Professional Documents
Culture Documents
Construction Supervision-Qc & Qa
Construction Supervision-Qc & Qa
Construction Supervision-Qc & Qa
CONSTRUCTION
SUPERVISION
QUALITY
ASSURANCE
&
QUALITY
CONTROL
By: ENGR. MANNY B. LAURESTA
QA & QC DEFINITION
QA = QC
QA & QC DEFINITION
Quality Control – QC
Quality Control – QC
QC is…
5
QA & QC DEFINITION
Quality Control – QC
QC is…
6
QA & QC DEFINITION
Quality Control – QC
QC is…
Quality Control – QC
QC is…
8
QA & QC DEFINITION
Quality management is a
QUALITY ASSURANCE much broader field. While it
includes quality planning, as
well as quality control and
quality assurance, it also
includes quality improvement
QUALITY
and extends beyond just QA
CONTROL
and QC to a systems
approach and looking at the
quality management system
as a whole.
QA & QC DEFINITION
18
Measurements on Site
Have an accurate
standard length marked
out on site for checking
tapes.
Breakdown irregular
areas into
fundamental shapes
for measuring
purposes
Measurement on Site
Examine weigh
tickets for all bulk
materials brought
onto site.
SAND
Sand to be used for concrete –
evaluate against ASTM and C-
33 AASHTO M6
Sand for block work mortar
and rendering – evaluate
against ASTM C 144 and
AASHTO M45
Sand for internal plastering –
evaluate against ASTM C 144
and AASHTO M45
Test sand against ASTM
standards.
Quality and Testing of Materials
AGGREGATES
Upon delivery, check for
correct size and grading for
cleanliness and see
segregation doesn’t occur
during discharge.
If possible keep two stock
piles of the fine aggregates
to use alternately
Don’t let stock piles mix
Don’t store the stock piles
under the tree if possible.
Aggregates must be
durable, clean and fee from
deleterious matter.
Quality and Testing of Materials
CEMENT
Unless provision is made for the
bulk storage of cement on site,
cement will be delivered in sealed
bags.
Normally all testing is carried out in
the manufacturers test lab and
each consignment should have a
test certificates. Quality Tests for Cement
Different types of cement must be 1. Loss on ignition
stored in different silos or sheds. 2. Magnesium oxide
Storage should always be in such 3. Sulfur trioxide
manner that the cement is used in 4. Insoluble residue
the same order as it is 5. Soundness
delivered/received.
6. Air content
Storage should be well ventilated, 7. Fineness
at least 6” above the ground, stack
not more than five high. 8. Specific gravity
9. Time of setting
Quality and Testing of Materials
WATER
Use only clean fresh
water
Well water must be
tested to ensure its
suitability before use.
If water is potable it is
usually suitable.
QC for TEMPORARY FACILITIES
27
QC for DEMOLITION
28
QC for EARTHWORKS
Documents
Review the approved plans, specifications, and the tests
and observations made and showing the Geotechnical
Engineer's report.
Note and record the equipment being used on site.
Sampling of Materials
Sample and verify that the following materials are
delivered to the Materials Engineering Laboratory
for any required testing:
Subgrade materials,
Native-fill materials,
Imported materials, and
Additive materials (lime, cement, sand,
pozzolan, etc.)
QC for EARTHWORKS
Testing
Perform soils classification and properties tests as required on
native and/or imported soils.
Perform laboratory moisture-density relationship tests or other
structural property tests as required.
Where applicable, conduct laboratory-testing program to determine
soils' properties resulting from admixtures such as cement or lime.
In the field, conduct in-place field density and moisture tests using
procedures specified in the contract documents. Frequency of
testing should be predetermined to allow for representative
coverage of each lift, while interfering as little as possible with the
earthwork operation's schedule.
Testing must be timely to avoid having to retest previously covered
work. Similarly, test methods should be predetermined so as to
take into account the Contractor's procedures and soil types.
