www.pwc.

com

UPPDRP
Uttar Pradesh Power Distribution
Rehabilitation Project

Strictly private
and confidential
PuVVNL & MVVNL
Daily Project Report Dated
28.07.2022

1
Key issues- PuVVNL

Owner Point to discuss

1. TKCs to complete all the erection work under UPPDNRP project within scheduled project timeline i.e., till July-22.
Any delay in project completion beyond scheduled timeline shall entirely be the responsibility of the TKC & LD may
be imposed as per terms & conditions of the contract.
TKCs
2. TKCs to upload actual material & erection progress on portal.

3. TKCs to also submit the actual invoice details on portal.

1. PMA to submit habitation wise analysis on pending majras to be completed by TKC. In consultation with TKCs &
Discom, PMA shall submit the weekly completion plan for remaining habitations.
PMA
2. PMA shall submit the Site Observation Report including status of quality of work maintained at site & analysis on
non-compliances reported at site & rectification done by TKCs. PMA shall ensure that quality of work is maintained at
site.

2
Key issues- PuVVNL

Owner Point to discuss


1. Discom to provide the habitations details with population between 500-999 and more than 1000 population. Discom has informed
to share the details by 27/07/2022.

2. Discom to share the details of 6th Quarterly Progress Report (QPR). Discom has informed to share the details by 27/07/2022.

3. Discom need to submit the impact due to penalty clause conditions in the contract. Discom has informed to share the details by
27/07/2022.
4. Discom to appoint auditors for audit of Annual Project Financial Statements (APFS). Discom has informed that the auditor shall
be appointed by 29/07/2022.

5. Discom need to submit the details of TKC payment in process at various stages at Discom level. Discom has informed to share
the details by 30/07/2022.
6. What is the status of project completion & contract extension if any?
Discom
7. What is the status of BG to be recovered?

8. Discom shall ensure that JMC certification, Completion Certificates & Operation Acceptance Certificate are approved without any
delay after completion of habitations. The TKC wise estimated amount of payments that can be claimed against the pending
JMCs is enclosed in Annexure-I.

9. The Discom officials need to conduct site visits to ensure quality and report the findings to UPPCL on weekly basis. (ref UPPCL
letter no. 2807 dated 17.08.2022). Discom to ensure that the TKCs are maintaining the quality of works as per the standards and
specifications defined in the contract. The Discom/PMA should also ensure that same type of NCs are not repeated by the TKCs.

10.Discoms to share the revised BOQ as actual requirement of material at site. It is found that there is major difference in required
quantities for some packages.
3
Status of Asian Development Bank Funded “Uttar Pradesh Power Distribution Network Rehabilitation Project”
Purvanchal Vidyut Vitran Nigam Limited - Varanasi
Major Material Supply Progress Status
Pole Stock-in Progress as per portal Cable Stock-in Progress as per portal
Total AB
Poles (Nos) Pole
Workable Cable (Km) Cable
TKC Zone Habitations found Stock-in Stock-in %age progress Stock-in %age progress as
Today’s Stock-in Cable Today’s
after survey Pole Pole Stock-in as per Cable Stock-in per site
progress site Yesterday progress
BOQ Yesterday Today Pole BOQ Today Cable

NCC Ltd. Azamgarh 1469 20532 18929 18929 0 92% 18929 1941 1929 1929 0 99% 1928
AK Infra Ltd. Basti 1278 9258 8441 8441 0 91% 8441 1360 980 980 0 72% 1002.4
Stambh Power Gorakhpur 2480 33111 12183 12183 0 37% 12498 3132 2389 2389 0 76% 2455.8
SGIPL Mirzapur 881 9727 9690 9690 0 100% 9690 1222 1205 1205 0 99% 1220.8
L&T Ltd. Prayagraj 2813 49221 41897 41897 0 85% 42853 3791 2869 2869 0 76% 3019.7
MajorBuildcon
Ashoka Material Erection Progress
Varanasi 2284 Status20400 18905 18905 0 93% 18712 2724 1864 1892 28 69% 2003.1
DISCOM TOTAL 11205 142249 110045 110045 0 77% 111123 14171 11238 11266 28 79% 11630.12
Pole Erection Progress Cable Erection Progress

