Professional Documents
Culture Documents
Presentation 1
Presentation 1
Presentation 1
IMPROVEMENT PROJECT
(KUWASIP)
CONTENTS
Introduction
Karnataka water supply PPP model
Details
Project Description
Project Timeline
Stakeholders
About Project
PPP Context
PPP Structure
Role Of Private Player During O And M Phase
Financing Information
Process Analysis
Key Challenges
Risk Allocation Framework
Performance Levels
Shortcomings, Issues And Outcomes
Key observations
Impacts
INTRODUCTION
Source: http://abhinavinfo.com/idd_kannada/assets/pdf/case_studies/CS_Karnataka.pdf
PROJECT DESCRIPTION
Source: https://www.wsp.org/sites/wsp/files/publications/WSP_Karnataka-water-supply.pdf
ABOUT PROJECT
• The project involved Need: The water sector in Karnataka
refurbishment/rehabilitation of the suffers from the following issues:
Private • Rehabilitation existing distribution network of the • Chronic inefficiencies, Unreliable
develope works
• Operation and select five demonstration zones in service quality and limited coverage.
r maintenance
the three Urban Local Bodies. • At the technical level, problems
• It was followed by the operation and include sub-optimal resource
management of water distribution allocation, Mismatched capacity
systems on a PPP basis. investments, Lack of requisite
• Funding for • Under the PPP structure, the private technical manpower, Poor operation
capital
Public investment developer’s responsibility included and maintenance (O&M) practices,
party compensated
replacement of the distribution Un-economic tariff structure / levels,
by the World
Bank through pipelines, installation of bulk water Poor collection efficiency, High levels
KUIDFC
meters and consumer meters, and of unaccounted and non-revenue
setting up of a computerized billing • Water sector information systems
system. are deficient
• The rehabilitation activity was funded • Poor service coverage; service
Duration • 3 years and 6 by KUIDFC as a capital grant coverage in all the three participating
months
amounting to INR 42 crores. ULBs was estimated to be less than
50%.
PPP CONTEXT
• Commencement of World Bank (WB) project (financial and technical assistance) in 2000,
for addressing institutional/infrastructural deficiencies in the neglected northern districts
of Karnataka.
• The project envisaged development of management contracts, wherein private operators
would undertake planning, design and management of services in various ULBs in these
districts.
• Initiation of the Karnataka Urban Water Sector Improvement Project (KUWASIP) by
KUIDFC in 2002 under the WB programme, and decision to demonstrate 24X7 supply
through a pilot project.
• The project was aligned with the strategies enunciated by the Urban Drinking Water and
Sanitation Policy (2002) of the Government of Karnataka.
• Amendment of the Karnataka Municipal Corporations Act in January 2005, making
provisions for private sector participation in municipal water supply and allowing
deputation of ULB employees to private companies in case of PPP projects.
SECTORAL CONTEXT
• Coverage of water supply (average) in the 3 pilot cities was as low as 50%.
• Per capita consumption in Gulbarga was 46 LPCD and that in the other 2 cities about 123
LPCD, as against the accepted standard of 135 LPCD.
• Service reliability was low with average supply in the range of 2-6 hours of water supply
once in 3-5 days.
Source: http://abhinavinfo.com/idd_kannada/assets/pdf/case_studies/CS_Karnataka.pdf
PPP STRUCTURE
• (a) Beneficiary: the three ULBs viz.
Belgaum, Gulbarga and Hubli-
Dharwad
• (b) Sponsor: the GoK through its two
entities the Karnataka Urban
Infrastructure Development and
Finance Corporation (KUIDFC), and
the Karnataka Urban Water Supply
and Drainage Board (KUWSDB)
• (c) Developer: the private developer
responsible for rehabilitation and
operations.
• The private developer’s responsibility
included replacement of the
distribution pipelines, installation of
bulk water meters and consumer
meters, and setting up of a
computerised billing system. The
rehabilitation activity by the private
developer was funded by KUIDFC.
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
ROLE OF PRIVATE PLAYER DURING O AND M PHASE
• During the O&M phase of the • The private developer was
project, the private developer was compensated through a management
required to meet the following fee paid for the period of the
performance targets: contract. The fee included a fixed
• Ensure 100 per cent component of 60 per cent and a
individual house service variable component of 40 percent,
connections in the with the latter based on meeting the
demonstration zones performance targets.