Periodic sampling of materials in the field to verify continued
compliance with specification requirements is recommended.
30
QC for REINFORCING STEEL
Documents
Fabrication
Review the approved plans,
Check each shipment of
specifications, and approved
reinforcing steel for the
shop drawings.
following:
Review applicable sections of
Bar sizes and grades are
referenced codes, such as the
as specified
Building Code Mill marking is in
Mill Test Reports conformance with mill test
Verify reinforcing steel mill test reports
reports (when available) for mill Check for corrosion,
markings and test data, contaminants, surface
checking against project cracks and bars damaged
requirements . in shipment
Sample material for tests Check shop bends for
directly from unopened bundles specified radius and
when required by specifications cracks
QC for REINFORCING STEEL
Placement
During placement of reinforcing, check for proper bar locations, alignment,
laps, ties, form and ground clearance, supports, field bend radii and cracks,
gouges or tack welds causing stress concentrations, removal of
contaminants, and hardened concrete.
If welding of reinforcing is required, it should be observed with particular
emphasis on joint configuration, suitably of low hydrogen electrodes, preheat
and interpass temperatures, and interpass slag removal.
Prior to concrete placement, check for complete installation and notify
contractor of any variations form plans and specifications. If variations are
not corrected prior to start of concreting, immediately notify the design team
representative and PIU for appropriate action.
During concrete placement, check that reinforcing stays in place and is
adequately supported. Check for removal of dirt, concrete spatter, grease, or
other contaminants.
Check embedded items, including, anchorages, inserts, and bolts installed in
concrete for compliance to project documents. Verify they are solidly cast in
place during placement of concrete.
QC for READY MIX CONCRETE
Documents
Verify that the class of concrete
ordered is being delivered and
conforms to approved mix
designs.
Equipment
Check the trucks for worn out or damaged fins, excessive
buildup of hardened concrete, and for the presence of wash
water from the previous delivery.
Verify that load capacities are not exceeded.
Check the current "weights and measures” seal on scales.
Verify that the moisture-metering device is operable.
Verify that the scales start at and return to zero after each
weighing operation.
Verify that the metering devices for admixtures have been
calibrated recently and are operating.
QC for READY MIX CONCRETE
Materials, Storage and Handling
Visually check the sand and course aggregate for
method of storage, handling, source, grading,
cleanliness, and moisture condition.
Obtain samples of aggregates when specified or when
it appears that they may not conform to the required
gradation or cleanliness.
Obtain grab samples of cement and pozolanic
materials when required by project specifications.
Check the cement temperature.
For lightweight aggregates, check loose moist unit
weight regularly and verify whether the plant is making
proper adjustments to batch weights to compensate
for variations in weight as well as moisture.
QC for CONCRETE
Documents
Verify that the class of concrete delivered conforms with
specifications
Observation Procedures
Check forms for cleanliness and proper treatment prior to
placement.
Visually estimate the slump of each batch delivered and
perform slump tests regularly.
Determine concrete temperature, number of mixing
revolutions, and/or length of time since batching.
Observe placement procedures for evidence of segregation,
possible cold joints, displacement of reinforcement or forms,
and proper support of embedded items, anchor bolts, etc.
Inspect for proper compaction/consolidation.
QC for CONCRETE
Slumped
300 mm
Slumped concrete
sample
200 mm 39plate
Base
CURING OF CONCRETE
FORMWORKS
Forms are employed to mold
concrete to a desired shape and
smoothness as specified in the
plans.
They are constructed so that
concrete slabs, walls, and other
members will be of correct sizes,
dimensions, shape, alignment,
elevation and positions.
Forms should be checked for
tightness and bolding during pouring
operations and any loose tie wire or
bolts should be tightened.
