Professional Documents
Culture Documents
Regulatory Matters: Availability Based Tariff (ABT) and Deviation Settlement Mechanism (DSM)
Regulatory Matters: Availability Based Tariff (ABT) and Deviation Settlement Mechanism (DSM)
Date : 17.02.2022
EASTERN
REGION Area : 433680 SQ KMS
Population : 240 Million
WESTERNR Peak Demand :@ 23.45 GW
EGION :441 MU / Day
Area : 951470 SQ KMS
Population : 244 Million
Peak Demand : @58GW
:1180 MU / Day
Target by 2027:
SOUTHERN Installed Capacity: 685 GW
REGION Peak Demand : 520 GW
Area : 651000 SQ KMS
Population : 232 Million
Peak Demand : @45.6 GW
:966.5 MU / Day
March 2003
West synchronized NEW Grid
With East & Northeast
SR
North
All India Grid
East
West
31st Dec. 2013,
Northeast
South NEW & SR grid South
Grid
synchronized
Five Regional Grids Five Regional Grid
Five Frequencies One Nation - One frequency
Grid Operation and Control in India
Central
Formation of Electricity Policies and implementation of
Electricity
ACT and Policies through NPC, RPCs and NLDC –
Authority Consultants to MoP, GoI
Under
MoP, GoI
Operational
Commercial aspects
aspects
Inter State Regional Grid operations& Inter
National National Region / Cross Border Grid connections, Power
Power Load Exchanges. Regulatory Authority :Central
Committee Despatch Electricity Regulatory Commission (SERC)
(NPC) 1 No. (NLDC) 1 No.
OPEN ACCESS
- Nodal Agency
PLANNING INPUTS
- Based on operational
experience
Constituents of Availability Based Tariff mechanism
What is ABT and Why?
Grid problems till 2000 : Wide frequency deviations, uncontrolled drawal by states , undisciplined
generation (higher generation during night hours to achieve total generation targets , frequent
blackouts/ grid disturbances , grid voltage issues etc.
Inter – State ABT mechanism introduced at Central Level in 2001, namely Unscheduled Interchange
(UI) mechanism
Further, modified as Deviation Settlement Mechanism (DSM) since February 2014.
The Forum of Indian Regulators (FOIR) upon recommendations of its sub-committee acknowledged
that State Electricity Regulatory Commissions are competent to determine mechanism for
introduction of Availability Based Tariff mechanism at State level,
However, it needs to be ensured that Intra-State ABT mechanism is compatible with inter-State ABT
mechanism.
The clause 5.7.1(b) of National Electricity Policy (NEP) notified by Central Government mandates the
Appropriate Commissions to introduce Availability Based Tariff (ABT) mechanism at State level.
MERC introduced Intra-state ABT mechanism in Maharashtra vide order in case no 42 of 2005 dated
17th May, 2006 , however Generating companies were excluded from the settlement mechanism
Interim Balancing and Settlement Mechanism (IBSM) : October 2006.
Final Balancing and Settlement Mechanism (FBSM) : August 2011.
State Deviation Representation of State Grid & Settlements
= Actual -
Schedule Intra-state Generators InSGS
G G G G G
Import
From
National
Grid ISTS Generator
Transformers
Deviation Settlement
Mechanism ( Frequency Based) Transmission Lines,
Sub-stations
Transmission System InSTS & Interconnecting Transformers
Power
Transformers
Contracted Capacity of D1 D2 D3 D4
Drawl of D1 D2 D3 D4
UI settlement at
Transmission Bus
Unscheduled Interchange (UI) (UI)
Low 50 Hz High
Frequency Frequency
Discourag
Encourage
e
Generatio
Generatio
n
n
12
Concept of Deviation Price (erstwhile Unscheduled Interchange)
CS Schedule 2000 MW
State Load 12500
MW
State Gen
10000 MW CS Deviation
500 MW
If System frequency is below 49.7 Hz, the State has to pay at Rs 8.0 PU is Rs.10,00,000 in 15 minutes!