Poles Poles Total AB ABC ABC


Poles
Workable Progress Progress Cable Progress Progress
(Nos)
Habitation (Nos) (Nos) (Km) (Km) (Km)
Work Completed Pendency Pole Pendency ABC
TKC Zone s found %age Pole %age ABC
initiated Habitation in Pole Progress in ABC Progress
after erected erected
survey erection per day erection per day
BOQ Yesterday Till date BOQ Yesterday Till date

NCC Ltd. Azamgarh 1469 1469 829 20532 15598 15751 76% 4781 153 1941 1121 1148 57% 890 27

AK infra ltd Basti 1278 1278 646 9258 7881 7886 85% 1372 5 1360 637 643 46% 754 6
Stambh
Gorakhpur 2480 2480 1046 33111 10844 10844 32% 22267 0 3132 2203 2203 70% 989 0
Power
SGIPL Mirzapur 881 881 463 9727 8607 8607 88% 2213 0 1222 1116 1116 91% 106 0
L&T Ltd. Prayagraj 2813 2813 1788 49221 38597 38597 78% 10624 0 3791 4176 4176 110% -385 0
Ashoka 4
Varanasi 2284 2284 1158 20400 13999 14170 69% 6313 171 2724 1648 1667 60% 1084 19
Buildcon
Status of Asian Development Bank Funded “Uttar Pradesh Power Distribution Network Rehabilitation Project”
Purvanchal Vidyut Vitran Nigam Limited - Varanasi
Execution Summary
Completed Habitation Work verification done JMC Done Ho-to done

Work Execution completed


Total Pre- Work verification JMC verify Ho-to
inititated by TKC
TKC Zone Workab Execution %age %age
Habitation Today's Today's Today's Today's
le Majra Completed Compl JMC
by TKC progress progress progress progress
Yesterday Till date etion Yesterday Till date Yesterday Till date Done Yesterday Till
date

NCC Ltd. Azamgarh 1469 1469 1469 803 829 0 56% 624 624 0 428 428 0 29% 0 0 0
AK infra.
Basti 1278 1278 1278 645 646 0 50% 80 103 23 71 71 0 5% 0 0 0
Ltd.
Stambh
Gorakhpur 2480 2480 2480 1068 1046 0 42% 322 324 2 280 280 0 11% 0 0 0
Power
SGIPL Mirzapur 881 881 881 463 463 0 52% 71 71 0 39 39 0 4% 0 0 0
L&T Ltd. Prayagraj 2813 2813 2813 1801 1788 0 63% 593 600 7 383 383 0 14% 0 0 0
Ashoka
Varanasi 2284 2284 2284 1191 1158 0 50% 92 92 0 43 44 1 2% 0 0 0
Buildcon
Gang
  Details
Total 11205 11205 11205 5971 5930 0 52% 1782 1814 32 1244 1245 1 11% 0 0 0

Estimated no of Gangs
Habitations- work Gangs instructed to Gangs required to complete the
TKC Zone
not completed be deployed by TKC Deployed balance habitations by
31/07/2022*
NCC Ltd. Azamgarh 640 100 81 171
AK infra. Ltd. Basti 632 50 34 173
Stambh Power Gorakhpur 1434 90 75 340
SGIPL Mirzapur 418 0 49 114
L&T Ltd. Prayagraj 1025 72 64 279
Ashoka *Assuming 5 days will be required by each gang to
Varanasi 1126 150 66 217 complete each majra.
Buildcon
Total 5275 462 369 1294 5
Key issues- MVVNL

Owner Point to discuss

1. M/s Gupta Power to provide the Labour insurances for Lucknow CESS zone. TKC has informed to share the
TKCs insurance by 27/07/2022.

1. PMA to submit habitation wise analysis on pending majras to be completed by TKC. In consultation with TKCs &
Discom, PMA shall submit the weekly completion plan for remaining habitations.
PMA
2. PMA shall submit the Site Observation Report including status of quality of work maintained at site & analysis on
non-compliances reported at site & rectification done by TKCs. PMA shall ensure that quality of work is
maintained at site.