REMOVAL OF FORMS
Grouting Observations
2. Seal filled containers with clean, dry, and tight fitting aids
1. Undisturbed Soils
are those obtained from the field with minimum disturbance
by using drilling equipment that provides clean hole before
insertion of thin walled tubes that is both the natural density
and moisture content are preserved as much as practicable.
soil samples are obtained for investigation to determined the
properties of the materials necessary for the design analysis
of a structure.
are those obtained from the field thru manual sampling on the point of
sources and or at stockpiles for investigation purposes and
construction materials for use in the road and other structures.
Take all the increments from the roadway for the full depth of the
material, taking care to exclude the underlying material.
Sampling from a Roadway Sampling from a Stockpile
REDUCING FIELD SAMPLES OF AGGREGATES TO TESTING SIZE
Mechanical Splitter
• METHOD B - QUARTERING
Apparatus:
1. Straightedge
scoop,
2. Shovel or trowel
3. Broom or brush
Shovel Straightedge scoop
& broom brush
Flattening Dividing
Quartered Sample
SAMPLING, TESTING AND INSPECTION REQUIREMENTS ON
MANUFACTURED, PROCESSED OR NATURAL PRODUCTS
PRE-TESTING
In case the result of the acceptance test is unsatisfactory, the supplier shall
have the option to request a re-test at his own expense. The delivered
material shall be re-sampled by authorized government representative in
the presence of the supplier or his representative.
MINIMUM REQUIREMENTS FOR SUBMISSION OF SAMPLES
Materials Minimum Testing Minimum Qty./Vol. of
Matl’s. Requirements for Sample
Submitted
1. Cement 1 Sample per 2000 bags 10 kg
8. Steel Pipe (Galvanized) 1 Sample per 500 m length 2 pcs. of 100 mm long
taken from both ends
w/o thread
9. Conc. Hollow Blocks 1 Sample per 10,000 units
13. Gabions 1 m x 2m
a. Classification 20 kg.
b. Routinary 50 kg.
c. Compaction &
CBR 50 kg.
mpling for Acceptance of Completed Asphalt Pavement
Significance :
Core drilling on the completed asphalt and concrete pavements is conducted
to determine the compliance of both pavement construction with design
specifications.
QAU - BRS Representative QAU - BOC/BOD Representative QAU - Regional Office Implementing Office Representative
Representative
QAU Form No.9
Date: June 08, 2013, Issue No.2
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY
MANILA
A B C D E F G H I J K L M
Standard Lab
Compacted
WEIGHT IN WEIGHT WEIGHT IN BULK DEGREE OF
AVERAGE Specimen
THICKNESS (cm) AIR SSD WATER SP.GRAVITY COMPACTION
SAMPLE ID STATION THICKNESS LAB DENSITY
(cm) (AASHTO T16)
H %
grams grams grams g/cc
1 2 3 4 I-J L/M x 100
QAU - BRS Representative QAU - BOC/BOD Representative QAU - Regional Office Implementing Office
Representative Representative
QAU Form No.7
Date: June 08, 2013, Issue No.2
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY
MANILA
Cross
Length/ Comp. Corr. Comp.
CORE SAMPLE Diameter Sectional Unit load Corr.
No. Height L/D Area Strength Strength Remarks
Factor
Identification Station/Location (Cm) (Cm) (Cm2) (KN) (Mpa) (Mpa)
1.
2.
3.
4.
5.
6.
7.
8.
9.
QAU - BRS Representative QAU - BOC/BOD Representative QAU - Regional Office Implementing Office Representative
Representative
QAU Form No.10
Date: June 08, 2013, Is s ue No.2
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY
MANILA
Thickness (Cm)
No. Station/Location of Test Pit Item 200 Item 201 Item 300 Remarks
Plan Actual Plan Actual Plan Actual
Prepared by:
Conformed:
Implementing Office
Representative
1
8 2
3
7
9
6 4
MATERIALS TESTING
Recognize the basic technologies in testing of construction
materials.
T. Urmaza
S. Orate CLARITA C. FLORES
J. Tagalo Engine e r V
J. B e rgonio
C. de la Cruz ATTESTED :
Witnessed by:
Const. Of 2 Storey RGR Type Sch. Bldg. At Dona Ma. Platon Laurel, Aya, Talisay, Bats.