( Deviation of 500 MW in one block -- > Deviation charge Rs. 1 million )
13
Components of Tariff for MSPGCL units under present system
Technical Minimum
Capacity (MW) –
Presently 55% of IC
Actual
Generation
16
Key Definitions
“Declared Capacity” means, in relation to a generating Station, the capability to
deliver ex-bus electricity in MW declared by such generating Station in respect of
any time-block of the day as defined in the State Grid Code or whole of the day,
taking into account the availability of fuel and/or water, and subject to further
qualification in the relevant Regulation;
“Scheduled Generation” at any time or for a time block or any period means
schedule of generation in MW or MWh ex-bus given by the concerned Load
Despatch Centre;
“Deviation” in a time-block for a Seller means its total actual injection minus its
total scheduled generation and for a Buyer means its total actual drawal minus
its total scheduled drawal and shall form part of the State Energy Accounts to be
prepared by the State Load Despatch Centre;
Key Definitions
T
H
E
R
M
A
L
H
Y
D
R
O
Key Definitions
Session I-B
Introduction to DSM Regulations
Hon’ble Commission has issued the Deviation Settlement Regulations, 2019 for introduction of Deviation
Settlement Mechanism in Maharashtra , in line with CERC mechanism.
• DSM under these Regulations shall be applicable for all seller(s), including OA generators, captive generators
(excluding In-Situ captive generators) connected to Intra-State Transmission System but excluding wind and
• ‘Deviation’ in a time-block for Seller (i.e. generator) = Total actual injection – (minus) Total scheduled
generation.
• The Commission had proposed to implement this DSM Framework in phased manner by April 2020
considering implementation period of 12 to 15 months , to allow adequate time for all key stakeholders
including MSLDC for preparedness and to provide sufficient time to set up necessary hardware/software and to
• As per the original schedule, the Regulations was to become applicable from 1 st April, 2020.However due
to Covid-19 difficulties and as the DSM software was not stabilised the implementation was postponed.
MERC DSM Regulation 2019 for Intra-State ABT
• Deviation = Actual Injection - Scheduled Generation
• The price for the deviation i.e. Deviation Price or DSM vector is linked to Daily Area Clearing Price (ACP)
for the Power Exchange as daily published on NLDC (National Load Despatch Center website). This price will
be applicable for 50 Hz.
• Deviation Price rate changes daily . Ceiling for Cap rate is 394.35 paise/unit for domestic coal based units
and also APM gas based units.
15 min
Schedule
Issued
(MWh)
Payment by
Beneficiary at
PPA rate
Actual
Generation
24
DSM Price Vector
49.85 Hz
50.05 Hz 50.00 Hz
600
500
394.3
400
^ Applicable for MSPGCL
300 309.98
200
100
0
0
4 5 6 7 8
.8 9.8 9.8 9.8 9.8 9.8
9 .9 91 92 93 94 95 96 97 98 99 50 1 2 3 4
.0 0.0 0.0 0.0 0.0
5
49 4 4 4 4 4 49 49. 49. 49. 49. 49. 49. 49. 49. 49. 50 5 5 5 5
Tabular representation of Deviation and Additional Deviation Charges for Seller as per MERC DSM
Regulations
Over injection (Positive deviation) Under -injection (Negative Deviation)
Frequency band Within volume limit (12% Above volume limit (12% Within volume limit (12% of Above volume limit (12% of
of schedule or 50 MW of schedule or 50 MW schedule or 50 MW schedule or 50 MW whichever is
whichever is lower) whichever is lower) whichever is lower) lower)
50.05 Hz =< Actual freq. < 50.1 Zero DSM charge, No Zero DSM charge, No Zero DSM charge , No Zero DSM charge , No Additional
Hz Additional DSM charge Additional DSM charge Additional DSM charge DSM charge
No DSM charge will be computed if all the units under the tariff group are under Zero schedule shutdown
during the period.
-- For Additional DSM Rates in Table I of Annexure –II of MERC DSM Regulations (reproduced as Annexure –II with this Procedure) shall be
referred.
-- For Additional DSM Rates for under-injection by Gen. stations using Coal or Lignite or Gas supplied under APM Table II of Annexure –II of
MERC DSM Regulations
•Specific modalities for Intra-state Generators :
Continued..
•Specific modalities for Intra-state Generators :
•Total deviation for a station /unit over the day should not exceed 1% . In case of violation of this
limit, 20% additional charge of daily DSM is to be paid. – Yet to be notified
•No over-injection of electricity by any Seller shall be permissible when grid frequency is “50.1 Hz
and above”
•Additional condition for a change in sign of the deviation shall be met once every 6-time blocks by
Buyer/Seller, failing which, additional charges @20% of the Deviation Charges on daily base DSM
payable/ receivable as the case may be shall be levied for the duration of continuance of violation.
