Professional Documents
Culture Documents
CPM - Pert Analysis
CPM - Pert Analysis
Managerial Approach
Chapter 8 – Scheduling
Scheduling
• Definition.: A schedule is the conversion
of a project action plan into an operating
timetable.
• Is the basis for monitoring and controlling
project activity.
• Taken together with the plan and budget,
it is probably the major tool for the
management of projects.
21-1
Network Techniques: PERT and CPM
51-1
Network Techniques: PERT and CPM
• Advantages
– Can visualize task relationships.
– Facilitates CP (Critical Path) Calculation
– Can see impact of decisions on downstream activities.
• Disadvantages
– May be complex, not easy to understand at a glance.
61-1
Scheduling Terminology
• Activity - A specific task or set of tasks that are
required by the project, use up resources, and take
time to complete.
• Event - The result of completing one or more
activities. An identifiable end state occurring at a
particular time. Events use no resources.
• Network - The combination of all activities and
events define the project and the activity
precedence relationships.
71-1
Scheduling Terminology
91-1
Drawing Networks
• Activity-on-Arrow (AOA) networks use arrows to
represent activities while nodes stand for events
• Activity-on-Node (AON) networks use nodes to
represent activities with arrows to show
precedence relationships
• The choice between AOA and AON
representation is largely a matter of personal
preference
101-1
AOA (Activity on Arrow)
Network Building Blocks
AON AOA
111-1
AOA (Activity on Arrow)
Network Building Blocks
AON AOA
121-1
AOA (Activity on Arrow)
Network Building Blocks
Any activity must have its source in one and only one node. If two activities
occur between the same two nodes, insert a “dummy node” & activity
w/duration 0.
131-1
Sample Input Information to a CPM Problem
(Action Plan)
Duration
Activity* Predecessor
(weeks)
A 14 Start
B 3 Start
C 3 A,B
D 7 B
E 4 C,D
F 10 E
Start E 4 F 10
B 3 D 7 Finis
h
Calculate:
Project Duration
Critical Path (CP)
Activities on CP
(AON): Letters indicate activities, Arrows indicate relations
151-1
The Critical Path (CP)
ES = 0 ES =
EF = 14
14 EF = 17
A 14 C 3 ES = ES =
17 21
EF = 21 EF = 31
Start E 4 F 10
B 3 D 7 Finish
ES = ES = 3
0 EF =
EF = 3 10
ES: Earliest (Possible) Starting
Time
EF: Earliest (Possible Finish Time
161-1
Determining Slack
•How much slack is there
•Where is it?
•How do you know?
•Why might you care?
171-1
Determining Slack
ES = 0 ES = 14
EF = 14 EF = 17
LS = 0 LS = 14 ES = ES = 21
LF = 14 LF = 17 17 EF = 31
EF = 21 LS = 21
A 14 C 3 LS = 17 LF = 31
LF = 21
Start E 4 F 10
B 3 D 7 Finis
h
ES = 0 ES = 3
EF = 3 EF = 10 Work Back . . .
LS = 7 LS = 10
LF = 10 LF = 17
Critical Activity
LS: Latest Starting
Time 181-1
LF: Latest Finish Time
Program Evaluation and Review
Technique (PERT)
What does Program Evaluation and Review Technique
(PERT) mean?
Program evaluation and review technique (PERT)
is a technique adopted by organizations to analyze
and represent the activity in a project, and to
illustrate the flow of events in a project.
PERT is a method to evaluate and estimate the
time required to complete a task within deadlines.
-PERT serves as an management tool to
analyze, define and integrate events.