Professional Documents
Culture Documents
Jeldeti ZZZ
Jeldeti ZZZ
Jeldeti ZZZ
Fund:- ANRS
Consultant:-Amhara Design
and
Supervision Works Enterprise
(East Amhara Brach Office)
AUGEST/2014 E.C 1
Points of presentation
• Background
• Objective
• Hydrology study
• Head work design
• Cost estimation
• Conclusion and Recommendation
2
Project location
Administrative Location
• Region-Amhara Region
• Zone-Oromia special zone
• Woreda-Bati
• Kebele-Jeldeti
Geographic Location
• North: 1248905.35
• East: 601676.33 3
• Average Altitude: 1364.895 a.m.s.l
CONTINUED
4
Accessibility
Distance from Bahirdar to Head works site is 570km, out of this distance
545km on asphalt and 25km on weathered road.
Distance from Zonal town (Kemisie) to head work site 134km out of this
distance 109km on asphalt and25km on weathered road.
The weathered road needs cross structure like ford and culvert and some
part of the road needs maintenance for sustainable.
The weathered road from Jeldeti Kebele to site (about 5km) should be
5
widen because it is not enough for machinery and damp truck and
another 40m length needs road access.
Existing irrigation
7
Objectives of the project
To ensure food
security through Efficient utilization of
irrigation the resources.
development.
9
Water resources & measurement
14
Continued---
Consistency
Consistency of theof the
data data
series seriesstation
for Degan for degan station
• by double mass curve technique
No abrupt change in the curve, hence, consistency exist in the data series 15
Continued
16
No abrupt change in the curve, hence, consistency exist in the data series
Continued
No abrupt change in the curve, hence, consistency exist in the data series 17
Design rainfall
Gamble Powell distribution method for each station has been used for
the computation of design rainfall.
Rainfall distribution profile both through out the catchments area and
time has not yet modeled at the project site.
20
CONTINUED
21
2-2.4 62 71.5813 73.08 52.312 3.710 3.710 5 5.581 52.312
CONTINUED
Catchment data for further hydrology analysis
22
CONTINUED
Comm.
Rainfall,P
(mm) curve Differenc Direct Direct
RF number at e b/n runoff runoff
Duration/ Re -arranged codition raifall & cummalative increment,
D/ RF/mm/ III,N runoff /S/ ,R(mm) Ri (mm) Remarks
Qtotal
500.000
450.000
400.000
350.000
Descharge in m^3/se
300.000
250.000 Qtotal
Linear (Qtotal)
200.000
100.000
50.000
0.000
0 1 2 3 4 5 6 7
25
Duration in hour
Tail water depth computation
Slope by End area method
Average height (H) 0.258
Horizontal distance (L) 209.319
Average slope S =H/L 0.001
Slope by best fit method
Slope by best fit line Method
1366.000
1365.500 f(x) = − 0.0128938438284271 x + 1365.8450284296
1365.000 R² = 0.987421812606829
1364.500
elevation
1364.000
1363.500
1363.000
1362.500
1362.000
1361.500
0.00 50.00 100.00 150.00 200.00 250.00
chainge
1375.000
Elevetion,m
1370.000
Series1
1365.000
1360.000
1355.000
0 10 20 30 40 50 60 70 27
discharge,m/s
Tail water depth from the discharge-gage rating
curve/table
1370
1368
Elevetion,m
1364
1362
1360
0.00 200.00 400.00 600.00 800.00 1000.00 1200.00
discharge,m/s
28
Head work
Head work
Diversion
Intake (Bed bar) i.e.
Storage head work i.e. /distribution head
Prevent bed
Dam work (i.e. Weir or
fluctuations
barrage)
Weir
32
Continued
Topography of head work site
Head work site is 2-4 km from the main command area.
At the head work site, the river width=24m at the bottom
33
Detail Design Of Diversion Head Work
• weir height-H
• Elevation of command area =1366m
• Proposed length of the main canal, =280m
• Minimum river bed level at proposed headwork
site=1364.89m
Design • Main Canal full supply depth including free
board=0.6m
35
CONTINUED
The velocity head, ha is computed from the approach velocity as
shown below va
2
ha
2g
Where g: acceleration due to gravity = 9.81m/sec2
Va is Approach velocity determined by
Q
Va
Lxhd
• D/S HFL = highest flood level before construction • U/S profile for, X=-0.27He.
=RBL+TWD=1364.89+3.83=1368.72m.