To illustrate, if a state entity has positive deviation from schedule, i.e. from 07.30hours to9.00 hours,
sign of its deviation from schedule shall be changed in the 7thtime block, i.e. 9.00 hours to 9.15 hours either
from positive to negative or from negative to positive. The additional Charge for violation of sign change
stipulation shall be leviable for each such violation during a day from the date to be notified separately by
the Commission.
•The issue regarding DSM charges being levied when the units are under “zero schedule shutdown” /
RSD was raised by MSPGCL. Thus Hon’ble Commission has modified the provision and now. When all
the units are under Zero schedule shutdown or RSD , there will be no DSM charge computed.
Continued..
Timelines for Scheduling and Despatch Procedure
Time
Responsibility From To Form No.
Lines
By 0600 Station wise ex-power plant MW and MWh Capabilities foreseen for the next Day ISGS WRLDC
Available on
Availability of ISGS Station wise ex-power plant MW and MWh capabilities
By 0800 WRLDC MSLDC WRLDC's
foreseen for the next Day
Website
Available on
Availability of ISGS Station wise ex-power plant MW and MWh capabilities
By 0830 MSLDC Beneficiary WRLDC's
foreseen for the next Day
Website
Sellers including RE
Unit-wise ex-power plant generation availability in MW and MWh taking into
By 0900 Generators MSLDC Form IS
consideration any outage of its generating unit for the next day.
connected to InSTS
By 0900 Consent for ISGS capacities by Beneficiaries Beneficiary MSLDC
By 0900 Consent for ISGS capacities by Beneficiaries to WRLDC MSLDC WRLDC
Consent for Beneficiary to the ISGS for quantum and duration of power for next
By 0945 WRLDC ISGS
day for sale in the market
QCA to upload Pooling Sub-Station wise and Buyer-wise day ahead Forecast and
By 1000 QCA. MSLDC Form IS
Abailable Capacity on 15-min time block basis
Buyers to upload Pooling Sub-Station wise and Buyer-wise day ahead Forecast
By 1000 Buyers MSLDC Form IS
and Abailable Capacity on 15-min time block basis for next day in MW and MWh
Full Transmission Open Access Consumers furnish detailed Drawal schedule on Form
By 1000 Full TOA consumers MSLDC
15 minutes time block basis for next day in MW and MWh IB/Form IS
By 1100 Preparation of Load Generation Balance and URS if any MSLDC On web site
Buyers and
By 1115 Target deshpatch Schedule for Seller and Target Drawal Schedule for Buyers. MSLDC Form 3S
Sellers
Time
Responsibility From To Form No.
Lines
By 1400 ISGS drawal schedule of Beneficiaries Beneficiaries MSLDC
By 1500 ISGS drawal schedule of Beneficiaries MSLDC WRLDC
Available on
By 1800 "Net drawal schedule" of the State in MW and MWh for the next day WRLDC MSLDC WRLDC's
Website
Sellers QCAs
Unit wise ex-bus generation revised availability in MW and MWh taking into
By 2000 connected to MSLDC Form IS-R
consideration any outage of its generating unit for the next day.
InSTS
Revised drawal schedule for next day against bilateral power and IPP requisition
By 2000 Buyers MSLDC Form IB-R
they have contracted in short term and long term basis.
By 2000 Revised ISGS Drawal Schedule by Beneficiaries Beneficiaries MSLDC
By 2200 Revised ISGS Drawal Schedule by Beneficiaries MSLDC WRLDC
By 2300 Final Load Generation Balance and URS available if any MSLDC MSLDC Website
Final targeted despatch schedules for Sellers and targeted drawal Schedules for MSLDC
By 2330 MSLDC Form No. 2S
Buyers. Website
Centralised MOD
MSLDC shall issue necessary despatch or curtailment instructions in accordance with
Centralised MoD principles for the state as whole, considering the grid parameters including
frequency, voltage, transmission line loading, substation loading conditions or State volume
limits to maintain the Load-Generation balance and comply with conditions stipulated under
IEGC and State Grid Code.
In such cases, the revised schedules shall become effective from the 4th time block, counting
the time block in which the revised schedule is issued by the MSLDC to be the first one.
