Professional Documents
Culture Documents
TPCC 15
TPCC 15
QUANTITY SURVEYING
“With GOD all things are Possible”
MATTHEW 19:26
SHORT REVIEW
Building Plans and Drawings
1. Floor Plans
2. Elevations
3. Foundation Plans
4. Beam Framing Plans
5. Column-Footing Details
6. Beam Details
7. Roofing Plans
8. Roof Framing Plans
9. Truss Detail
QUANTITY SURVEYING
This course provides a basic understanding of the methods used to prepare a cost estimate of the
following:
1. Building Construction
2. Earthworks
CONCRETE WORKS
Concrete Proportion
The most common and convenient method in proportioning concrete mixture is called:
“Volume Method”
CONCRETE PROPORTION
Mixture Class Proportion Cement in Bag Sand (cu.m) Gravel (cu.m)
(40kg)
AA 1 : 1.5 : 3 12 0.50 1.0
A 1:2:4 9 0.50 1.0
B 1 : 2.5 : 5 7.5 0.50 1.0
C 1:3:6 6 0.50 1.0
CONCRETE WORKS
Example 1.
A proposed concrete pavement has a general dimension of 10 cm thick, 3 meters wide and 5 meters
long. Determine the quantity of cement in bags, sand and gravel in cubic meters required using class
“A” mixture.
SOLUTION
V=LWh
V = 5m (3m) (0.10m)
V = 1 .5 cu. m
A rural road 6 meters wide after base preparation requires concreting of one kilometer long. Find the
number of cement bags, sand and gravel required using class “A” concrete if the slab is 6 inches thick.
SOLUTION
V=LWh
V = 900 cu.m
2. The ground floor of a residential house has an area of 200 sq. m. The plan specify 4 inches thick concrete floor on
fill using class “C” concrete. List down the materials required.
3. A concrete wall, 3 inches thick with general dimensions of 3 meters high by 7 meters long specify class “B”
mixture. List down the materials required.
4. A reinforced concrete square column is 5 meters long with a cross sectional dimensions of 16 inches by 16 inches.
Determine the quantity of cement, sand and gravel using class “A” concrete.
5. A concrete column 4 meters high with cross sectional dimensions of 40 cm. x 40 cm. is supported by a footing slab
20 cm. thick by 1.20 meters square. Using class “A” concrete, find the quantity of cement, sand and gravel if there
are 12 columns of the same size.
MASONRY
Concrete Hollow Blocks (CHB)
1. Load Bearing Blocks – the thickness ranges from 15 to 20 cm and are used to carry load aside from
its own weight.
2. Non-load Bearing Blocks – these are intended for walls, partitions, fences, dividers and the like
carrying its own weight whose thickness ranges from 7 to 10 cm.
STANDARD HOLLOW BLOKCS
The standard hollow blocks has three void cells and two half cells at both ends having a total of four.
These hollow cells vary in sizes depending to the type of mold used by the manufacturers.
It is recommended that CHB with bigger cells be considered in estimating for a more realistic result.
ESTIMATING CHB
Area Method - The most convenient and simplest way in estimating concrete hollow blocks.
A concrete hollow block wall has a general dimension of 3.5 meters high by 4 meters long. The wall
should be plastered finished. Determine the number of CHB, cement and sand required to construct the
wall.
SOLUTION
A = 3.5 m (4 m)
A = 14 sq. m
CHB = A x 12.5
CHB = 14 (12.5)
Note: an allowance of 5% is necessary to cover the breakage during delivery and construction.
V = 0.57 cu. m
Estimating Plaster:
V = 0.36
A firewall is to be constructed. Determine the number of CHB, Cement and Sand needed for the
construction.
METAL REINFORCEMENT
Steel bars
most widely used reinforcing materials for almost all types of concrete construction.
An excellent partner of concrete in resisting both tension and compression stresses.
The National Building Code has promulgated guidelines on how and what kind of reinforcement is
appropriate for a certain type of work depending upon the purpose for which it is to serve.
CONCRETE HOLLOW BLOCK
REINFORCEMENT
This is the simplest type of vertical and horizontal reinforcement placed in between the layers and
hollow core of the blocks.
This type of reinforcement is installed and spliced progressively with the rise of the concrete blocks.
The size and spacing requirements for concrete hollow blocks reinforcement must be indicated on the
plan or specifications.
CONCRETE HOLLOW BLOCK
REINFORCEMENT
Area Method – is the simplest approach in computing the steel bar reinforcement for CHB.
60 2.15 3 2.15
CONCRETE HOLLOW BLOCK
REINFORCEMENT
Example 1.
h = 4 meters
L = 5 meters
A= 5 mx 4 m
A = 20 sq. m
A = 20 sq. m
Note:
Always check the specification of the reinforcement stated in the plan.
h = 3 meters
from finished
floor line.
COLUMN-FOOTING
REINFORCEMENT
Solution
Estimating Column reinforcement:
h = 3 m + 1 m + 0.20
h = 4.20 m or 6 m
Size of each Lateral Ties = [ 200 mm – 2 (40 mm) ] x 4 sides = 480 mm or 500 mm
= 3.17 or 4 bars
No. 16 G.I. Tie Wire for Column
and Footing Reinforcement
Steps in Estimating tie wire for column and footing reinforcement:
Count the number of intersections
Number of intersections x 30 cm (length of tie wire) = Total length of tie wire needed
Tie wire =
Number of Intersections = 5 x 5 = 25
Tie wire =
A one way slab having the ff. dimensions: L = 5.70 m, W = 5.50 m. Estimate the number of 12 mm
dia. Bars and the quantity of tie wire if the bar spacing is 200 mm on center both ways.
Solution:
A = 5.70 m (5.50 m)
A = 31.35 sq. m
One Way Slab Reinforcement
Number of 12 mm bars = A x 1.980
A Two way slab having the ff. dimensions: L = 7.20 m, W = 7.20 m. Estimate the number of 12 mm
dia. Bars and the quantity of tie wire if the bar spacing is 175 mm on center both ways.
Solution:
A = 7.20 m (7.20 m)
A = 51.84 sq. m
Two Way Slab Reinforcement
Number of 12 mm bars = A x 2.647
Concrete mixture is generally semi-fluid that reproduces the shape of anything into which it is poured.
Forms
Greasing of Forms
Forms are constantly greased before its use. The purpose of greasing the form is to make the wood
waterproof preventing the absorption of water in the concrete which causes swelling and warping.
Crude oil is the most economical and satisfactory materials for this purpose. The crude oil is mixed
with no. 40 motor oil.
Forms
Types of forms/ framework to be adopted
b) Stud type
Forms
Plywood as Construction Form
Six concrete column at 3 meters high with a uniform cross sectional dimensions of 0.30m x 0.30m.
Estimate the use of marine plywood and 2”x2”x10’ wood frame using a continuous rib type forms.
Forms
Solution:
P = 2 (a + b) + 0.20 m
P = 1.40 m
No. of Plywood =
Forms
Estimating number of 2”x2”x10’
10 feet = 3 meters
A reinforced concrete building has 9 columns with a clear height of 4.00 meters as shown on figure.
Determine the required scaffolding under the following specifications: 2” x 3” vertical support; 2” x 2”
horizontal and diagonal braces.
Scaffolding
Solution:
1. Scaffolding for Columns