ACSA - Milestone Plan - V3
Development Timeline*
Milestone 1
14th March - 01st April 2022 Demo Date: 06th April 2022
Milestone 2
4th April - 15th April 2022 Demo Date: 20th April 2022
(Dev. Payment Milestone 2)
Milestone 3
18th April - 29th April 2022 Demo Date: 4th May 2022
(Dev. Payment Milestone 3)
Milestone 4
2nd May - 13th May 2022 Demo Date: 18th May 2022
(Dev Payment Milestone 4)
Note: The timeline above may be altered depending on the amount of feedback we receive and other internal/external factors. Stakeholders will be notified if there will be
any changes.
Development Timeline*
Milestone 5
16th May - 31st May 2022 Demo Date: 3rd June 2022
Milestone 6
1st June - 14th June 2022 Demo Date: 17th June 2022
Dev. Payment Milestone 5)
15th June - 28th June 2022 Demo Date: 1st July 2022
UAT Cycle
4th July- 29th July 2022 Final Product Demo : 29th July 2022
(UAT signoff payment)
Note: The timeline above may be altered depending on the amount of feedback we receive and other internal/external factors. Stakeholders will be notified if there will be
any changes.
Milestone 1 | 14th March - 1st April 2022
● SSO Implementation
SSO login
External Authentication using OAuth
on the event registration after the attendee is
authenticated He/She will redirect back to the further
registration of event
Milestone 4 |2nd May - 13th May 2022