SITE CONSTRUCTION PLAN

COOLING TOWER PAD-1 R&D CENTER


- Excavation (Open Cut)
- Base Improvement
- Concrete Slab
- Concrete Wall
- Concrete Top Slab
- Waterproofing & Backfill

2020. AUGUST.
Proposed by Approved by

HMMI Project In Indonesia


■ Outline Project HMMI Project In Indonesia

1 Name of Work Cooling Tower Pad-1 R&D Center ■ Site Plan

Method of
2 Open Cut
Work

3 Location Kawasan Industri GIIC

Schedule
4 Sept 1st – Oct 20th 2020

Concrete
SITE PLAN
Specification f’c = 10 MPa (LC) Slump 12+-2
5 Material f’c = 25 MPa (Structure) Slump 12+-2
All steel reinforcement, fy = 420 Mpa

Supplier Material :
PT. Hanwa Indonesia (Steel Bar Material)
PT. Graha Konstruksi Perkasa (Forming Material)
PT. Merak Jaya Beton (Concrete Material) ■ Photo Location
Subcontractor & Subcontractor :
7 Supplier PT. PBS (Exavation Work)
CV. Budi Jaya (Steel Bar Work)
PT. Graha Konstruksi Perkasa (Forming Work)
CV. Annisa Jaya Hasanah (Concrete Work)

Target
9 On Schedule
Progress
COOLING TOWER PAD-1
- Dimension of the Coling Tower Pad-1
according to shop drawing.
- Level of the Coling Tower Pad-1 according to
10 Target Quality shop drawing.
- Compressive strength of the concrete
according to the spesification.

11 Target Safety - Zero Accident


■ GENERAL SCHEDULE R&D CENTER HMMI Project In Indonesia

Proposal By Approved By
PT. TAKENAKA INDONESIA
CONSTRUCTION SCHEDULE OF R & D STRUCTURE BUILDING HMMI PROJECT ReV : 04 Date : 6 July 2020

PT. Takenaka Indonesia PT. HEIN GLOBAL UTAMA

Period 2020
MARCH APRIL MAY JUNE JULY AUGUST SEPTEMBER OCTOBER
Description 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

STRUCTURE WORK SCHEDULE : 5.5 Months


R & D BUILDING
STRUCTURE WORK Start of Work Completion Completion Completion
Holiday Completion
8 May 2020 2nd Floor 3 rd Floor Roof Slab
Construction
A. PRELIMINERIES Prelimineries 1 October, 2020
Based on LOA
16 mARCH 2020
B. LOA Completion
C. DESIGN
STRUCTURE DESIGN STRUCTURE DRAWING 1st Floor
April 30 May 6 May 8
PILE DESIGN Takenaka Submit TAK DESIGN Structural
Pile Cap &Column Detail Design
HEIN Approved HEIN Design Tak Design Tak Drawing
May 14
RC DESIGN Takenaka Submit RC Design HEIN Approval
HEIN Approved HEIN

Parapet Wall
SHOP DRAWING Takenaka Submit Pile Shop Drawing RC Shop Drawing RC Shop Drawing
HEIN Approved
HEIN HEIN HEIN
Kolom & Roof Top
PROCURMENT MATERIAL PROCUREMENT PROCUREMENT MATERIAL
26 Aug 5 Sept 15 Sept Water Proofing &
Casting-1 Casting-2 Curing
Casting-2 Conc. Protection

Staircase 3 ~
Roof Slab
Roof Slab FL

Column 3FL

12 Aug 22 Aug 1 Sept


Casting-1 Casting-2 Casting-3

Slab 3FL Staircase 2~3 FL

Column 2FL
Roof Slab
Staircase 29 Jul 8 Aug 18 Aug
D. CONSTRUCTION Casting-1 Casting-2 Casting-3
Roof Slab

3 FL Fab Re-Bar Fab Re-Bar Slab 2FL Staircase 1~2 FL


2FL

Fab Forming Fab forming Column 1 FL


1FL
Excavation Excavation Foundation 30 Aug 5 Sept
15 Sept
Delivery Pile 131 pts Delivery Pile 25 pts Casting 1 Casting 2
Stake Out Casting 2
Pile Driving ( 131 pts) Driving 25 pts

Slab 1 FL
PIT Elevator 2 weeks for
curing
PIT Dynamo

Road base arround R & D Building Concrete Pavement R & D Building

Cooling Tower Pad


■ ORGANIZATION CHART HMMI Project In Indonesia

Senior Project Manager


Ridwan Widyana

Project Manager
Irwan Sofwan

Chief Operational
Rahmat Eko

Safety Engineer Task Engineer Quality Control Surveyor Mechanic Logistic


Arif Budiman Haris Teresa Adlin Arifin Muharom Sabdo Sidiq
Trijoko Jimmy Dani Prayoga
Herwin Purnomo Kornelius Purba
Agus Arief
Ast. Surveyor
Furqon

Forming Metal Smith Steel Bar Scaffolding Concrete Pouring


PT.GKP CV. APJ CV. Budi Jaya CV. FGB CV. AJH

Concrete Pump Finishing Concrete Supplier


PT. Indosarana PT. Intra Floor PT. Merak Jaya Beton
■ COOLING TOWER PAD-1 _ CONSTRUCTION PLAN HMMI Project In Indonesia

