Professional Documents
Culture Documents
Project Planning & Controls rEV. 2
Project Planning & Controls rEV. 2
Project Planning & Controls rEV. 2
By VIJAY KAMBLE
1. INTRODUCTION
1. WHY PLANNING IS IMPORTANT ?
Technical Baseline
Systematic Approach Schedule Baseline Cost Baseline Identifies the responsibility holder Identifies project critical areas Identifies progress trends Control Procedures Built up confidence / morale Acts as a catalyst in stakeholders co-ordination Basis for Project Success Works as a challenge / motivation
2.
Cost Budgeting
Procurement
Procurement Planning Risk Identification Solicitation Planning Qualitative Risk Analysis
Human Resource
Organisational Planning Quantitative Risk Analysis Staffing Planning Risk Response Planning
Communication Risk
3. PROJECT MANAGEMENT
Project Management is defined as a process of initiating, planning, organizing, monitoring and controlling the organization / other resources in order to complete the PROJECT within contractual time period within allocated budget to the satisfaction of client. Project is defined as a temporary endeavor undertaken, which is having definite start and finish dates. Generally Project requirements include, Completion of project / defined milestones within contractual completion dates. Completion of project within the budgeted man-hours and budgeted cost. Building up the customers/clients confidence
J. Ray McDermott Middle East, Inc.
3. PROJECT MANAGEMENT
SAMPLE GENERIC PROJECT LIFE CYCLE
Scope / Efforts
Initial Phase
Intermediate Phase
Final Phase
TIME
Each Project phase normally include a set of defined deliverables designed to establish the desired level of management control The phase cycles generally involves some form of technology transfer or handoff such as requirements to design, construction to operation or design to manufacturing The project phases may sequentially linked or they may overlap. Overlapping project phases is called as Fast Tracking. The project phase varies with projects.
J. Ray McDermott Middle East, Inc.
3. PROJECT MANAGEMENT
PROJECT LIFE CYCLE FOR EPIC CONTRACT
100% Procurement, Sub-Contracts Feasibility, Initiation, Planning, Design Fabrication, Construction, Testing, Logistic Installation, Commissioning, Close-out
Cumulative Progress
TIME Generally, During Phase-1, the feasibility of project is evaluated, the transfer of as bid documents and details to project manager takes place along with detailed planning and cost finalization. All the stakeholders are agreed on to the liabilities and timely completion of their responsibilities which is also called as Kick-Off. This also consists of the planning and designing the contractual requirements. Completion of designing of the project requirements may or may not get overlapped by next phase-2, during which, the procurement of the materials and placing of sub-contracts for various works is carried out and the receipt of all necessary material to start the fabrication / construction activities. The next project phase-3 witnesses the receipt of all materials and other services from sub-contractors to complete the fabrication / construction of the final product to make it ready for load out / installation. The final phase-4 witnesses completion of installation and commissioning of the product / systems to the requirements of clients and closing out of the project.
J. Ray McDermott Middle East, Inc.
3. PROJECT MANAGEMENT
Project Management calls for : Working as a Team keeping single goal in mind e.g. completion of project within provided time frame within budgeted cost. Building up good rapport with client from long term prospects. Effective use of historic data and creating new data for future use. Adhering to the commitments made to client / customers / vendors / sub-contractors Maintaining the quality and standards set by the company Increasing the expertise and knowledge of various new areas
J. Ray McDermott Middle East, Inc.
Project Planning & Constrols
3 1
