Professional Documents
Culture Documents
Mba 641 Chapter Five
Mba 641 Chapter Five
Mba 641 Chapter Five
NETWORK DIAGRAMS
BASIC COMPONENTS OF NETWORK
DIAGRAM
RULES FOR DRAWING A NETWORK
TYPES OF NETWORK MODELS
PROJECT MANAGEMENT OVERVIEW
2
There are two project management technique :
1. Critical Path Method (CPM)
2. Program Evaluation and Review Technique
( PERT)
1.Critical Path Method
This is a diagrammatic representation which
shows the various activities in a project.
The aim of the CPA is to identify how those
activities link together and to show the critical
path or the sequence of activities where a
delay will result in the overall project being
delayed.
An activity is said to be critical if a delay in
its start will cause a further delay in the
completion of the entire project. 3
Cont…
The sequence of critical activities in a network is called the
critical path.
It is the longest path in the network from the starting event to the
ending event
defines the minimum time required to complete the project.
In the network it is denoted by double line. This path identifies
all the critical activities of the project.
Hence, for the activity (i,j) to lie on the critical path, following
condition must be satisfied.
a) ESi= LSi
b) EFi = LFj
c) ESj- LSi = EFj- LFi = tij.
d) Float time=0 4
The procedure of determining the critical path
Job
1-2 1-3 2-3 2-5 3-4 3-6 4-5 4-6 5-6 6-7
Durati
on
15 15 3 5 8 12 1 14 3 14
( days)
Required:
a) Draw an arrow diagram representing the project.
b) Find the total float for each activity.
c) Find the critical path and the total project
duration. 10
Drawing a network diagram
(15,20)
(0,15)
15 2
(26,27)
1 (27,30)
(15,18)
4 7
(18,26) 5
(26,40)
(0,15)
(40,54)
3
(18,30)
6
11
The total float for each activity
13
Drawing a network diagram
(32,37)
(0,15)
15 2
(36,37)
1 (37,40)
(15,18)
4 7
(18,26) 5
(26,40)
(3,18)
(40,54)
3
(28,40)
6
11
The following table given the calculation for critical path and total float.
Earliest Latest
15 0 15 0 15 0
1-2
1-3 15 0 15 3 18 3
3 15 18 15 18 0
2-3
2-5 5 15 20 32 37 17
8 18 26 18 26 0
3-4
3-6 12 18 30 28 40 10
4-5 1 26 27 36 37 10
14 26 40 26 40 0
4-6
5-6 3 27 30 37 40 10
15
Drawing a network diagram
5
(32,37)
(0,15)
15
2
(36,37)
1 (37,40)
(15,18)
4 7
(18,26) 5
(26,40)
(3,18)
(40,54)
3
(28,40)
6
11
3. The critical path
17
2. Project Evaluation and Review Technique
(PERT)
18
cont…
PERT method uses the following three
estimates.
1. Optimistic time estimate (to)
It is a time required for the completion of
an activity under optimum conditions.
2. Pessimistic time (tp)
It is a time estimate under worst conditions.
3. The most likely time estimate (tm)
It is the most probable amount that will be
required. 19
Formulas
Estimated duration:
Activity Optimistic Most likely Pessimistic
1-2 1 1 7
1-3 1 4 7
1-4 2 2 8
2-5 1 1 1
3-5 2 5 14
4-6 2 5 8
5-6 3 6 15 22
Having been provided with this information, let us
try to find the following facts;
A.Construct the net work diagram.
B. Find the expected duration and variance of
each activity
C. Find the expected duration of the project.
D.calculate the variance and standard deviation of
project length.
Supplement 13-22
2
1 5
6
3
4
Supplement 13-23
Estimated duration
Supplement 13-24
MANY
THANKS
Supplement 13-25