6
Key issues- MVVNL

Owner Point to discuss


1. Discom to appoint auditors for audit of Annual Project Financial Statements (APFS). Discom has informed that the
auditor shall be appointed by 30/07/2022.

2. Discom to provide the habitations details with population between 500-999 and more than 1000 population. Letter
issued to Discoms on 02/07/2022 & 20/07/2022 to provide the details by 23/07/2022. Discom has not confirmed any
timeline for submission of details.

3. Discom need to submit the details of TKC payment in process at various stages at Discom level. Discom has not
confirmed any timeline for submission of details.

4. Discom shall ensure that JMC certification, Completion Certificates & Operation Acceptance Certificate are approved
without any delay after completion of habitations. The TKC wise estimated amount of payments that can be claimed
Discom against the pending JMCs is enclosed in Annexure-I.

5. The Discom officials need to conduct site visits to ensure quality and report the findings to UPPCL on weekly basis. (ref
UPPCL letter no. 2807 dated 17.08.2022). Discom to ensure that the TKCs are maintaining the quality of works as per
the standards and specifications defined in the contract. The Discom/PMA should also ensure that same type of NCs
are not repeated by the TKCs.

6. Discoms to share the revised BOQ as actual requirement of material at site. It is found that there is major difference in
required quantities for some packages.

7. What is the status of BG to be recovered.

8. What is the status of project completion & contract extension if any?

7
Status of Asian Development Bank Funded “Uttar Pradesh Power Distribution Network Rehabilitation Project”
Madhyanchal Vidyut Vitran Nigam Limited - Lucknow
Major Material Supply Progress Status (Original Habitations)
Pole Stock-in Progress AB Cable Stock-in Progress
Workable
Pole
Habitations Poles %age AB Cable Stock-in Cable progress
TKC Zone Stock-in Pole Stock-in till Today’s progress Stock-in Cable Today’s %age Stock-in
found after (Nos) Stock-in (Km) Cable till as per site
till Yesterday Today Progress per site till Today Progress Cable
survey BOQ Pole BOQ Yesterday
Bareilly-1 703 5517 5517 5517 0 100% 5517 752 752 752 0 100% 752
NCC Ltd. Bareilly-2 924 11299 11299 11299 0 100% 11299 1103 1103 1103 0 100% 1103
Devipatan 830 5525 5525 5525 0 100% 5525 763 763 763 0 100% 763
NCC Ltd. - 2457 22341 22341 22341 0 100% 22341 2618 2618 2618 0 100% 2618
Ayodhya 1116 13076 13076 13076 0 100% 13076 1258 1258 1258 0 100% 1258
L&T Limited Lucknow-1 1026 17168 17168 17168 0 100% 17168 1194 1182 1182 0 99% 1194
Lucknow-2 782 10453 10453 10453 0 100% 10453 882 882 882 0 100% 882
L&T Limited - 2924 40697 40697 40697 0 100% 40697 3334 3322 3322 0 100% 3334
Gupta Power Lucknow-CESS 158 1700 1496 1496 0 88% 1696 135 134 134 0 99% 134
Gupta Power - 158 1700 1496 1496 0 88% 1696 135 134 134 0 99% 134
DISCOM Total 5539 64738 64534 64534 0 100% 64734 6087 6074 6074 0 100% 6086

Major Material Supply Progress Status (Additional Habitations)


Pole Stock-in Progress AB Cable Stock-in Progress
Workable
Habitations Pole
Poles %age AB Cable Stock-in Cable progress
TKC Zone found after Stock-in Pole Stock-in till Today’s progress Stock-in Cable Today’s %age Stock-in
(Nos) Stock-in (Km) Cable till as per site
till Yesterday Today Progress per site till Today Progress Cable
survey BOQ Pole BOQ Yesterday