34
Centralized and De-centralized MoD
De-Centralized MoD
Discom Forcasted Contracted Generators Sum Short Fall After
Drawl Contracte / Surplus MoD
Considaring
Embaded d Capacity
Generators
A B C D E F G
Centralized MoD
State Demand Contracted Generators Sum Contracted Short After
Capacity Fall / MoD
Surplus
A B C D E F G
35
Virtual State Entity
Every intra-state entity under DSM Regulation has to Register with MSLDC and furnish all
relevant technical details.
In Day ahead scheduling de-centralized MoD will be run i.e. MoD within contracted
generators of concern Discom.
In real time operation, any Discom is deviating from drawl schedule more than allowed limit
or on revision of its contracted generator effecting on availability of concern Discom, De-
centralized MoD will be run to match load-generation balance.
During intra-day operation, Centralized MoD is required to be run considering the grid
parameters including frequency, voltage, transmission line loading, substation loading
conditions or State volume limits to maintain the Load-Generation balance and comply with
conditions stipulated under IEGC and State Grid Code or on direction from WRLDC.
During Centralized MoD run schedules of the Generators are subjected to revision, even if
concern Discom is not requiring the power enhanced or reduced for its generators.
A Virtual State Entity (VSE) is created, such enhancement or reduction of power due to
Centralized MoD shall be allocated to (VSE) and settlement will be between VSE and
Generator at prevalent DSM rate.
36
Virtual State Entity settlement
Energy allocation from Generator to VSE, Generator will receive from VSE at DSM rate subject to Cap.
Energy allocation from VSE to Generator, Generator will pay to VSE at DSM rate subject to Cap.
Schedule
in MW
Day ahead Declared Capacity (MW)
0 24 30 96
48 52 72 80
Time Blocks De-centralized MoD Centralized MoD Centralized MoD
37
Recovery of energy charge under DSM
Provision in MYT Regulations for consideration of DSM charges for Annual
Revenue requirement
39
Expected impact on recovery
Case 1 : Below freq. of 50 Hz , the deviation price ramps from Rs.3.09 /unit at a rate of 30.68 paise per 0.01 Hz.
(subject to cap rate of 3.943 / unit for domestic coal based units)
It will be better to increase the generation above the Schedule to the extent possible . As the Deviation will be
positive, there can be additional recovery . If the actual fuel cost per unit is lower than Deviation Price, this will
give additional gain. However, it is to be noted that in case of generation lower than schedule, the penalty will
also be at the same rate.
Case 2 : Above freq. of 50.05 Hz , the deviation price is 0 (zero) .
It will be better to reduce the generation below the Schedule , to the extent possible. As there will be no Deviation
Price, the total recovery will be at Scheduled energy , there will be saving in fuel expense to the extent of
generation below schedule. Generation more than schedule under such circumstances will lead to non
recovery of fuel cost for such excess generation.
40
Case 2 : A. Over-injection when frequency is above 50 Hz. (assumed ACP = DSM charge at 50 Hz = Rs.
3.09/kWh)
Scheduled Actual
Scheduled
Block No. Frequency (Hz) generation Actual generation Generation Deviation (MW) Deviation (MUs) Energy charge Actual Fuel
(MW) Generation (MW) (MUs) (MUs) Rs./kWh Expense Rs. Lakh
22 50.02 200 220 0.05 0.055 20 0.005 2.75 1.513
23 50.05 200 218 0.05 0.0545 18 0.0045 2.75 1.499
24 50.01 200 210 0.05 0.0525 10 0.0025 2.75 1.444
25 50.03 200 216 0.05 0.054 16 0.004 2.75 1.485
26 50.05 200 208 0.05 0.052 8 0.002 2.75 1.430
27 50.06 200 205 0.05 0.05125 5 0.00125 2.75 1.409
28 50.1 200 210 0.05 0.0525 10 0.0025 2.75 1.444
10.223
With over-injection at frequency above 50 Hz, there is under recovery of fuel cost.
