Planning & Research

Development Department
Management Meeting
May 27, 2022
TGR-Commercial
TGR-Benasa
PROJECT ACCOMPLISHMENTS as
of May 27, 2022

Planning & Research Development


Department
Management Meeting
May 27, 2022
PROJECT
ACCOMPLISHMENTS
as of
Status of Units

Total No. of Units: 692 units


Sold Units: 424 units
Turnover Units: 257 units
Move-in: 118 units
Regular Occupants: 19 units
50
Accomplishment as of May 26, 2022 (%)
44.79
45
41.79
40

35

30
27.28
25.65
25
21.44
20 19.34
17.72
16.02 16.4
15.27
15

10

0
Civil & Arch. Electrical Plumbing & Sanitary Fire Protection Mechanical

Actual Projected
Civil &
Architectural
Works
CHB Works

Installation of 1st
Layer:
• 17F in-progress
CHB Works

CHB Laying:
• 16F in-progress
Plastering Works

Interior Walls:
• 15F in-progress
Rub Concreting Works

Ceiling & Column:


• 16F in-progress
Precast Works
Fabrication of Formworks & Rebar works:

• 21F in-progress
Precast Works

Concreting Works:
Precast
• 2F to 20F
completed.
Cast back
• 2F to 12F
completed.
Precast Works

Installation Works:
• 8F to 17F
completed.
Lightweight Panel

Installation Works:
• 8F to 11F in-
progress.
Lightweight Panel

Plastering Works:
• 8F to 11F in-
progress.
Kitchen Counter Top

Formworks & Rebar


works:
• 15F in-progress.
Kitchen Counter Top

Concreting works:
• 12F in-progress.
Zocalo at Toilet Entrance

• 8F-9F in-progress
• 10F-11F completed
Concreting Works
Fire Protection
Works
Crossmain

Roughing ins:
• GF to 4F, 8F to
18F completed
Branchline

Roughing ins:
• GF to 3F, 8F to
18F completed
Sanitary/
Plumbing
Works
50mm PVC Vent Line

Installation:
• GF to 17F
completed
• 18F in-progress
15mm G.I. Cold Waterline

Roughing-ins:
• GF to 17F
completed
• 18F in-progress
Sanitary & Wasteline

Roughing-ins:
• 3F to 17F
completed
• 18F in-progress
Soil Stack & Vent Stack

Roughing-ins:
• 8F to 17F
completed
• 18F in-progress
Electrical
Works
Junction Box & PVC Droppings

20F in-progress
Box Setting

• 17F
in-progress.
Panelboard Box

Installation works:
1. Residential
• 16F in-progress
2. Commercial
• Units 1,7-9, and
17 completed.
Mechanical
Works
75mm PVC Exhaust Pipe

Installation:
• 16F in-progress
• 8F-15F
completed
STP Exhaust Pipe

On going
installation.
Waterproofing
Works
Hot Process Applied Membrane

Installation:
• 11F in-progress
THE END