Project : Const. Of Circumferential Road Around Lake Taal, Agoncillo, Bats.
Completion of Aya-Tranca-Talisay Road, Talisay, Bats.
Kind of material : Reinforcing Steel Bar ( 16 mm dia., deformed )
Sample identification : DMP- 5
Quantity represented : 10,000 kgs.
Sampled at : Stockpile at jobsite
Original source : Top Steel
Supplied by : Revere Construction & Supply
Proposed use : for concrete reinforcement
Spec's Item No. : PNS 49 Grade 275 NW
Sampled by : F. Opena,Lab. Tech. II DPWH-Bats. 3rd DEO 06-08-06
(Name & designation) (Office) (Date)
Submitted by : Ma. B. M. Marquez - do - 6-14-06
(Name & designation) (Office) (Date Received)
Lab. No. : 1718-06 ( Paid under OR No. 2595342 )
Witnessed by:
BUREAU OF RESEARCH AND STANDARDS
EDSA, Diliman, Quezon City
(Date)
REPORT ON CONCRETE MASONRY UNITS
: Construction of 2 Storey RGR Type Sch. Bldg. At Dona Ma. Platon Laurel, Aya, Talisay, Bats.
nit : Concrete Hollow Blocks (Non Load Bearing) 4" thick
epresented : 10,000 pcs.
t : Stockpile at jobsite
ource : Allied
y : REVERE Construction & Supply
use : for walling
m No. : ASTM C-129 ( Non- Load Bearing )
y : N. Magnaye Revere Cons't. & Supply 06-08-06
F. Opena,Lab. Tech. II DPWH-Bats. 3rd DEO 06-08-06
(Name & designation) (Office) (Date)
by : Ma. B. M. Marquez - do - 6-16-06
(Name & designation) (Office) (Date received)
: 1720- 06 ( Paid under OR No. 2595342 )
PLE I.D. TESTS REQUIREM ENTS RESULTS
T. Urmaza
A. Emperador CLARITA C. FLORES
J. Tagalo Engine e r V
J. Bergonio ATTESTED:
d by :
Department of Public Works And Highways
BUREAU OF RESEARCH AND STANDARDS
EDSA, Diliman, Quezon City
Project : Concreting of Road, Barangay II, San Carlos City, Negros Occidental
Sample identification : CRBII-01
Quantity represented : 2000 bags
Sampled at : Jobsite
Manufactured by : Taiheiyo Cement Phils., Inc., San Fernando, Cebu City
Brand : Grand Portland Cement
Supplied by : Kuntel Construction
Spec's Item No. : ASTM C-150
Sampled by : R.dela Cruz/J.Yanson DPWH-Neg. 1st EDO/Kuntel Const. 6-16-06
: (Name & designation) (Office) (Date)
Submitted by : N.A. Noble-Engr. III DPWH-Neg. 1st EDO Neg. Occ. 6-20-06
: (Name & designation) (Office) (Date received)
Lab. No. : 1741-06 (Paid under OR # 2595384)
TESTS REQUIREMENTS RESULTS
Magnesium Oxide (MgO), % 6.0 Max. 1.30
Sulfur Trioxide (SO 3), % 3.0 Max. 2.47
Loss on Ignition, % 3.0 Max. 4.70*
Insoluble Residue, % 0.75 Max. 1.10*
Air Content of Mortar, % 12.0 Max. -
Fineness : Amount Passing
No. 0.075 mm Sieve, % - 99
Autoclave Expansion, % 0.8 Max. 0.03
Time of Setting : Gilmore Test
Initial set, min. 60 Min. 120
Final set, min. 600 Max. 253
Compressive Strength, Avg. mortar
cubes, Mpa:
3 days 12.0 Min. 19.0
7 days 19.0 Min. 17.5
28 days 28.0 Min. 23.0
Specific Gravity - 3.09
REMARKS: * Sample fails to meet Specification requirements.