• D/S TEL=D/S HFL + Ha=1368.72+1.5=1370.22m
• U/S HFL= 1364.89+2.2+3.779=1370.86m
• U/S TEL=U/S HFL+ Ha=1370.86+0.57=1371.43m
• Afflux= U/S HFL-D/S HFL=1370.86-1368.72=2.14m.
• However, in rocky formation a higher value of afflux
may permitted.
37
U/S face profile coordinates(X,Y)
Y=(0.724*(X+0.27Hd)^1.85)/(Hd^0.85)+0.126Hd-0.4315Hd^0.375*(X+0.27Hd)^0.625
It extends up to X= - 0.27Hd
X Y
0.00 0.00
-0.10 0.00
-0.20 0.01
-0.30 0.02
-0.40 0.05
-0.50 0.07
-0.60 0.11
-0.70 0.16
-0.80 0.21
-0.90 0.29
-1.020 0.476
D/S profile
38
0.0
Y, 0 0.01 0.03 0.06 0.11 0.16 0.23 0.30 0.39 0.48 0.58 0.69 0.82 0.95 1.08 1.23 1.39 1.55 1.73 1.91 2.10 2.19
CONTNUED
weir section
Series1 2.5 Logarithmic (Series1) Series3 vertical slope
2.0
1.5
y-axcis
1.0
0.5
0.0
-2.0 -1.0 0.0 1.0 2.0 3.0 4.0 5.0
-0.5
39
x-axcis
Stability analysis
0.16
Overturning
0.42
W3
Sliding
0.48
W1
0.65
W5
Tension And
Bearing Capacity Pw W6 W7
2.19
Ps
2.03
1.71
1.61
W2
W4 W8
0.96
Forces to consider W9
Water pressure (Pw). 1.02 1.00 1.00 1.00
1.09
Self weight (W). 40
5.11
Silt pressure (Ps).
Uplift pressure (Pu). Pu
CONTINUED
Static condition
Checking for sliding 2.67 ok!
Checking for overturning 2.65 ok!
Tension
41
CONTINUED
Dynamic Condition
Checking for sliding 8.01 ok!
Tension
0.00 ok! B/6=5.11/6=0.85
42
Scour depth determination
44
Stilling basin design
Still basin level fixation
a) Undepressed floor
45
Water jump depth > tail water depth
TWD $ JUMP Vs DISCHARGE
6.00
5.00
4.00
Elevation,m
Discharge Vs TWA
3.00
Discharge Vs JUMP
2.00
1.00
0.00
0.00 100.00 200.00 300.00 400.00 500.00 600.00
Discharge,m3/s
I. Hydraulic jump=5.16m
II. Creep length =19.7m
There for Taking into the geologic and river topography of the
head work,.
U/S floor length =L-(2d1 + b +2d2 +Ld) =-12.47 But, as per the
geological formation, 1.0m impervious floor length has been provided.
48
By Bligh’s theory
1.86 1.8
1.52 1.4
1.19 1.1
0.86 0.8
0.53 0.5
0.00 0.0
49
By Khosla's theory
Thickness, (t) by Khosla
t= h/(G-1.0)
Residual head
1.64 1.2
1.40 1.0
1.20 0.9
0.99 0.7
0.79 0.6
1.0 1.4
0.9 1.2
0.7 1.0
0.6 0.8
50
Outlet design
Under sluice
Ps1 Ps2 W1
W2
wall=6m
W3
0. 49
0. 10
54
1.20
2.10
C-20 cyclopian
concrete
0.80
D/S retaining wall(masonry)
55
Stability analysis
U/s Retaining wall
Moment about
HEIGHT Forces(KN) Lever arm toe(KN.m)
Horizont
5.0 Vertical al (m.) Stabilizing Disturbing
WIDTH
2.90
self weight(W1) 55 0.25 13.75
self weight(W2) 132 1.30 171.6
lateral earth pressure(Pa) 79.28 1.67 0.0 132.13
earth load on wall (Ps) 114 2.10 239.4
Total 301 79.28 424.8 132.13
SUMMARY OF BILLS
Bill
No. Description Unit Qty Unit price Total Amount
1 LS 1.00
General Items 4,680,294.25 4,680,294.25
10,613,171.6
2 LS 1.00
Head work 7 10,613,171.67
Total 15,293,465.92
VAT(15%) 2,294,019.89
58
Conclusion
59
Recommendation
61