Over-
Billing under DSM
Energy charge Billing as per recovered
Frequency Scheduled Actual DSM rate
Block No. present method ( on actual Energy Charge (on DSM Total fuel cost
(Hz) generation (MW) Generation (MW) Rs./kWh
generation) Rs. Lakh the schedule basis) charge recovery under DSM
Rs. Lakh Rs. Lakh Rs. Lakh (Rs. Lakh)
22 50.02 200 190 0 1.306 1.375 0.000 1.375 0.069
23 50.05 200 185 0 1.272 1.375 0.000 1.375 0.103
24 50.01 200 192 0 1.320 1.375 0.000 1.375 0.055
25 50.03 200 185 0 1.272 1.375 0.000 1.375 0.103
26 50.05 200 180 0 1.238 1.375 0.000 1.375 0.138
27 50.06 200 183 0 1.258 1.375 0.000 1.375 0.117
28 50.1 200 184 0 1.265 1.375 0.000 1.375 0.110
8.931 9.625 0.694
Energy
Energy Total
Schedule Actual Deviation Volume % Deviation Price Approved add.DSM Total Actual billing as
Charge As DSM Billing
Block Freq. Generation Generation MW =Actual w.r.t.Sche Rate(ps/unit) as Rate(MOD charge on DSM Generation per present Diff.
per DSM Charge Rs. under
Mw Mw -Scheduled du. Gen per matrix rate) (ps/unit) sign change charge (Kwh) mechanism
Rs. DSM
Rs.
1 49.98 200 205 5 2.50% 371.2 309.98 154990 4640 0 4640 159630 51250 158865 766
2 49.95 200 212 12 6.00% 463.1 309.98 154990 13893 0 13893 168883 53000 164289 4594
3 50.04 200 208 8 4.00% 62.0 309.98 154990 1240 0 1240 156230 52000 161190 -4960
4 50.01 200 212 12 6.00% 248.0 309.98 154990 7440 0 7440 162430 53000 164289 -1860
5 50.02 200 215 15 7.50% 186.0 309.98 154990 6975 0 6975 161965 53750 166614 -4650
6 50.04 200 220 20 10.00% 62.0 309.98 154990 3100 0 3100 158090 55000 170489 -12399
7 49.99 200 226 26 13.00% 340.6 309.98 154990 22139 -7457 14682 169672 56500 175139 -5467
add.DS add.DS
M M add.DS add.D
Deviation Deviation Total Energy
Deviation Deviation Energy -12% of charge charge M SM
Approved generatio generatio Deviation add.DS Total Charge
Schedule Actual MW Volume % Price Charge DSM schedu on on charge chargeTotal Actul
Bloc Rate(MO n n generatio M Billing as per
Freq. Generation Generatio=Actual - w.r.t.Sche Rate(ps/un As per Charge ed deviatio deviatio on on DSM Generatio Diff.
k D rate) between between n above charge under present
Mw n Mw Scheduled du. Gen it) as per DSM Rs. generat n n deviatio sign charge n (Kwh)
(ps/unit) 12% to 15% to 20% limit on DSM mechani
matrix Rs. ion betwee betwee n above chang
15% limit 20% limit volume sm Rs.
n 12% n 15% 20% e
to 15% to 20%
68 49.99 200 205 5 2.50% 340.6 309.98 154990 4258 -6000 4258 159248 51250 158865 383
69 50.01 200 201 1 0.50% 248.0 309.98 154990 620 -6000 620 155610 50250 155765 -155
70 49.95 200 185 -15 -7.50% 463.1 309.98 154990 -17367 -6000 -17367 137623 46250 143366 -5742
71 49.92 200 172 -28 -14.00% 555.0 309.98 154990 -38849 -6000 1000 0 0 -1110 0 0 -1110 0 -39959 115031 43000 133291 -18261
72 49.88 200 162 -38 -19.00% 677.5 309.98 154990 -64362 -6000 1500 2000 0 -2032 -5420 0 -7452 0 -71814 83176 40500 125542 -42366
73 49.88 200 155 -45 -22.50% 677.5 309.98 154990 -76218 -6000 1500 2500 1250.00 -2032 -6775 -8469 -17276 0 -93494 61496 38750 120117 -58622
74 49.94 200 185 -15 -7.50% 493.7 309.98 154990 -18515 -6000 -18515 136475 46250 143366 -6891
75 49.92 200 200 0 0.00% 555.0 309.98 154990 0 -6000 0 0 154990 50000 154990 0
Frequency lower
Heavy Loss
Generation drops below Deviations exceed
Schedule due to coal mill volume limits
outage
1. Though the DSM Regulations, 2019 were expected to be implemented from 1 st April, 2020, due to
difficulties in finalisation of the DSM Software, the implementation was delayed. However, due to
considerate and supportive approach taken by Hon’ble Commission , the delay has proved to be
2. The formation of Working Group Committee as per instruction of Hon’ble Commission and pro-active
actions taken by the Working committee has helped in providing adequate period for proper testing
of the software . Also through regular interactions in DSM Working Group Committee meetings, the
difficulties faced by the stakeholders were discussed in details along with possible solutions.
amendments on many contentious issues and has even provided stabilization period of 6 months
after Go-live.
