Professional Documents
Culture Documents
Planning of Lifting Operations Subsea 7 Cosalt
Planning of Lifting Operations Subsea 7 Cosalt
Planning of Lifting Operations Subsea 7 Cosalt
Bill Uren
Training Manager
Welcome to Training Facility
WORKSHOP
REFRESHMENTS
SMOKING
Planning of Lifting Operations
Aim
To provide information and instruction sufficient to identify the nature and level
of risks and stages associated with planning of lifting operations.
Objective
Health And Safety At Work etc Act 1974 as amended 1987 (HASAWA)
1 Mile
The Law Requires ( L.O.L.E.R.)
Regulation 8; “Organisation of Lifting Operations”
1) Every Employer shall ensure that every lifting operation involving lifting
equipment is: -
P.P.P.P.P.
Proper
Planning
Prevents
Poor
Performance
Lifting Operations may not be hi-tech or glamorous;
2. It makes sense.
So
The ‘competent person’ should have the necessary training, background and
experience to be recognised as being competent in the particular field in which
they specialise.
MHSWR
L.O.L.E.R. A.C.O.P.
“The person planning the operation should have adequate practical and
theoretical knowledge and experience of planning lifting operations”
Proper Planning
Relocate motor cover from its present position to the indicated landing area.
1.25 m
Tare
Weight
500 kg
2.5 m
150mm x 250mm H Beams SWL
3 tonnes
Note:
The runway beam is in-line
With the tank, but out of
line with the cover
3m
9b
7 9a
8
10
13
12
14
15
11
P.U.W.E.R
Selection and Suitability
Ensure:
• Human injury
• Damage to property
Consequence:
• The result of a hazardous event occurring
Risk
Some examples of lifting operations incidents that could have been avoided by
proper planning.
Crane driver told
it was 9 tonne
What do I do now???
Actually it
was 14 tonne
Oh *!!*t!
Help
How Could This Incident Have Been Avoided?
• A higher capacity crane reducing the risk should have been considered.
• A load indicator should have alerted the crane operative that this load
was excessive.
Contributing factors:
1. Lack of supervision
2. Lack of Training
A You cannot afford to have any doubts as to your expected role in the
development of lifting plans.
• When you review the validity of the plan, and are determining whether
anything has changed. If there is a change, ask yourself and others at
the Toolbox Talk;
• Will this change mean that the operation category has changed from
Routine to Non-Routine or Complex?
• The users of the equipment need to have been specifically trained in its
use and familiar with its limitations.
• The involved personnel must be familiar with both the written risk
assessment and the written lifting plan for the operation being
conducted.
• The written plan must be verified as the current issue (all routine lifting
operations will be reviewed prior to the commencement of the
operation).
Routine
Non Routine Lifts
Are those lifts, which do not meet all the criteria for
Routine Lifts
Responsible Person
• Vessel Master, Offshore Manager, Shift Supervisor, Base
Manager or Project Engineer
Competent Person
• The Competent Person is someone who has the necessary
competency to plan a lift as well as the necessary technical expertise
relevant to lifting operations and the supervisory skills and experience
required to organise the lifting operation. The Competent Person may or
may not supervise the lifting operation but is the focal point of authority for
the technical aspects of the lift.
Roles & Responsibilities
Lift Supervisor
• The Lift Supervisor must be clearly identifiable, must have a clear view
of the lift and must ensure that lifting activities follow the agreed plan.
• In the case where the load is not always visible to the Crane or Forklift
Operator, the Lift Supervisor must ensure that clear communication
systems are in place to ensure sufficient co-ordination between pick up
and lay down areas.
Roles & Responsibilities
• Subsea 7 has competency standards for offshore marine personnel which are
aligned to the IMCA (International Marine Contractor’s Association)
competency assurance and assessment guidance.
Roles & Responsibilities
The following standards identify the minimum competency criteria for deck
crew and Forklift Operators:
•Is there an existing and adequate lift plan for the lifting operation?
•Do the personnel selected to undertake this lifting operation have the
correct level of experience and knowledge ( both theoretical and practical)?
•Has the lifting procedure been communicated and understood by all involved
•Have you considered other factors e.g. wind, lighting, centre of gravity?
•Have you assessed the path the load will take?
Management Team
UK
Site/Project ICP
Responsible Person
Onshore
Support
Maintenance Base Manager Contractors
Supervisor(s) Engineering Focal Compliance Lead
& Sub-Contractors
Point HSE & Q
Crane
Site Lifting Rigger
Operators
Equipment Engineer
Fixed/Mobile/Overhead
Competent Person
Onshore Lifting Support –
to be displayed at each worksite
Sandy Gowing
(I.C.P.)
227905
Dave Dobeson
(Engineering) (Compliance)
795738
Cosalt Ltd.
(Competence)
826662
344521
Laurence Hosie
Site/Project HSE Advisor
(Equipment)
Varies by Site/project
292290
Stage 3 Horizontal
Position
Crane 2 Boom
Position 2
Fixed Rotation
Point Crane 1
Sling Attachment Sling Attachment
Points C & D Points A & B Crane 2
Hoist & Boom
Movements
Stage 1 Vertical
1 metre
Ground Level
Plan No – Yard – 02D
Turning Tank
From Horizontal to Crane 2 Boom
Vertical Position Position 3
Crane 2 Boom
Position 1
Stage 1 Vertical
1 metre
Ground Level
Tank Sitting Horizontally
D Frame B
Top
Crane 1 Crane 2
View
A
C
Side
View
Tank Sitting Vertically
Frame
Crane 1 Crane 2
Top View
Side
View
Equipment List
Lifting Plan No Yard –02 - D
B. 2 x signs (crane 1) and ( crane 2), suitable for display on each crane
window (printed both sides).
E. 2 x 25 tonne SWL alloy bow safety pin shackles c/w split cotter pins.
Every employer shall ensure that every lifting operation involving lifting
equipment is:
SWL The safe working load of a crane is calculated on the assumption that
the load will be raised and lowered in a vertical plane.
The crane structure will have been designed to withstand any lateral loads
imposed by accelerations in the crane motions, but it is unsafe to rely on this
lateral strength to withstand horizontal components of out-of- plumb lifts.
It is recommended that the safe working load of each crane for the required jib
length and operating radius should be at least 25% in excess of the calculated
share of the load to be handled by each crane during the tandem lift.
BS 7121: Part 1: 1989
The hoisting slewing, traversing, luffing or travelling motions of a crane should not be
used to drag any load along the ground with the hoist rope out of the vertical position.
Tandem Lifting CP 3010: 1972
The cranes are owned by Lampson, however, Lampson personnel had no involvement in the lift.
What made the M4100WS2 tip? The M4600WS5 and M4100 lifted the load, no problem. They then tracked sideways. During the
tracking, the site personnel noticed the M4600's counterweight was going to hit a steel bollard (post concreted into the ground).
They kept tracking! Then they slewed the M4600 to the operator's right, in effect pulling the load away from the M4100. They kept
this going, thinking that they were almost there.
From reports, they then decided it was not going to make it and slewed the M4600 back (whoops), in doing so, it allowed the load to
swing into the M4100's boom as its tracks sat back down.
In any case, good planning would have identified the bollard before any crane work began. PREVENTABLE right?