as of
Remarks
Equipment Location 03-30-2022
Legend:
Ready On-going Not Ready
7
Building Equipment
Building Facilities / Area Served / Status as of
Remarks
Equipment Location 03-30-2022
Legend:
Ready On-going Not Ready
8
Building Equipment
Building Facilities / Status as of
Area Served Remarks
Equipment 03-30-2022
• Pressure testing floor -Tested with minor punchlist
• Water Lines, Sanitary and Storm Drainage Pipes done for
Water System All Floors submission of Hydrotest / Gravity Test forms
• On going functionality testing and drain flusing– simultaneously
tested with Garbage room punch listing per floor.
• Insulation / Continuity Test of Feeder Lines - For submission of
test form
• Electrical Reading - Passed
Pump Room
Transfer Pump • Flowrate (gpm) vs Dynamic Head (meter) – On going as of
(Basement)
February 16, 2022
• Functional Test of Safety Devices - Passed
• Simulation Test of System Operation - Passed
• Electrical Reading - Passed
• Flowrate (gpm) vs Dynamic Head (meter) - Done
• Functional Test of Safety Devices - Done
Ground Pump Room
• Simulation Test of System Operation Cut in and cut out failed.
Booster Pump Maximum allowable pressure that the actual motor cannot
reached the approved system pressure.
Legend:
Ready On-going Not Ready
9
Building Equipment
Building Facilities / Status as of
Area Served Remarks
Equipment 03-30-2022
Legend:
Ready On-going Not Ready
10
Building Equipment
Building Facilities / Status as of
Area Served Remarks
Equipment 03-30-2022
Service • Ready with minor punchlist(No control panel and safety overload
elevator relay)
Elevator Pit Pump Elevator Pit
Passenger 1
• Balance simulation testing
and 2
11
Permits Monitoring
Status as of
Remarks
03-30-2022