Professional Documents
Culture Documents
Part 4 Workshop
Part 4 Workshop
Part 4 Workshop
Management reform
DJBM must issue an instruction redefining the “Conditions of
Contract” rules under which
7 Work requiring Holding Point approval, may proceed only after approval of the
work Request by the Supervision Team except that work may proceed if the
Supervision team fails to respond within the time defined by ……….
8 Submit all Work Requests sufficiently in advance of the time at which work is
required to start, to allow timely approval. (timely approval is defined as approval that
does not cause any delay to the works)
The Solution: Quality Management reform
The Supervision Engineer must
1. Systemic issue: Not approve any further work requests for the systemic issues defined by Director
JBH letter of 29 July 2022 unless comprehensive Method of Work reforms have been agreed and
implemented. (Annex 4):
2. Timeliness of response: Not unreasonably delay the response to any Work Request.
3. Avoidance of delay: Undertake all duties efficiently so as to minimise delay
4. Holding Point approval: Before approving any Work Request:, assess the contractors readiness to
carry out the work, assess weather conditions, assess all relevant test results, (reference may be
made to the Check Lists provided as Annex 2)
5. Surveilance or Witness Point inspections: Undertake Inspections as work proceeds of matters not
subject to Holding Point inspection, to ensure contract compliance.– Annex ..)
6. Covering preceding work: Not permit any work to proceed that will cover up or prevent any
necessary corrective action of preceding works
The Solution: Quality Management reform
The Supervision Engineer must
7 Test frequency: Ensure that all specified tests are undertaken at the specified frequency or at an
agreed and appropriate frequency if no frequency has been specified
8 Stoppage of works: Instruct corrective action or stoppage of work if necessary to correct a non
conformity. Stoppage of work is required when continued work would either bury non conforming work
or would also be non conforming
9 NCRs: Issue NCRs for matters requiring corrective action and not immediately corrected and to
monitor the close out of those corrections
10 Timliness of test results: Require that all routine specified or requested test results are made available
on the same day or in the case of tests requiring several days to complete, within that period from the date
requested. Therefore off site tests will not be permitted for routine tests.
End Part 4 - terima kasih