Bareilly-1 219 1664 1602 1602 0 96% 953 378 431 431 0 114% 431
NCC Ltd. Bareilly-2 267 3274 2719 2719 0 83% 2553 327 272 272 0 83% 272
Devipatan 1042 9389 9175 9175 0 98% 8925 1072 799 799 0 75% 821
NCC Ltd. - 1527 14327 13496 13496 0 94% 12431 1777 1502 1502 0 85% 1524
Ayodhya 849 19834 3021 3021 0 15% 4242 1689 147 147 0 9% 174
L&T Limited Lucknow-1 530 9011 4695 4695 0 52% 7472 649 0 0 0 0% 531
Lucknow-2 834 21220 1010 1010 0 5% 5321 1511 115 115 0 8% 264
L&T Limited - 2213 50065 8726 8726 0 17% 17035 3849 262 262 0 7% 969
Gupta Power Lucknow-CESS 157 3422 0 0 0 0% 0 917 0 0 0 0% 0
Gupta Power - 157 3422 0 0 0 0% 0 917 0 0 0 0% 0
DISCOM Total 3898 67814 22222 22222 0 33% 29466 6543 1764 1764 0 27% 2493
BoQ against additional habitations will drastically reduce once survey qty on portal is finalized; this BoQ figures correspond to the qty shown in change proposal
Status of Asian Development Bank Funded “Uttar Pradesh Power Distribution Network Rehabilitation Project”
Madhyanchal Vidyut Vitran Nigam Limited - Lucknow

Major Material Erection Progress Status (Original Habitations)

Pole Erection Progress AB Cable Erection Progress


Poles Poles Total AB ABC ABC
Poles
Workable Progress Progress Cable Progress Progress
(Nos)
Habitation (Nos) (Nos) (Km) (Km) (Km)
Work Completed %age Pendency Pole Pendency ABC
TKC Zone s found %age ABC
initiated Habitation Pole in Pole Progress in ABC Progress
after erected
survey erected erection per day erection per day
BOQ Yesterday Till date BOQ Yesterday Till date

Bareilly-1 703 703 500 5517 4799 4837 88% 680 38 752 652 667 89% 85 15
NCC Ltd. Bareilly-2 924 924 686 11299 9755 9755 86% 1544 0 1103 1004 1004 91% 99 0
Devipatan 830 830 685 5525 5621 5621 102% -96 0 763 823 823 108% -60 0
NCC Ltd. - 2457 2457 1871 22341 20175 20213 90% 2128 38 2618 2479 2494 95% 124 15
Ayodhya 1116 1116 1000 13076 12082 12082 92% 994 0 1258 1244 1244 99% 14 0
L&T Limited Lucknow-1 1026 1026 1018 17168 18702 18702 109% -1534 0 1194 1177 1177 99% 17 0
Lucknow-2 782 782 448 10453 9722 9722 93% 731 0 882 821 821 93% 61 0
L&T Limited - 2924 2924 2466 40697 40506 40506 100% 191 0 3334 3242 3242 97% 92 0
Lucknow-
Gupta Power 158 158 132 1700 1253 1280 75% 420 27 135 92 96 71% 39 4
CESS
Gupta Power - 158 158 132 1700 1253 1280 75% 420 27 135 92 96 71% 39 4
DISCOM Total 5539 5539 4469 64738 61934 61999 96% 2739 65 6087 5780 5780 95% 255 19
Status of Asian Development Bank Funded “Uttar Pradesh Power Distribution Network Rehabilitation Project”
Madhyanchal Vidyut Vitran Nigam Limited - Lucknow
Execution Summary
JMC Verification Done (Approved HOTO done
Completed Habitation Work verification done
on Portal) (Uploaded on portal)
Total Pre Work Work
workabl Execute inititated Today' Gangs verificatio Work JMC JMC
TKC Zone
e Complete Habitation Execution Execute s
%age At Site
n
Verificatio
Today's Verificatio Verificati
Today's %age Hoto till
Today's
Majra d by TKC completed Complete progre Complet Approved
n
progress n till on till
progres JMC yesterd Hoto
progress
yesterday d till date ion Approved s Done ay
ss till yesterday today
till today
yesterday
Bareilly-1 703 703 703 500 500 0 71% 30 104 104 0 0 0 0 0% 0 0 0
NCC Ltd. Bareilly-2 924 924 924 683 686 3 74% 29 225 225 0 0 0 0 0% 0 0 0
Devipatan 830 830 830 685 685 0 83% 69 643 643 0 288 288 0 35% 227 227 0
  2457 2457 2457 1868 1871 3 76% 128 972 972 0 288 288 0 12% 227 227 0
Ayodhya 1116 1116 1116 1000 1000 0 90% 19 620 620 0 311 352 41 32% 183 178 -5
L&T Ltd. Lucknow-1 1026 1026 1026 1018 1018 0 99% 25 878 878 0 781 781 0 76% 490 490 0
Lucknow-2 782 782 782 448 448 0 57% 28 29 29 0 0 0 0 0% 0 0 0
  2924 2924 2924 2466 2466 0 84% 72 1527 1527 0 1092 1133 41 39% 673 668 -5
Lucknow-
Gupta Power 158 158 158 132 132 0 63% 7 1 1 0 0 0 0 0% 0 0 0
CESS
  158 158 158 132 132 0 63% 7 1 1 0 0 0 0 0% 0 0 0
Total 5539 5539 5539 4466 4469 3 81% 207 2500 2500 0 1380 1421 41 26% 900 895 -5

