Development Department
Management Meeting
May 27, 2022
TGR-Commercial
TGR-Benasa
PROJECT ACCOMPLISHMENTS as
of May 27, 2022
35
30
27.28
25.65
25
21.44
20 19.34
17.72
16.02 16.4
15.27
15
10
0
Civil & Arch. Electrical Plumbing & Sanitary Fire Protection Mechanical
Actual Projected
Civil &
Architectural
Works
CHB Works
Installation of 1st
Layer:
• 17F in-progress
CHB Works
CHB Laying:
• 16F in-progress
Plastering Works
Interior Walls:
• 15F in-progress
Rub Concreting Works
• 21F in-progress
Precast Works
Concreting Works:
Precast
• 2F to 20F
completed.
Cast back
• 2F to 12F
completed.
Precast Works
Installation Works:
• 8F to 17F
completed.
Lightweight Panel
Installation Works:
• 8F to 11F in-
progress.
Lightweight Panel
Plastering Works:
• 8F to 11F in-
progress.
Kitchen Counter Top
Concreting works:
• 12F in-progress.
Zocalo at Toilet Entrance
• 8F-9F in-progress
• 10F-11F completed
Concreting Works
Fire Protection
Works
Crossmain
Roughing ins:
• GF to 4F, 8F to
18F completed
Branchline
Roughing ins:
• GF to 3F, 8F to
18F completed
Sanitary/
Plumbing
Works
50mm PVC Vent Line
Installation:
• GF to 17F
completed
• 18F in-progress
15mm G.I. Cold Waterline
Roughing-ins:
• GF to 17F
completed
• 18F in-progress
Sanitary & Wasteline
Roughing-ins:
• 3F to 17F
completed
• 18F in-progress
Soil Stack & Vent Stack
Roughing-ins:
• 8F to 17F
completed
• 18F in-progress
Electrical
Works
Junction Box & PVC Droppings
20F in-progress
Box Setting
• 17F
in-progress.
Panelboard Box
Installation works:
1. Residential
• 16F in-progress
2. Commercial
• Units 1,7-9, and
17 completed.
Mechanical
Works
75mm PVC Exhaust Pipe
Installation:
• 16F in-progress
• 8F-15F
completed
STP Exhaust Pipe
On going
installation.
Waterproofing
Works
Hot Process Applied Membrane
Installation:
• 11F in-progress