Professional Documents
Culture Documents
Lec No - 6,7
Lec No - 6,7
Lec No - 6,7
OPERATION RESEARCH
1
Network analysis
2
PERT and CPM
3
PERT and CPM
4
PERT and CPM
5
PERT and CPM
6
PERT and CPM
7
NETWORK
8
Framework of PERT and CPM
9
Terminology
Activity
A specific or set of tasks required by the project
10
Terminology
Event
Outcome of one or more activities
11
Terminology
Network
Combination of all activities and events
12
Terminology
Path
Series of connected activities or between any two
events
13
Terminology
Critical path
Longest - Any delay would delay the project
14
Terminology
Slack/float
Allowable slippage for a path
15
The Project Network
16
Activity on Node & Activity on Arrow
Activity on Node
- A completion of an activity is represented by a node.
Activity on Arrow
- An arrow represents a task, while a node is the completion of a
task
- Arrows represent order of events.
17
Activity Slack
Latest time , TL , which is the latest time the event can occur
with out delaying the subsequent events and completion of
project.
18
Activity Slack
Difference between the latest time and the earliest time of an
event is the slack time for that event
19
Critical Path
20
Benefits of CPM/PERT
21
Questions Answered by CPM & PERT
Completion date?
On Schedule?
Within Budget?
Critical Activities?
How can the project be finished early at the least
cost?
22
23
Activity relationship
24
Activity relationship
25
Activity relationship
26
Dummy Activity
27
Dummy Activity
List of activities
28
Dummy Activity
29
Dummy Activity
30
Dummy Activity
31
Example
32
Example
Before starting any of the above activity, the questions asked would
be :
What activities must be finished before this activity can start"
could we complete this project in 30 weeks?
could we complete this project in 2 weeks?
One answer could be, if we first do activity 1, then activity 2, then activity
3, ...., then activity 10, then activity 11 and the project would then take the
sum of the activity completion times, 30 weeks.
“What is the minimum possible time in which we can complete this project ? “
33
Example
34
Example
35
Packages are available to determine the shortest path and
other relevant information.
36
Use Forward & Backward pass to determine
Project Duration & Critical Path
37
Use Forward & Backward pass to determine
Project Duration & Critical Path
38
Use Forward & Backward pass to determine
Project Duration & Critical Path
39
Use Forward & Backward pass to determine
Project Duration & Critical Path
40
Example
41
Example solution
42
Example
43
Example solution
44
Example solution
45
Example
46
Example solution
47
Example
48
Example solution
49
Example
50
Example solution
51
Make a Network Diagram
52
Example solution
53
Example
54
Example solution
55
Questions??
56
Exercises
Ex. 1
Draw a PERT Network, Identify Critical Path and
Calculate Critical Time.
57
58
59
Exercises
Ex. 2
Take a Real World or Hypothetical Project, Identify
60
Limitations to CPM/PERT
61
Gantt chart
62
A Gantt chart, commonly used in project management, is one of the most popular
and useful ways of showing activities (tasks or events) displayed against time. On
the left of the chart is a list of the activities and along the top is a suitable time
scale. Each activity is represented by a bar; the position and length of the bar
reflects the start date, duration and end date of the activity. This allows you to see
at a glance:
What the various activities are
When each activity begins and ends
How long each activity is scheduled to last
Where activities overlap with other activities, and by how much
The start and end date of the whole project
To summarize, a Gantt chart shows you what has to be done (the activities) and
when (the schedule).
Gantt chart
Advantages Limitations
- Gantt charts are quite commonly used. - Do not clearly indicate details regarding
They provide an easy graphical the progress of activities
representation of when activities (might)
take place. - Do not give a clear indication of
interrelation ship between the separate
activities