Lec 8 Schedule Updating and Project Control
Lec 8 Schedule Updating and Project Control
Control
1
Schedule updating
Schedule updating is just one part of the project control process.
2
What is an updated schedule?
A revised schedule reflecting project information at a given data
date regarding completed activities , in progress activities , and
change in the logic , cost , and resources allocated at any level .
3
Why Update Schedules?
a. Unintentional events
b. Intentional changes
4
What kind of information is needed for updating
schedules ?
1. Past information : what has happened since the last
update ?.
B. user’s changes
5
Frequency of updating
Construction schedules may be updated monthly ,
biweekly, weekly, or according to another time
interval .
6
Effect of adding or deleting activities on
logic
An activity in a schedule is usually like a link in a chain ; removing a
link may disturb the whole chain if it is not done properly.
For example :
Deleting activity AS250 in the partial network shown in figure will remove any link
between activities in each side.
AS210
TL160
AS250
AS245 AS260
7
It is strongly recommended that the scheduler review the
logic before making any change by first printing a logic
report showing all predecessors and successors for the
activity be deleted.
8
Steps for Updating a Schedule
9
2. The PM (or superintendent) fills up the form, signs and dates it;
and submits it back to the scheduler
3. The scheduler enters the info in the computer and updates the
project, signs and dates the forms
10
4. The scheduler prints a preliminary report and discusses it
with the PM
11
Project Control
12
Project Control
Project control is the continuous practice of
1. monitoring work progress,
13
Why Project Control?
14
What is a baseline schedule?
15
Percent Complete
Activity
Project
16
Major objectives for a good control plan:
17
Where do project control lie in the project life cycle phases?
18
Level of Control
Detailed network
Reporting mechanism
Detailed network
Summary network
19
How Monitoring of the Project can be done?
1. Feedback from direct contact
Efficient but requires close cooperation between the manager
and field personnel.
20
4.Feedback from bar chart.
21
22