RAN-PRJ-102 Phase-2 MOCN Trial Assessment - PEW Application - 20220817

You might also like

Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 8

RAN-PRJ-102 MOCN Trial

Phase-2 Trial
Background & Progress

Background
 In MOCN active sharing has benefits of Spectrum pooling and higher efficiency.
Enhance the revenue to utilize the Existing Spectrum with sharing.
 Activity involve two PEW’s.

Progress
Initial Trial configuration is schedule on 25-Aug-2022 & 26-Aug-2022

Type Total Site Action Done Remain Progress Complete Date Status
LTE 2 0 2 0% 2022/09/25 Planned
LTE 1 0 1 0% 2022/09/26 Planned
Schedule of Active MOCN Trial

RequestOperation
1. MOCN Trial Schedule with action

 SN Weeks(Date) CR/PEW CR W33 W34 W35 W36 W37

  PEW Activity item          
PEW Submission: IP Removal from old site(SHS00466) & IP config to new site (YGN02177)-
1
LTE
PEW        
PEW implementation: IP Removal from old site(SHS00466) & IP config to new site
2
(YGN02177)-LTE
3 KPI Monitoring        
4 CR IP Ping test Parameter change CR        
5 Implementation Ping Test Parameter

6 KPI Monitoring

7 PEW Submission: MOCN Configuration and activation for New Site (YGN02177) PEW

8 PEW Implementation: MOCN Configuration and activation for New Site (YGN02177)

9 KPI Monitoring        
10 Testing and functionality check

Completed Planned Note: Assume that W34 we will get approval and W35 we will implement
the MOCN
Activities Summary
Project RAN-PRJ-xx MOCN Trial
Purpose MOCN Activation on 1 Site ( YGN02177) with MPT and OML & Parameter change on 2 sites ( SH00466 &
YGN02177)
PO FOC PO issue MPT MA
Change of Operation Implement by HW, the PEW application owner is HW and approver is MPT MA.
And person
Supervisor (MPT), Thet tun Oo (+66 867823051) PIC1(MPT) : Adil Murad (Ph:+95 9795644746 )
PIC1(HW) : Aung Bo Bo (Ph:+95 9768768548) PIC2(HW) : Wai Yan Myint (Ph: +95 9250011911)
Operation Date 25-Aug-2022 & 26-Aug-2022 Time 00:00 ~ 06:00  
Service Impact Have
Office access No Need. (Remote Access for implementation )
 Activities are Plan in 2 Batch 2 CRs.
Service Impact
Target CR Target
Order System Target Area Activities Operation time
Date Number site Have Time

LTE: IP Removal for old site


IP Configuration 25-Aug CR-7392 LTE SHS/YGN 2 SHS00466 & IP config for New Yes 3M 00:00 ~ 06:00  
site(YGN02177 )
LTE : MOCN Configuration and
MOCN Activation 26-Aug CR-7394 LTE YGN 1 Yes 3M 00:00 ~ 06:00  
MOCN activation

Note: Operation time 00:00 ~06:00 preferred but in case any issue then suggest support as per
actual situation.
Risk Assessment
<Background>
To Complete the MOCN Trial we have to do configuration change on 1 Trial site and to perform this activity we need to Remove
the IP from Old site (SHS00466) and configure IP to new site YGN02177 in order to evaluate the trial results we need to raise PEW’s
schedule on 25-Aug-2022 & 26-Aug-2022.

Sr Risk Assessment Possibility Service Impact Countermeasures


1 Any risk of site down? Medium Risk Medium 1) In case of failure, rollback the script.
(1~3 Minute /Site service 2) In case of internet connection issue, operation will be
interruption, cell reset) & hold
cell service will resume
back to normal
2 Any risk need to go to No Risk Low Risk impact N/A
site ?
3 If need to go on-site, NA N/A 1) In case of remote desktop access issue, operation will
who is the PIC? be canceled.
2) In case of internet cut issue on PIC1, PIC2 will be
perform.

Note: Even we are going to deployed the MOCN, capacity will be shared to OML and MPT.
Responsibilities Matrix for MOCN Trial

Activity Sub-Activity Action Point HW RF HW WL MPT MA


PEW Application R I A
Old site IP removal and New Site
IP Configuration PEW Implementation R R I
IP Configuration
KPI monitoring R I I
PEW Application R I A
MOCN License Distribution and PEW Implementation R R I
Activation Parameter change Test and Verification R I I
KPI monitoring R I I

R: Responsible, A: PEW Approval, I: Inform, S: Support


MOCN Trial PEW summary

R: Responsible, A: PEW Approval, I:


Inform, S: Support

Network Service Impact MPT


Activity Sub-Activity Action Point Tentative Date Activity Time Service Impact WH RF HW WL
Access Duration MA
PEW Application 17-Aug-22 00~06 Remote No   R I A
Old site IP removal and New Site
MOCN Trial PEW Implementation 24-Aug-22 00~06 Remote Yes 3 min per site R R I
IP Configuration
KPI monitoring 24-Aug-22 00~06 Remote No   R I I
PEW Application 12-Aug-22 00~06 Remote No   R I A

MOCN License distribution & PEW Implementation 26-Aug-22 00~06 Remote Yes 3 min per site R R I
Activation Configuration change at RAN Test and Verification 26-Aug-22 00~06 Remote No   R I I
KPI monitoring 26-Aug-22 00~06 Remote No   R I I

Standby Team (Huawei/MPT MA) confirmation


1. [H]Supervisor – HW-RF/ HW-WL /R&D
2. [MPT]Supervisor – NA
Note: HW- RF Team will monitor KPI from existing U2020/PRS as per normal operation workflow.
End