… Conti. 46
Sharing of experience and learning from operations during trial run
4. This has helped to over-come many of the issues/ difficulties of the utilities , especially generators,
5. The extended time period helped MSPGCL in better understanding of the new system , increasing
awareness amongst the station staff and taking appropriate corrective actions at Station level to
improve preparedness .
6. Due to the support provided by Hon’ble Commission as well as DSM Working Group , the plant
operations after DSM Go-live are much smoother as compared to the expectations regarding
47
Some of the main issues raised by MSPGCL during trail run and support
provided by Hon’ble Commission.
48
Cont…
Some of the main issues raised by MSPGCL during trail run and support provided
by Hon’ble Commission.
49
Cont…
Session II-A
DSM preparedness by MSPGCL
Currently on many occasions it is observed that the actual generation at some of the MSPGCL stations
is lower than the schedule. In case if the frequency is on lower side during such deviation, the State may
require to draw excess power from RLDC and such exchange will be at high Deviation Price. When
Gencos are included in the settlement, naturally these charges for excess power drawal will have to
borne by MSPGCL on such occasions of low injection.
In view of this, MSPGCL stations will have to be alert in declaring capacity as well as timely
rescheduling in case of difficulties to follow the declared capacity.
For achieving Scheduled generation in each block the following become very critical
Co-ordination between CHP and Plant Operations , without which accuracy in declaration can’t be
achieved.
Ensuring reliable operations of auxiliaries – Best O & M efforts
Better assessment of outage situations and timely corrections in declared capacity accordingly.
Tapping opportunities for gain during “lower frequency” regime
Expected impact and Actions required at Hydro stations
In normal course , for Hydro stations, while computing the DSM charges
Scheduled Energy will be considered to be equal to Actual injection.
Thus there is no Deviation and no DSM charge for Hydro stations.
However , as per Scheduling and Dispatch Code, the Hydro units above 25 MW capacity have to
declare their capacity on regular basis. Thus specific input modules are prepared for
-Koyana Units ( all 1956 MW capacity), Tillari , Bhira and Vaitarana HPS and Ghatghar PSS, which are
of capacity more than 25 MW.
- For other hydro stations, monthly data for next month , based on water availability / water release
programme , to be provided to MSEDCL and SLDC by 21 st of every month . In case there is any
change in planning for utilisation of water during the month, same shall be informed by Generating
Station or concerned Distribution Licensee to MSLDC in advance.
-In normal case , the schedule for small hydro stations will be as per their declaration as above.
For above 25 MW units , the day-ahead schedule is as per requisition given by MSEDCL but in real
time, the schedule may be changed by SLDC as per grid requirement.
DSM preparedness at our end
MSPGCL DSM Readiness
• During the Trial run process, all the MSPGCL Management including CMD Sir , were regularly
apprised on the related developments and the management had pro-actively issued necessary
directions to the Stations as well as HO offices to ensure that MSPGCL stations remain well
prepared for changes under the new regime.
• For TPS level internal DSM real-time Dashboard is developed by MSPGCL IT team for online
monitoring .
• DSM groups were formed at local level to co-ordinate the activities at station level.
• Awareness training given to all operation staff .
• Monitoring & issuance of necessary directions by Director (Operations) for effective and
successful adoptin of DSM regime.
• With all these collective efforts , all MSPGCL stations are generally trying to follow DSM Schedule
and minimise DSM charge implication.
55
DSM preparedness for MSPGCL
Preparation of DSM Dashboard for ready reference for Plant control room Operations staff – IT
- Providing the input signals for the DSM dashboard – Testing , I & C / Electrical
- Updation of live data available from SLDC software – IT section with DSM Group
- Computation of expected DSM charges to help decision making – IT section / DSM group
- Working out strategies for loss reduction and then gain maximization – DSM group
Improving awareness amongst the different wings – Operations & CHP , Operations and
Maintenance , CHP & Chemists etc. So that declaration of capacity is correct and then plant
operations are as per schedule or as per DSM charges optimization strategy - S.E of the
concerned departments
Timely verification of Metered data and DSM bills received from SLDC.- DSM group / Testing , I &
C / Electrical
DSM web page available in control room for Talcher TPS NTPC
Average Additional charges payables are Rs. 10 lakh per week which are relatively low.
