Professional Documents
Culture Documents
Presentation by Saqib
Presentation by Saqib
Presentation by Saqib
KAKRA
DAM
EMERGENCY
SPILLWAY SUKIAN DYKE
POWER INTAKES
MAIN SPILLWAY
POWER STATION
MAIN DAM
INTAKE EMBANKMENT
Concrete 20 M Cu Yd
WATER SCARCITY
USES
ABOVE RIM STATIONS 5.7 MAF
CANAL DIVERSION 105.4 MAF
TOTAL 111.1 MAF
81.49
80.59
80
Annual Discharge (MAF)
69.08
62.76
60
52.86 53.29
40
30.39 29.81 29.55 29.11 35.15
33.79 26.90
20.10 20.79
17.53
20 17.22
9.68 10.98
8.83
2.32
0.77 1.93
0
*02-03
76-77
77-78
78-79
79-80
80-81
81-82
82-83
83-84
84-85
85-86
86-87
87-88
88-89
89-90
90-91
91-92
92-93
94-95
95-96
96-97
97-98
98-99
00-01
01-02
93-94
99-00
Years
* Upto Dec. 20, 2002
MANGLA DAM RAISING PROJECT
RESERVOIR SEDIMENTATION (MAF)
STORAGE LOSS BY
ORIGINAL STORAGE STORAGE LOSS BY THE
RESERVOIR YEAR 2010
CAPACITY (MAF) YEAR 2002 (MAF)
(PROJECTED) (MAF)
0
2
4
6
8
10
12
14
1967-68
1968-69
1969-70
1970-71
1971-72
1972-73
1973-74
1974-75
1975-76
1992-93
1993-94
1994-95
HISTORIC FLOOD SPILLAGES
1995-96
1996-97
1997-98
1998-99
1999-00
2000-01
2001-02
2002-03
HISTORIC INFLOWS AT MANGLA
30
20
15
Min. 12 maf
10
Years
Source: WAPDA Water Wing Mangla
RESERVOIR FILLING (%)
10
20
30
40
50
60
70
80
90
0
100
1967-68
1968-69
1969-70
1970-71
1971-72
1972-73
1973-74
1974-75
1975-76
1976-77
1977-78
1978-79
1979-80
1980-81
1981-82
1982-83
1983-84
1984-85
1985-86
1986-87
1987-88
1988-89
WATER YEAR (APRIL TO MARCH) 1989-90
1990-91
AVERAGE FILLING = 97 %
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
1997-98
1998-99
HISTORIC RESERVOIR FILLING
1999-00
2000-01
2001-02
2002-03
Year
Water
2000-01
1999-00
1985-86
1974-75
1971-72
1970-71
2001-02
Average
83%
85%
83%
97%
69%
80%
91%
75%
RESERVOIR FILLINGS
25
PRE-RAISING POST-RAISING
100% Filling = 30 out of 37 years (81%) 100% Filling = 27 out of 37 years (73 %)
Av. of Partial Filling = 83 % Av. of Partial Filling = 80 %
Av. Filling (37 years) = 97 % Av. Filling (37 years) = 93 %
20
CONSTRUCTION PERIOD
Raised
Reservoir
15 Existing
Reservoir
MAF
10
2.6 MAF
1.5 MAF
Sediment Deposition
0
1969-70
1979-80
1987-88
1991-92
1997-98
1999-00
2001-02
2009-10
2013-14
2018-19
2022-23
2024-25
2028-29
2032-33
2037-38
2046-47
1967-68
1971-72
1973-74
1975-76
1977-78
1981-82
1983-84
1985-86
1989-90
1993-94
1995-96
2003-04
2005-06
2007-08
2011-12
2016-17
2020-21
2026-27
2030-31
2035-36
2039-40
2041-42
2044-45
WATER YEAR (APRIL TO MARCH)
MANGLA DAM RAISING PROJECT
MANGLA RAISING
30 Ft. Raising of Dam (Permits 40 Ft. Raising of Reservoir Level)
Provision for Raising upto 40 Ft. was Kept in Dam Foundations at
a Cost of $ 18 Million
Existing Main Spillway Designed for Raised Mangla, Only Gravity
Wall to be Raised
No Alteration Needed in Emergency Spillway
All the Ten Power Units Cater for Raised Mangla Conditions
MANGLA DAM RAISING PROJECT
Desilting of Reservoir
MANGLA DAM RAISING PROJECT
DEVELOPMENT OF SMALL STORAGE RESERVOIRS
UPSTREAM MANGLA
EIRR 18%
Award of Contract June 20, 2004
(Main Works – Dam Raising)
Associates:
Techno - Consult, Karachi
Associates in Development (AID), Peshawar
Pakistan Architect & Consulting Engineers (PACE), Hyderabad
MANGLA DAM RAISING PROJECT
CONSTRUCTION OF
SADDLE 100% / 100%
EMBANKMENT
( Rs. 9.37 Million )
CONSTRUCTION OF
POWER HOUSE
BYPASS ROAD AND 80.00% / 100%
BRIDGE ON BONG
CANAL
( Rs. 106.81 Million )
•The main reason for delay in the construction of bong canal bridge/road is slow
mobilization of contractor’s resources.