• Supply treated water to all • In addition to this, further incentives
the customers were to be provided to the private
• Ensure reduction in developer for achievement of targets
distribution losses as per beyond a set level. This incentive was
targets set over and above the operator fee
• Bill generation and remuneration.
distribution to consumers for • Post the rehabilitation phase,the
payment as per the tariff set private developer was only provided
by the ULBs. the right to operate and maintain the
• Bill collection was the facilities.
responsibility of the
respective ULBs
FINANCING INFORMATION
• The total cost for the • The project was structured with
construction/rehabilitation activity financial incentives to the private
was capped at INR 42 crores developer for efficient execution -
• The ULBs did not bear the debt bonus set at 25 per cent of the
burden for the capital costs. remuneration decided.
• The operator fee of INR 22 crores was • During the rehabilitation and
paid from the revenues accruing to construction phase of the project, the
the private developer was able to reduce
• Delays during the course of the the capital costs by over 25 per cent
implementation of the project, led to and was eligible to avail the
escalation in the compensation to be incentives as set
paid to the operator by KUIDFC and • During the course of execution of the
the operator fee was increased to INR O&M phase of the project, the
28 crores. private developer was able to bring
• Estimated project cost- approximately about savings of greater than 25 per
INR 62 crores cent in the O&M expense, reduction
• World Bank’s loan based assistance in the losses to less than 15 per cent
to the project - INR 45 crores. and also increase the billed water
supply to over 25 per cent.
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
PROCESS ANALYSIS
PPP Project
Inception Procurement
Preparation
• Launch • Assessment by Tata Consultancy • a two stage bidding process was
• Identification of 3 ULB’s with poor water Engineering (TCE) followed, i.e. the Request for
supply levels • Identified that the water supply service Qualification (RFQ) stage followed by
• 5 demonstration zones with 24*7 water delivery were extremely poor in the the Request for Proposal (RFP) stage
supply three ULBs • At the RFQ stage -From the 30 bidders,
• This assessment was followed by seven were selected and invited to
estimation of capital investment, and a submit their proposals.
review of the financial position and • Only international players in the water
capacity of the three Municipal business being eligible for undertaking
Corporations. the project
• A project for rehabilitation, operation • The lowest quote was received from the
and maintenance of a 24x7 water French company Compagnie Generale
supply system in the demonstration des Eaux was selected as the preferred
zones on a PPP basis was prepared. bidder.
• The quote was of INR 22 crores.
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
PROCESS ANALYSIS
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
KEY CHALLENGES
• Improved bulk water supply in demo • To suppress the anxiety prevailing
zones and towns were essential for amongst the political class and the
the demonstration of service level public-related to volumetric billing
improvements. Delay in completion and usage of water meter- ULBs
of such prioritized work has had adopted flat tariff for six months so
serious implications. that in the meantime consumers
• HDPE pipes were used by the could moderate their consumption
operator during replacement of and adapt to the billing system.
entire distribution network of water • Extensive efforts were made to
supply, as the existing pipes could not ensure local political support for
withstand the pressure, but there regularization of unauthorized
was resistance by KUWS&DB in connections, providing new
accepting the new material connections to slum dwellers as per
• Adoption of volumetric tariff system state’s pro-poor policy.
was delayed by the State government • Social intermediation and
because of public concerns raised in communication teams were
the demonstration zone. strategically placed to put forth the
right messages at the right time.
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
RISK ALLOCATION FRAMEWORK
RISK TYPE SENSITIVITY RISK PERIOD PRIMARY RISK BEARER
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
PERFORMANCE LEVELS
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
http://abhinavinfo.com/idd_kannada/assets/pdf/case_studies/CS_Karnataka.pdf
SHORTCOMINGS, ISSUES AND OUTCOMES
• The project was delayed (by more • Continuous pressured (24/7) water • Continuous pressured (24/7) water
than a year) in Stage II which involved supply has been operationalized in all supply has been operationalized in all
contracting out works as envisaged the five Demonstration Zones viz., (1) the five Demonstration Zones viz., (1)
under the Improvement plan, Belgaum (South) (2) Belgaum (North) Belgaum (South) (2) Belgaum (North)
primarily due to the detailed (3) Gulbarga (4) Hubli and (5) (3) Gulbarga (4) Hubli and (5)
procurement specifications laid down Dharwad during 2007-08 and the Dharwad during 2007-08 and the
by the World Bank. O&M period commenced from O&M period commenced from
• The Project suffered initially due to 3.4.2008. 3.4.2008.