Tested by: Checked by:
P. Malonzo
B.A. Minano
E. Cruz CLARITA C. FLORES
E. Flores Engineer V
M. S. Gianan ATTESTED :
Witnessed by:
Republic of the Philippine s
Departme nt of Public Works And Highways
BUREAU OF RESEARCH AND STANDARDS
EDSA, Diliman, Que zon City
Witne s s e d by:
Tests:
1 – G, Grading Test
Minimum Testing
Requirements:
Tests :
Tests:
1 – F, Fractured Face
ITEM 300 – AGGREGATE SURFACE COURSE
Tests :
A. Aggregates
Tests:
1 – G, Grading Test
1 – Ext., Extraction
1 – Sty., Stability
1 – C, Laboratory Compaction
D. Hydrated Lime
1 – Q, Quality Test
E. Mineral Filler
F. Compacted Pavement
C. Course Aggregate
G. Steel Bars
Tests:
Five (5) holes per km per lane or five (5) holes per
500 m when two (2) lanes are poured concurrently.
ITEM 404 - REINFORCING STEEL
1 – Q, Quality Test
ITEM 405 - STRUCTURAL CONCRETE
A. Cement : Quantity : ( 40 kg./bag )
Class A ----------- 9.0 bags / m3 of concrete
Class B ------------ 8.0 bags / m3 of concrete
Class C ------------ 9.5 bags / m3 of concrete
Class P ----------- 11.0 bags / m3 of concrete
Tests: For every 2000 bags or fraction thereof :
1 Q, - Quality Test
B. Fine Aggregate
Quantity :
For Rounded For Angular
Class A --- 0.50 m3/m3 of conc. 0.54 m3/m3 of concrete
B. Fine Aggregates
Quantity : 0.17 m3/m3
Tests: For every 75 m3 or fraction thereof:
1 – G, Grading Test
C. Stone
Tests: Inspection Report
D. Water
Tests: 1 – Certificate from Project Engineer or
B. Fine Aggregates
C. Stone
D. Water
B. Rock Fill
Tests:
Tests:
104 (1) Emb. From Rd. Excavation cu.m. 659 GPC – 1, D-7
1O4 (2) Emb. From Borrow cu.m. 1657 GPC –1, D-17
105 (1) Subgrade Preparation sq.m. 21,808 GPC –3, D-44
200 (1) Agg. Subbase Course cu.m. 4811 GP-16, C-4, D-64,
Q-4, CBR-2
201 Agg. Base Course cu.m. 7474 GP-25, C-5, Q-5,
D -100, CBR-3
311 PCCP sq. m. 34,181
a. Cement bags 61,526 Q – 31
b. Fine Agg. cu. m. 3419 Q – 3, G- 46
c. Coarse Agg. cu. m. 5264 Q – 4, G-71
d. Steel Bars kg. 700 Q–1
e. Concrete cu. m. FS – 91 sets CB
f. Completed PCCP, 200mm. , thk. 5 – cores/km/lane
B. Inspection:
_________________________ _______________________
Materials Engineer Project Engineer
QUALITY WORDS TO LIVE BY
Quality means conformance, not elegance.
Qualityis an achievable, measurable,
profitable entity that can be installed once
you have commitment and understanding
and are prepared for hard work.
Quality
is needed because nothing is simple
anymore.
There is no such thing as the economies of
quality; it is always cheaper to do the job right
the first time.
QUALITY WORDS TO LIVE BY
Quality measurement is
only effective when it is Quality department/unit are
done in a manner that supposed:
produce information To measure and report
people can understand conformance
and see. Demand corrective action
The only performance Encourage defect
measurement is the cost prevention
of quality. Teach quality improvement
The only performance And act as the conscience
standard is zero defects. of the operation.
There is no such thing as
a quality problem.
Email Me at
mannylauresta@live.com
That’s all folks…
THANK YOU!