The highlighted cells against TkC completions also include few habitations reverted by PMA; Total reverted count for MVVNL is 99 (71 in Bareilly-1 only)
Status of Asian Development Bank Funded “Uttar Pradesh Power Distribution Network Rehabilitation Project”
Madhyanchal Vidyut Vitran Nigam Limited - Lucknow
Survey Status for Additional Majras
Workable Habitation Submitted on PMA Approved - Workable SE Approved - Workable
portal Habitation Habitation Per day
Screening Pending
Additiona Workable target as
Name of Forms for
Zones l Majras habitatio % % per
TKC submitted submissio
(Nos) n-On Site Till %age Till approve Yesterd Till approv deadline
Yesterday Progress Yesterday Progress Progress by PMA n on portal
date uploaded date d by ay date ed by 30 June
PMA SE

Bareilly-1 250 219 198 198 90% 0 140 143 72% 3 65 65 45% 0 143 55 1
NCC,
Bareilly-2 284 267 267 267 100% 0 186 186 70% 0 133 133 72% 0 186 81 5
Hyderabad
Devipatan 1135 1042 836 843 81% 7 616 625 74% 9 554 554 89% 0 625 218 51
    1669 1528 1301 1308 86% 7 942 954 73% 12 752 752 79% 0 954 354 57
Ayodhya 3153 849 598 598 70% 0 532 533 89% 1 405 471 88% 66 533 65 60
L&T Lucknow-1 966 530 412 419 79% 7 330 331 79% 1 242 242 73% 0 331 88 28
Lucknow-2 1729 834 242 242 29% 0 159 164 68% 5 113 113 69% 0 164 78 94
    5848 2213 1252 1259 57% 7 1021 1028 82% 7 760 826 80% 66 1028 231 182
Gupta Lucknow-
669 157 58 58 10% 0 50 50 86% 0 0 0 0% 0 50 8 52
Power CESS
    669 157 58 58 10% 0 50 50 86% 0 0 0 0% 0 50 8 52
DISCOM Total 8186 3898 2611 2625 67% 14 2013 2032 77% 19 1512 1578 78% 66 2032 593 291
Disclaimer

This document has been prepared solely for UPPCL, being the express addressee to this document. PwC does not accept or assume any liability,
responsibility or duty of care for any use of or reliance on this document by anyone, other than (i) UPPCL, to the extent agreed in the relevant contract
for the matter to which this document relates (if any), (ii) as expressly agreed by PwC in writing in advance.

This publication (and any extract from it) may not be copied, paraphrased, reproduced, or distributed in any manner or form, whether by photocopying,
electronically, by internet, within another document or otherwise, without the prior written permission of PwC. Further, any quotation, citation, or
attribution of this publication, or any extract from it, is strictly prohibited without PwC’s prior written permission.

© 2022 PricewaterhouseCoopers Private Limited. All rights reserved.

In this document, PwC refers to PricewaterhouseCoopers Private Limited (a limited liability company in India) an India member firm and may
sometimes refer to the PwC network.