public non acceptance. However this • The following are the perceivable • The following are the perceivable
was addressed by KUIDFC and the differences in the Demo Zones, differences in the Demo Zones,
World Bank, by undertaking where continuous water supply is in where continuous water supply is in
systematic Information, Education operation. Per capita supply of -- operation. Per capita supply of --
and Communication activities (IEC). lpcd, as against 135 lpcd assumed lpcd, as against 135lpcd assumed
• Following the delay in procurement • Equitable water supply to all • Equitable water supply to all
processes, the period of the customers without operating a single customers without operating a single
concession had to be suitably valve Scientific pressure valve Scientific pressure
extended to accommodate the delay. management without throttling the management without throttling the
• No other issues have emerged during valves. valves.
project implementation
Source: https://www.indiawaterportal.org/sites/default/files/iwp/NUWAwards_KarnatakaUrbanWaterSectorImprovementProject_KUIDFC_2009_0.pdf
KEY OBSERVATIONS
Pre project assessment critical: • Effective facilitation of project • Government needs to provide full
• Before tendering out the project, it is implementation by the government: cooperation to the private developer
important that the government Project awareness activities, which at various phases.
undertakes a first level service were initiated by KUIDFC, to • It has been observed that there were
assessment of the project area to be familiarize the consumers with the delays during the demonstration
able to indicate the status of the proposed project. Additionally, phase of the project due to the non-
physical infrastructure and the service several NGOs and PIUs were brought availability of bulk water for supply
delivery gaps, and later on the basis of together to facilitate effective by KUWSDB.
the assessment, ascertain the nature implementation of the project. • Further, the ULBs did not provide
of rehabilitation works required and • The project incorporated a strategic sufficient and prompt information,
the investment needed. Such an communication during the and also did not release the
assessment would give a realistic preparation and implementation of payments to the developer on time.
picture of the on ground situation to the project involving door-to-door • It is important that such payments
the government and also post award distribution of questions, are made on time to the private
of bids, to the private developer. establishment of public information developer. There were also delays in
These studies include: centres so that transparent access to getting permits.
o Water audit studies information was made available to
o Energy audit studies all, meetings, media tours,
o Consumer survey information sharing with media, and
o Pre-feasibility studies paid-advertisements.
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
http://abhinavinfo.com/idd_kannada/assets/pdf/case_studies/CS_Karnataka.pdf
KEY OBSERVATIONS
• Project ownership by the • Appropriate time allocation for • Proper preparation for takeover by
implementing agency and the different phases of the project is the ULBs and KUIDFC: The private
participating ULBs is important critical that the private developer be developer has provided training to
• To identify what potential users want provided reasonable time for the existing staff of the three ULBs for
and what resources they are willing to achievement of the various tasks managing the system post hand over
apply to finance and manage installed enlisted under each phase of the by the private developer.
systems, it is also required that correct project. • It is important that these skills are
and relevant information be collected • In the context of a situation where well absorbed by the officials and the
during preparation. the ULBs have a poor information management of the system
• Consultation and participation of the base of the existing infrastructure understand well for effective
consumers and other stakeholders are level and service delivery status, it is implementation and continuance of
crucial for successful implementation important that sufficient time be smooth operations of the system by
of the project. provided to undertake a detailed the ULBs.
assessment in order to arrive at an • In designing similar projects, it would
accurate situation analysis. be helpful to carry out
comprehensive benefit monitoring
and evaluation.
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
http://abhinavinfo.com/idd_kannada/assets/pdf/case_studies/CS_Karnataka.pdf
IMPACTS
Consumers are benefitting O&M costs are being covered
• Households received continuous • In 2003, before the project began,
water supply at the designed the three participating urban local
pressure, with water in taps inside bodies recovered less than half of the
their homes, even in third-storey Operations and Maintenance (O&M)
apartments. costs of their water supply systems.
• The water which came out of the • The project aimed to cover 80
pipes was potable and anecdotal percent of O&M costs by the end of
reports suggest that health has the initial two-year maintenance
improved. period and achieve a billing and
collection efficiency of at least 70
Water consumption has reduced percent by the end of the project.
• Contrary to expectations, the • In March 2011, when the project
provision of 24/7 water supply ended, over 80 percent of consumers
resulted in less water being were paying their bills, enabling the
consumed. People tended to municipal corporations to recover
conserve water when they were sure O&M costs, along with arrears.
of reliable supply and were made
aware of the value of water and cost
of its provision.
Source: https://www.pppinindia.gov.in/documents/20181/27199/Compendium_July8.pdf/74f766db-c9ba-4ff9-8492-a0ff4493103f
http://abhinavinfo.com/idd_kannada/assets/pdf/case_studies/CS_Karnataka.pdf
THANK YOU