CONSTRUCTION
STEP

1. SETTING OUT

2. EXCAVATION 8
8

3. BASE IMPROVEMENT
(Premix, Base Coarse, Lean 1
Concrete) 1 1
1

4. CONCRETE 6 6
SLAB
6
5. CONCRETE
WALL 2 5 5
5
2
7 4
6. CONCRETE 7
TOP SLAB
RC WORK

FINISHING 3
7. WATER WORK
PROOFING

8. BACKFILL
■ COOLING TOWER PAD-1 _ Plan of Execution HMMI Project In Indonesia

■ General Schedule
September October
Description
1 2 3 4 1 2 3 4
Cooling Tower Pad-1

Setting Out
Excavation
Basecoarse and Lean Concrete
Forming Slab
Rebar Slab
Water Stop Wall
Concrete Slab
Forming Wall
Rebar Wall
Concrete Wall
Forming Demolishing
Top Slab Forming and Rebar
Concrete Top Slab
Backfill Compaction
Finishing
Foundation Pad

■ Specification of Cooling Pit


Item Spesification
Pit Size 9.30m (L) * 3.50m (W) * 3.10m (H)
Footing : 0.40 m,
Thickness
Wall : 0.30 m
Volume excavation 472.18 m³
Concrete Floor : 6.87m³, Wall: 12.95m³
□ COOLING TOWER PAD-1 _ Excavation Work HMMI Project In Indonesia

1 Safety Facility 2 Method of Work

Erosion Protection

A C A Safety
Fence
Work Access

Volume
Temporary
Excavation= 472.18 m³
Access for
Worker B B FL -3350

4 Quantity of Work

Safety Fence Volume Excavation = 472.18 m³

Handrail Blue Sheet


A C A Horizontal pipe 2”= 20 pcs @6000 A= 3.35 m x 4.75 m = 4 lbr
Vertical pipe 2 = 24 pcs @2000 B= 9.20 m x 4.75 m = 2 lbr
Clamp = 48 pcs C= 5.20 m x 4.75 m = 2 lbr

5 Manpower & Machinery


3 Schedule
Item Manpower Sept Oct Item Machinery Sept Oct

Excavator 1 1 Excavator 1 1

Dump Truck 1 1 Dump Truck 1 1

Helper 1 1

Total 3 3
□ COOLING TOWER PAD-1 _ Concrete Slab HMMI Project In Indonesia

1 Work Squences 2 Safety Facility 3 Method of Work

Work
Access

Safety
Volume Fence
Concrete Slab
Temporary = 6.87 m³
Access for
Worker

Erosion
Safety Fence Protection
Sump
Pit
Sump Pit
5 Quantity of Work

Volume Concrete = 6.87 m³


Forming Floor = 8.28 m²

6 Manpower & Machinery


4 Schedule
Item Manpower Sept Oct Item Machinery Sept Oct
September October
Item Concrete 4 4 Crane 1 1
1 2 3 4 1 2 3 4
Coolant Forming 1 1 Vibrator 1 1
TOWER
PAD-1 Rebar 1 1
Slab Work
Total 6 6
□ COOLING TOWER PAD-1 _ Concrete Wall HMMI Project In Indonesia

1 Work Squences 2 Safety Facility 3 Method of Work

Work
Access

Safety
Fence
Volume
Temporary Concrete Wall
Access for
Worker
= 12.95 m³

Erosion
Safety Fence Protection
Sump
Pit
Sump Pit
5 Quantity of Work

Volume Concrete = 12.95 m³


Forming Wall = 102.6 m²

6 Manpower & Machinery


4 Schedule
Item Manpower Sept Oct Item Machinery Sept Oct
September October
Item Concrete 4 4 Crane 1 1
1 2 3 4 1 2 3 4
Coolant Forming 1 1 Vibrator 1 1
TOWER
PAD-1 Rebar 1 1
Wall Work
Total 6 6
□ COOLING TOWER PAD-1 _ Concrete Top Slab HMMI Project In Indonesia

1 Work Squences 2 Safety Facility 3 Method of Work

Work
Access

Safety
Fence
Volume
Temporary Concrete Top
Access for
Worker
Slab
= 4.55 m³

Erosion
Safety Fence Protection
Sump
Pit
Sump Pit
5 Quantity of Work

Volume Concrete = 4.55 m³


Forming = 6.44 m²

6 Manpower & Machinery


4 Schedule
Item Manpower Sept Oct Item Machinery Sept Oct
September October
Item Concrete 4 4 Crane 1 1
1 2 3 4 1 2 3 4
Coolant Forming 1 1 Vibrator 1 1
TOWER
PAD-1 Rebar 1 1
Top Slab
Work Total 6 6
□ COOLING TOWER PAD-1_ Waterproofing & Backfill HMMI Project In Indonesia

1 Waterproofing 2 Backfill

Backfilling Work
Outside
Compaction @300 mm

PARATEX
WATERPROOF

5 Manpower & Machinery


5 Schedule
Item Manpower Oct Item Machinery Oct
September October
Item Excavator 1 Excavator 1
1 2 3 4 1 2 3 4
Coolant Dump Truck 1 Dump Truck 1
TOWER
PAD-1 Opr. Baby Roller 1 Baby Roller 1
Waterproof-
ing & Back-
fill
Total 3