Professional Documents
Culture Documents
Competitive Bid
Competitive Bid
procedures
ICB: International competitive bidding
NCB: National competitive bidding
LCB: Local competitive bidding
Invitation to bid
Scope of work
Language of the bid.
Bid currencies.
Bid security.
Bid validity period.
Price preference
Signing of Agreement
Commencement of work
Liquidated damages
Variation
Retention money
Advance payments
Escalation
Day works
Provisional sum
Tender notices are published in at least three national
newspapers in case of NCB, local newspapers incase of LCB and
three international publications in case of ICB.
The ADB insists on ICB for contracts valued in excess of US $500,000 for
goods and us S 1.000,000 for civil works.
For the WB, the limits are US $200,000 for goods and US $10 million for
works. In suitable cases, which are not frequent, a relaxation may be
allowed.
The GOI rules suggest an open tender system whenever the purchase value
is Rs. 50,000.00 or more. Purchases through approved suppliers with whom
Government of India has entered into long-term supply contracts known as
rate contracts also fall in the category of open bids. The rate contracts
come into force through open unrestricted competitive bidding.
The WB and the ADB allow domestic competitive bidding if the likely value
of the purchase transaction is below the monetary limit for ICB.
Limited Tenders
The GOI has laid down that limited tenders should generally be invited only
where the purchase value is up to Rs. 50,000.
Language of the bid.
For example, if a bid is accepted for, say, US dollars 1000, and the rate of
exchange on the date of opening bids is Rs. 45 to one US dollar, the
purchase transaction is valued at Rs. 45,000. However, when the buyer
pays for the goods, it may have to buy US dollars for a higher amount of,
say, Rs. 46,000 if the US dollar is quoted at Rs. 46 to a dollar.
The buyer has accepted the exchange risk in this case. If a bidder is to
quote in rupees, it may either not agree to this, or may quote a rate based
on a likely future rate of exchange when the payment would fall due.
Price Preference
The price preference is 7.5 per cent for domestic works for
both the World Bank and the ADB.
Performance Security.
NCB
In the form of BG of the amount of 5% of contract price , to
be submitted within 21 days of receipt of the LOA.
To be returned within 28 days from the expiry of defect
liability period
Signing of Agreement.
Commencement of Work.
The engineers notice to commence the work to be issued
within 35 days after the LOA or 7 days after signing of the
contract agreement, whichever is earlier.
At the rates and prices set out in the BOQ of contract, if applicable
The rates and price of the BOQ items shall be the basis if found
reasonable/ applicable from similar items.
The agreed rate between engineer and the contractor after due
consultation if above are not applicable.
If, in the opinion of the Engineer, any BOQ tem rate becomes
inappropriate or inapplicable owing to the quantum of variation due to
reason of the nature and amount of any varied work in relation to the
nature or amount of the whole of the work or any part thereof… then a new
suitable rate shall be agreed between the engineer and the contractor
after due consultation with the client.
But change in the quoted rate of the BOQ item shall be considered only if
(i)The BOQ item amount is more than 2% of the contract price
(ii)The quantities exceed or fall by 25% or more
If overall variation due to the varied work and all payments on BOQ
( except provisional sums, day work and escalation exceeds by more than
15% of the contract price , a sum either agreed or determined by the
engineer shall be added to compensate for the increase in O/H , equipment
etc. The addition will be based only on an amount in excess of the above
15%.
In NCB for changing the quoted rate of the effected item, its quantity
must change by 25% or more, and the cost of the change should exceed 1%
of the contract price.
Retention Money
6% of IPC( interim payment certificate) starting from the 1st IPC till its
totals to 5% of the contract price (Limit)
The full amount once realised can be replaced by the unconditional BG.
One half (50%) of the total money so retained shall be certified for
payment by the engineer after the issue of the taking over certificate.
The other half (50%) shall be certified after expiration of the defect
liability period.
Part of the retention money can be withheld depending upon the
requirement at the different stages of repayment to cover any eventuality
in the defects liability etc.
Escalation
Price adjustment for Escalation shall apply only for work out within the
stipulated time and within the extension period.
Price adjustment after the period stated above and the delay being
attributable to the contractor but extension, still granted , shall made
either using the indices at the completion time or those current at the
time he should have theoretically completed the work, whichever is
favorable to employer.
In applying price adjustment formulae percentage of various components
have top be fixed by the client.
Currency conversion has to be taken into account.
Dayworks
The contractors unit rates for different categories of labour and for
material and equipment inputs are provided by him in the relevant part of
BOQ to cover the eventualities of any ( other than BOQ) works to be got
done by him on daywork basis.
The theoretical amount for virtual quantities specified for this purpose in
the tender, are worked out and accounted for in the variations of tenders/
bids at bid evaluation time
Escalation on days work not payable if costs paid against actual vouchers
and costs each time such work called for and executed.
No escalation payable on such woks as these are paid against actual costs
and vouchers.