MANGLA DAM RAISING PROJECT
MAJOR COMPONENTS OF MAIN WORKS
KAKRA
DAM
EMERGENCY
SPILLWAY SUKIAN DYKE
POWER INTAKES
MAIN SPILLWAY
POWER STATION
MAIN DAM
INTAKE EMBANKMENT
STAGE 1 STAGE 2
STAGE 3 STAGE 4
MANGLA DAM RAISING PROJECT
MAIN DAM
STATUS AS OF SEPTEMBER 30, 2006
% age Achieved
Total Quantityas per
Placed Quantity with respect to Balance Quantities
Construction Stages Construction Drawings Remarks
(Cu Yd) the Total (Cu Yd)
(Cu Yd)
Quantity
Stage - 1 8,650,000 7,828,005 90.50% 821,995 Last 9 Months progress achieved is 97%
Stage - 2 (Excavation of Crest) 927,000 0 927,000 of planned.
Workshop facilities are being improved,
Stage - 3 2,644,000 0 2,644,000
however break down are frequent.
Stage - 4 1,253,000 0 1,253,000 Existing processing / crushing units are
Embankment Fill 12,547,000 7,828,005 62.4% 4,718,995 working satisfactorily but production is
Intake Toe Weight 2,800,000 0 2,800,000 less than required
Upstream Blanket 113,500 100,877 88.88% 12,623 Newly installed processing plant is not
functioning properly
Relocated Roads 280,000 135,595 48.43% 144,405 One more crushing plant has started
West Embankment 120,000 0 120,000 functioning
Overall progress of production of filters is
Total Fill 15,860,500 8,064,477 50.85% 7,796,023 less than required.
MANGLA DAM RAISING PROJECT
JARI DAM
STAGE 1 STAGE 2
STAGE 3 STAGE 4
MANGLA DAM RAISING PROJECT
RAISED MAIN SPILLWAY
RAISED SPILLWAY
RAISED RESERVOIR
EL 1264
EL 1242
EL 1234
EL 1202
EXISTING FLOOR TO BE
RESERVOIR RAISED BY 5 FT
GATE
EL 1069
FOUNDATION ROCKS
MANGLA DAM RAISING PROJECT
DETAIL 'D'
MANGLA DAM RAISING PROJECT
MANGLA DAM RAISING PROJECT
OVER ALL IMPLEMENTATION SCHEDULE
STATUS AS OF SEPTEMBER 30, 2006
2002 2003 2004 2005 2006 2007
COMPONENT
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
JUL 2002 JAN 2005
PREPARATORY WORKS
(452 MILLION Rs.)
Saddle Embankment, Power House
Bypass Road and Bridge Over Bong 93.0% / 100%
Canal & Staff Hostels etc.
MAIN WORKS
(13,794 Million Rs)
38.0% / 64.24%
RESETTLEMENT
(26,257 Million Rs.)
50.71% / 70.50%
OVERALL PROGRESS
47.0% / 68.70%
PLANNED ACTUAL
MANGLA DAM RAISING PROJECT
RESETTLEMENT
MANGLA DAM RAISING PROJECT
SCOPE OF RESETTLEMENT
POPULATION 44000
CHOHAN
KHARAK