ADM Arrow Diagramming Method
2 7 8 9 0
Act1
Act2
Act3
Act4
Act5
Act11
Act7
Act8
Act9
Act1 (10)
Start : 1/4/04 Finish: 10/4/04
Act3 (5)
Start : 16/4/04 Finish: 20/4/04
Act1 (10)
Start : 6/4/04 Finish: 15/4/04
Act3 (5)
Start : 16/4/04 Finish: 20/4/04
Act2 (15)
Start : 1/4/04 Finish: 15/4/04
Act2 (15)
Start : 1/4/04 Finish: 15/4/04
Act1 (10)
Start : 1/4/04 Finish: 10/4/04
Act2 (15)
Start : 11/4/04 Finish: 25/4/04
Act3 (5)
Start : 11/4/04 Finish: 15/4/04
Act3 (5)
Start : 16/4/04 Finish: 20/4/04
5. REPORTS
AZERI PROJECT PHASE-II DESIGN ENGINEERING PROGRESS
Microsoft Excel Worksheet
Mar-04 ACTIVITIES GENERAL EXECUTION PLANS & OIL RISK STUDIES 30" P-II OIL TRANSPORT PIPELINE WEST AZERI INTERFIELD PIPELINES EAST AZERI INTERFIELD PIPELINES PHASE-II SUBSEA STRUCTURAL DESIGN % WEIGHT 15.04% 21.57% 24.94% 28.07% 10.38% WEEKLY PLAN % EARN % CUMMULATIVE PLAN % 100.00% 100.00% 100.00% 100.00% 100.00% EARN % 89.72% 97.96% 100.00% 100.00% 100.00%
TOTAL
100.00%
100.00%
98.01%
Engineering Management, Administration & Control PROGRESS BY - LINE ACTIVITIES 30" P-II OIL TRANSPORT PIPELINE WEST AZERI INTERFIELD PIPELINES EAST AZERI INTERFIELD PIPELINES %
100.00%
5. REPORTS
AZERI PROJECT PHASE-II DESIGN ENGINEERING PROGRESS / MANHOURS STATUS ACTUAL PROGRESS % Activit y ID Activity description Man Hrs % Weight Original duration PLANNED PROGRESS % WEIGHTED DELTA
14-Mar-04
TOTAL
14-Mar-04
TOTAL
10520 6 7 8 9 10
PIPELINE MECHANICAL DESIGN Bottom Roughness Analysis - CAL 30 inch Phase 2 Pipeline Design Report - REP 30 inch CP Design - TEC Stability Analysis (CAL & TEC) 30 inch Anode Details - DTL CUMMULATIVE PROGRESS %
0.57% X%
98.01%
5. REPORTS
(A) MANHOURS SUMMARY DISCIPLINE PLANNED MHRS EARNED MHRS ACTUAL MHRS As on : PRODUCT IVITY 14-Mar-04 EXPECTED AT COMPLN (+/-)
3,750 Engineering Management, Administration & Control Lead Engineer (LE) 2,800
3,750
4,093
4093
343
2,748
2,453
0.89
2506
(295)
Engineer (EE)
4,213
4,188
5,102
1.22
5126
914
1,748
1,726
1,099
0.64
1121
(627)
Draftsman (DF)
4,112
4,089
4,418
1.08
4441
329
Material/Corrossion Specialist
225
212
84
0.40
97
(128)
TOTAL
16,847
16,712
17,249
1.03
17383
536
5. REPORTS
5. REPORTS
5. REPORTS
MS-EXCEL
Activity ID Act1 Act2 Act3 Act4 Act5 Act6 Act7 Act8 Act9 Act10 Act11 Start
Description Static Pipelay Analysis Internal Review (SPA) Clients for Review (SPA) Approved for Construction (SPA) Weld Repair Analysis Internal Review (SPA) Clients for Review (SPA) Approved for Construction (SPA) Dummy Activity - 1 Completion
Duration 0 15 2 7 7 7 2 7 7 0 0
Predecessor FS1 FS2 FS3 FS4 FS3 FS6 FS7 FS8 FS5 FS9,FS5
3 1 2
ES: 1/4 EF: 1/4 ES: 1/4 EF: 15/4
5
ES: 18/4 EF: 24/4 ES: 25/4 EF: 1/5
7
ES: 25/4 EF: 26/4
8
ES: 27/4 EF: 3/5
9
ES: 4/5 EF: 10/5
0
ES: 10/5 EF: 10/5
Early Start and Early Finish Date - Computation Forward Pass Method
3 1 2
LS: 1/4 LF: 1/4 LS: 1/4 LF: 15/4
5
LS: 27/4 LF: 3/5 LS: 4/5 LF: 10/5
7
LS: 25/4 LF: 26/4
8
LS: 27/4 LF: 3/5
9
LS: 4/5 LF: 10/5
0
LS: 10/5 LF: 10/5
Late Start and Late Finish Date Computation Backward Pass Method
Act4
ES:18/4, EF:24/4 LS:27/4, LF:3/5 FF: 0 TF: 9
Act5
ES:25/4, EF:1/5 LS:4/5, LF:10/5 FF: 9 TF: 9
Act1
ES:1/4, EF:1/4 LS:1/4, LF:1/4 FF: 0 TF: 0
Act2
ES:1/4, EF:15/4 LS:1/4, LF:15/4 FF: 0 TF: 0
Act3
ES:16/4, EF:17/4 LS:16/4, LF:17/4 FF: 0 TF: 0
Act6
ES:18/4, EF:24/4 LS:18/4, LF:24/4 FF: 0 TF: 0
Act7
ES:25/4, EF:26/4 LS:25/4, LF:26/4 FF: 0 TF: 0
Act8
ES:27/4, EF:3/5 LS:27/4, LF:3/5 FF: 0 TF: 0
Act9
ES:4/5, EF:10/5 LS:4/5, LF:10/5 FF: 0 TF: 0
Act11
ES:10/5, EF:10/5 LS:10/5, LF:10/5 FF: 0 TF: 0
8-10 hrs/day
120 28 56 28 -
8-10 hrs/day
16 16 -
8-10 hrs/day
16 28 16 28 -
8-10 hrs/day
4 28 56 4 28 56 -
TOTAL
528
232
32
88
176
Budgetary Allocations
TOTAL Manhours Cost 528 33,000 PE 232 17,400 FE 32 2,400 Management 88 8,800 Administration 176 4,400