It shows that the Stations are generally following the given schedule , by & large .
Occasional over-injection at higher frequency at some stations, is leading under-recovery of fuel cost.
64
BTPS CSTP CSTP KPKD KPKD KTPS- KTPS- Parli
BTPS-3 NTPS Paras Parli-8 Uran
4&5 S 3-7 S 8-9 1-4 5 6 8-10 6-7
Blocks 1097 1841 1551 2173 1372 1151 3559 2266 1605 2315 1499 648 1341
Loss
Amount -8.4 -54.7 -122.7 -94.0 -44.8 -30.1 -35.4 -155.4 -12.2 -45.2 -69.7 -6.1 -21.4
Under Injection
Blocks 3939 1900 1015 1465 1080 1025 2778 1473 2706 2583 2359 1105 1443
Gain
Amount 130.5 100.2 127.1 69.2 59.5 49.5 84.7 82.9 100.7 119.5 124.2 43.8 12.8
Blocks 2359 2272 3325 2058 2549 2824 1855 2055 3543 2151 4456 4598 1252
Loss
Amount -47.9 -104.4 -423.0 -115.6 -183.6 -88.1 -45.5 -124.1 -92.2 -58.6 -589.7 -238.6 -6.3
Over Injection
Blocks 1998 4718 4832 5024 3714 5727 2538 4922 2801 3681 2417 4280 6715
Gain
Amount 10.9 68.8 263.0 187.1 120.9 97.5 16.2 122.2 5.6 44.6 32.6 43.5 83.1
Balance (Transmission
15 21 28 32 21 25 22 36 97 22 21 22 1
Constraint/ Central MOD
Blocks 570 772 1101 897 826 1137 599 810 818 631 1053 1295 626
Applicable DSM Loss
Rate lower than Amount -18.8 -39.1 -181.8 -39.1 -83.1 -42.6 -16.5 -36.4 -35.9 -27.6 -180.9 -95.7 -3.4
Over
MOD Rate
Injection
above 50.02 HZ Blocks 0 0 0 0 0 0 0 0 0 0 0 0 0
(B) Gain
Amount 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Blocks 692 885 1243 1046 966 1217 944 968 1007 814 1277 1374 699
Loss
Amount -20.0 -42.4 -193.6 -47.8 -87.1 -45.4 -21.4 -46.1 -37.1 -32.0 -196.2 -96.5 -4.6
Total for A&B
Blocks 103 13 0 0 0 7 22 0 0 7 61 27 0
Gain
Amount 8.3 1.1 0.0 0.0 0.0 0.5 1.2 0.0 0.0 0.5 2.1 2.0 0.0
Blocks 23 33 27 26 37 18 75 24 31 35 42 19 17
Under Injection
when freq is
below 49.85 Amount -0.5 -1.0 -1.5 -2.0 -1.1 -0.6 -1.3 -3.4 -0.6 -1.0 -9.0 -0.2 -0.2
Blocks 20 11 32 17 17 25 18 10 21 4 32 36 10
Over Injection
when freq is
ADSM above 50.1 Amount -0.6 -0.4 -7.8 -0.8 -1.8 -1.2 -0.4 -0.4 -1.5 -1.0 -4.8 -3.6 -0.1
Charges
Blocks 40 5 50 4 13 0 20 40 31 9 101 10 6
Under injection
beyond volume
limit when freq Amount 1.8 -7.4 -21.0 -1.2 -1.5 0.0 -1.4 -41.4 -7.6 -2.3 -38.9 -0.5 -1.5
is in between
49.85 to 50.01
Blocks 27 6 49 6 37 0 4 16 28 0 126 7 10
ADSM
Amount 1.1 5.9 10.2 0.9 6.2 0.0 0.0 8.6 10.6 0.0 41.9 0.0 0.8
5376 0.502 0.112 0.911 0.112 0.688 0.000 0.074 0.298 0.521 0.000 2.344 0.130 0.186
% of ADSM Blocks wrt Total Blocks