Construction Plan Cooling Tower Pad-1 R&D Center
Construction Plan Cooling Tower Pad-1 R&D Center
2020. AUGUST.
Proposed by Approved by
Method of
2 Open Cut
Work
Schedule
4 Sept 1st – Oct 20th 2020
Concrete
SITE PLAN
Specification f’c = 10 MPa (LC) Slump 12+-2
5 Material f’c = 25 MPa (Structure) Slump 12+-2
All steel reinforcement, fy = 420 Mpa
Supplier Material :
PT. Hanwa Indonesia (Steel Bar Material)
PT. Graha Konstruksi Perkasa (Forming Material)
PT. Merak Jaya Beton (Concrete Material) ■ Photo Location
Subcontractor & Subcontractor :
7 Supplier PT. PBS (Exavation Work)
CV. Budi Jaya (Steel Bar Work)
PT. Graha Konstruksi Perkasa (Forming Work)
CV. Annisa Jaya Hasanah (Concrete Work)
Target
9 On Schedule
Progress
COOLING TOWER PAD-1
- Dimension of the Coling Tower Pad-1
according to shop drawing.
- Level of the Coling Tower Pad-1 according to
10 Target Quality shop drawing.
- Compressive strength of the concrete
according to the spesification.
Proposal By Approved By
PT. TAKENAKA INDONESIA
CONSTRUCTION SCHEDULE OF R & D STRUCTURE BUILDING HMMI PROJECT ReV : 04 Date : 6 July 2020
Period 2020
MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER
Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
Parapet Wall
SHOP DRAWING Takenaka Submit Pile Shop Drawing RC Shop Drawing RC Shop Drawing
HEIN Approved
HEIN HEIN HEIN
Kolom & Roof Top
PROCURMENT MATERIAL PROCUREMENT PROCUREMENT MATERIAL
26 Aug 5 Sept 15 Sept Water Proofing &
Casting-1 Casting-2 Curing
Casting-2 Conc. Protection
Staircase 3 ~
Roof Slab
Roof Slab FL
Column 3FL
Column 2FL
Roof Slab
Staircase 29 Jul 8 Aug 18 Aug
D. CONSTRUCTION Casting-1 Casting-2 Casting-3
Roof Slab
Slab 1 FL
PIT Elevator 2 weeks for
curing
PIT Dynamo
Project Manager
Irwan Sofwan
Chief Operational
Rahmat Eko
CONSTRUCTION
STEP
1. SETTING OUT
2. EXCAVATION 8
8
3. BASE IMPROVEMENT
(Premix, Base Coarse, Lean 1
Concrete) 1 1
1
4. CONCRETE 6 6
SLAB
6
5. CONCRETE
WALL 2 5 5
5
2
7 4
6. CONCRETE 7
TOP SLAB
RC WORK
FINISHING 3
7. WATER WORK
PROOFING
8. BACKFILL
■ COOLING TOWER PAD-1 _ Plan of Execution HMMI Project In Indonesia
■ General Schedule
September October
Description
1 2 3 4 1 2 3 4
Cooling Tower Pad-1
Setting Out
Excavation
Basecoarse and Lean Concrete
Forming Slab
Rebar Slab
Water Stop Wall
Concrete Slab
Forming Wall
Rebar Wall
Concrete Wall
Forming Demolishing
Top Slab Forming and Rebar
Concrete Top Slab
Backfill Compaction
Finishing
Foundation Pad
Erosion Protection
A C A Safety
Fence
Work Access
Volume
Temporary
Excavation= 472.18 m³
Access for
Worker B B FL -3350
4 Quantity of Work
Excavator 1 1 Excavator 1 1
Helper 1 1
Total 3 3
□ COOLING TOWER PAD-1 _ Concrete Slab HMMI Project In Indonesia
Work
Access
Safety
Volume Fence
Concrete Slab
Temporary = 6.87 m³
Access for
Worker
Erosion
Safety Fence Protection
Sump
Pit
Sump Pit
5 Quantity of Work
Work
Access
Safety
Fence
Volume
Temporary Concrete Wall
Access for
Worker
= 12.95 m³
Erosion
Safety Fence Protection
Sump
Pit
Sump Pit
5 Quantity of Work
Work
Access
Safety
Fence
Volume
Temporary Concrete Top
Access for
Worker
Slab
= 4.55 m³
Erosion
Safety Fence Protection
Sump
Pit
Sump Pit
5 Quantity of Work
1 Waterproofing 2 Backfill
Backfilling Work
Outside
Compaction @300 mm
PARATEX
WATERPROOF