PIPELAY ANALYSIS Static Pipelay Analysis Static Pipelay Analysis Internal Review Client Review Approved for Construction Weld Repair Analysis Weld Repair Analysis Internal Review Client Review Approved for Construction TOTAL 7 2 7 7 56 36 56 84 528 10.61% 6.82% 10.61% 15.91% 100.00% 45.45% 32.20% 100.00% 0 0 0 0 240 0 0 0 0 170 0 0 0 0 180 1.06 56 36 56 84 538 0 0 0 0 10 15 2 7 120 36 28 22.73% 6.82% 5.30% 100.00% 100.00% 100.00% 100.00% 100.00% 50.00% 120 36 28 120 36 14 150 10 20 1.25 0.28 1.43 150 10 34 30 -26 6
112
21.21%
112
1 VO043 2 3 VO028
10850
Additional tie-in analysis for WA & EA Spool @ C&WP East Azeri & West Azeri FO/Power Cable Study
800
690
S -
10910 10920
C 335 O
572 31
Phase 3 Support Valve Gear Box Development Recovery Frame (Dantorque actuator installation frame for subsea installation ) East Azeri pipeline global buckling study using FE analysis 30" Phase-2 pipeline additional crossing (SOCAR DU500) KP 8 tie-in spool for Phase-2, 30" export pipeline (see IR6, Detail Design and Fabrication of a tie in spool) Exension of shore approach burial from 5m to 7m WD Revised Crossing Design to suit DSV installation WA Infield Pipeline Crossings TOTAL
10930
600
320
A3 issued
10960
200
6 VO043
11010
50
10980
300
108
A3 issued
8 9
S S
100 300
C O
207
10
200 2885
239 2258
8. FEATURES OF PRIMA-VERA
PRIMARY GOALS OF PROJECT TEAM / MANAGEMENT 1. TO COMPLETE PROJECT IN TIME, WITHIN BUDGETED MANHOURS AND WITHIN BUDGETED COST PROFIT MAXIMISATION AS BID PERFORMANCE
2. 3.
PROJECT SPECIFIC INFORMATION FLOW CAN BE GROUPED AS : 1. 2. 3. TOP MANAGEMENT MIDDLE MANAGEMENT OPERATING LINE MANAGEMENT
8. FEATURES OF PRIMA-VERA
TOP MANAGEMENT Information related to Progress Trends, Productivity, Cash Flow, Payment Received, Expected Profit MIDDLE MANAGEMENT Information for Monitoring, Controlling Project Activities OPERATING LINE MANAGEMENT Information for day to day work related activities for operating usage
Purpose
Information Preferred
Overall Progress Productivity Report Cash Flow Statement Manhours / Cost - TO GO Executive Summary Milestone Status Financial Status Areas of Concern
List of Activities, Start & Finish Dates, Floats Bar Charts / Gantt Chart Progress Measurement Model Weighted Delta Summary Productivity Report Target Vs Current Progress (Slippage of activities) List of Critical Activities List of nearly critical activities Project Likely Completion Date Look ahead Schedules Resource / Manhours Loading Data (to check Manhours Overloading) Resource / Manhours Consumption Data Projected Resource / Cost data
List of Activities with relevant details Look ahead Schedule List of activities with slippage in progress List of Critical Activities
8. FEATURES OF PRIMA-VERA
WBS List Activities, Define Durations & Relationships
SET Global Calendar Other Specific Calendars Activity Codes Cost Accounts
RESOURCES Define Resources Assign Units, Calendar, Limits for Unit resources, Price / Cost per Unit
8. FEATURES OF PRIMA-VERA
OUTPUT 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. Bar Chart / Network Diagram Early / Late Start & Finish Dates Free Float & Total Float List of Activities List of Critical / Near Critical Activities Target Vs Current Schedule Look Ahead Schedule Resource Profile / Table (to know resource overloading) Projected Resource / Cost S-Curve Level 0, 1, 2, 3, Schedules Earned Value Report Manhours / Cost Histogram Productivity Report Likely Completion Date Details Resourcewise Activity List and Vice Versa
Adobe Adobe Adobe Adobe Adobe Adobe
8. FEATURES OF PRIMA-VERA
OTHER FEATURES 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Resource Crashing Splitting of Activity Compatibility with any RDBMS data User Friendly Excellent for Presentation Data Multi Project Links Single Resource data linked to multi project requirements Supplementary Packages such as Monte-Carlo analysis, Time Sheet System Different activity types : Task, Independent, Meeting, Milestones, Flags etc Independent setting of individual resource calendars Different resource profile curves such as Bell Shape, Linear, Triangular Filtering of Activities as per WBS Groups, Activity Codes Sub-Project Option for monitoring / controlling
THANK YOU..