Modular LCD Installation Guidance

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 38

Modular LCD Installation Guidance

Jerry. Lu
Content

1 Modular Bracket Introduction

2 Installation Guidance

3 Trouble Shooting
1.1 Modular Bracket Introduction

Front Side
3
1.2 Modular Bracket Features

 Modular design, Easy assembly, Easy maintenance, Convenient future extension;

 The height of standard pedestal is 800mm or 1000mm; Other heights are customizable.

 Patented Bracket, 3-axis micro-adjustment: Vertical, Horizontal and back & forth,

Ensure the levelness and flatness of spliced screens;

 Structure diversity, including integrating LED, monitors or curved bracket, applicable for

different industries and environments;

 Adjustable anchor: micro-adjustment of the bracket height. Applicable for uneven

ground.

4
1.3 Bracket Material

 Main Material: High-quality cold-roll steel;

• Pothook: T3.0;
• Baseplate: T3.0;
• Pedestal and frame: T1.5-2.5;
 Surface, standard 3 steps: acid cleaning, phosphating and electrostatic spray;

• The temperature of electrostatic spray is 180-210°. Coating thickness is 80-100


micrometer.
• Customizable cathode electrophoretic coating primer if requiring high anti-
corrosion standard.
• Color customizable, (Default HIK black).
 High structure strength, support up to 55” 8x16, 6x10 Video Wall in real
application.
5
1.4 Modular LCD Installation Design Sketch

6
Content

1 Modular Bracket Introduction

2 Installation Guidance

3 Trouble Shooting
2.1 Installation Guidance

• Prepare for installation


1

• Bracket installation
2

• Screen body installation


3

• Tuning evenness and edge


4 joint

• System cabling
5

• System debugging
6

• Customer training and


7 acceptance

8
2.2 Prepare for installation

 Confirm with installation conditions


 Ground flatness, Weight capacity, Wall structure, (solid wall or hollow wall);
 Power supply ≥1KW at installation site, maximum power of the system shall be
1.5 times of video wall. To ensure installation process.
 Ensure construction security. Avoiding manual damage device.
 Clean and tidy. There’s enough installation space.
 Inspection
 LCD screen, Bracket quantity, Package verification;
 Check LCD screens quality after Unpacking;
 Devices shall be handed over to storage when customer don’t install instantly.

9
Carry the LCD Screens

me nded
e com
Un-r

Easy to Bend!

Carry Horizontally

m e nded
m
Reco

Stable
Carry Vertically

Note: Two people are required when carrying LCD Screens. hold and carry them at
same time with two hands. Clear space ahead for path of LCD screens.

10
LCD Checkup And Acceptance

 Acceptance Process
 One person holds LCD screen, another person plug in power and test.
 Test Procedures :
① Check if the screen can normally boot after plug in power;
② Connect to screen infrared remote controller, Press [TEST] button and check
if the screen display is normal or not, If it has bright line, broken screen and
liquid leakage, etc.

11
2.3 Bracket Installation

 Pedestal Installation
 Pedestal Inversion
 Baseboard Installation

12
Baseboard Installation

 Baseboard Installation
 Baseboard Assembly

13
Modular Shell Frame Installation

 Modular shell frame installation

Downside

 Notice:
 Distinguish the up and down side: The square hole of slider is
downward as the picture shows.
 Distinguish the forward and backward side: The side of shell frame
with wall hanging bar is forward direction.
14
Modular Shell Frame Installation

15
Modular Shell Frame Installation

 Modular Shell Frame Installation


 Junction Box Installation

16
Bracket Tie Bar Fixation

 Tie Bar Fixation

17
Modular Shell Frame Installation

 Working Sketch

18
2.4 Screen Body Installation

 Pot hook Installation

 Notice : Turn the adjusting screw below 1.5cm of hanging bar after finishing
pothook installation. Keep off bump against due to lack of reserved space when
installing screen.

19
Screen Body Installation

 Two people are in front of the screen and lift it up. And another person
shall be at back of bracket and cooperate. Hang the pot hook into
adjusting screw slot.

20
Screen Body Installation

 Micro-adjust the screen position:


 The screen should be tuned after spliced screen installation to ensure flatness
and perpendicularity.

Vertical Horizontal
Adjustment Adjustment

21
2.5 Flatness and bezel micro-adjustment

 After installing all screens, flatness and bezel micro-adjustment are required.

The method are similar to 2.4.

 Flatness micro-adjustment:

 Avoid uneven surface of the video wall;

 The screens shall be strictly 90° vertical, the difference shall be less than 2mm;

 The screens shall be strictly 180° horizontal, the difference shall be less than

2mm.

22
Flatness and bezel micro-adjustment

 Bezel Standard:
 Even bezel between screens, cross-shaped without dislocation;
 No squeezing between screens, the gap shall be strictly 0.6mm. Test standard:
a piece of A4 paper shall easily slide through.

23
Successful Installation Performance

Side Front

24
2.6 Cabling

 Control Cable
 Control cables are for loop output and splicing display, it transmit control
signals between screens, standard cables are network cable with RJ45
interfaces.

Screen 1 Screen 2

Screen 3 Screen 4

25
Cabling

 Video Signal Cable


 3 types: DVI/HDMI/VGA;
 Cable connection should follow screen sequence as the picture below
shows:

26
Cabling

 Power Cable

27
Cabling

 Cabling Rules:

 Signal cable and power cables shall be place separately to avoid

electromagnetic interference.

 The curving radius shall be more than 15 times of the cable diameter. Avoid

bending and squeezing of cables. Every 30cm of the cables shall have a bondage

to fix them.

 Both ends of the cables shall be marked with some tag for easy identification.

 Avoid exposing too many cables outside the brackets or twisting of the cables in

consideration of appearance and cable safety.

28
Successful Cabling Performance

29
2.7 System Debugging

 Screen ID Setting--:
Remote Controller;

 Setting Control Devices:


 Device connection;
 Device setting.

30
Content

1 Modular Bracket Introduction

2 Installation Guidance

3 Trouble Shooting
3.1 LCD Discard Issues

 LCD Discard due to improper installation


 Discard issues: Broken screen, liquid leakage, scratches due to improper
installation
 Broken screen and liquid leakage are not in RMA conditions.

Liquid
Leakage

Liquid
Leakage
Stripe Issues

 Stripes
 Horizontal/vertical stripes, blurry screens, color bars due to IC Circuit
Damage.

Horizontal
Stripe
Horizontal
Stripe
Stripe Issue Pictures

Vertical
Stripes
Horizontal
Stripes

Color
Bars
Color
Bars
3.2 Bad Pixel

 Bad Pixels
 Less than(including) 3 non-continuous bad pixels are acceptable quality.
 If more, discuss with customers for proper handling.
 Test method
 check the screens 1 meter away, if the bad pixel can’t be seen, it means the
screens are acceptable.

Bad Pixel
Bad Pixel
3.3 Light Leakage

 Sometimes light leakage is inevitable, improper shipment or installation can


cause light leakage.
 Two main reasons:
 Squeezing screens during installation;
 Uneven flatness, twisted screens.

 Maintenance:
 If leakage is caused by screen squeezing, adjust the gap between screens following
2.5;
 Or adjust the “L” shaped handle at the back of the screen frame, make sure the
screens are vertically even;
 After a while, the light leakage will disappear.
Light Leakage Picture

Light
Leakage
Thank you!