Heavy Fuel Oil Based Power Plant
Power system
• Generation
• Transmission
• Distribution
3
Heavy Fuel Oil Based Power Plant
Power Plant
A power plant is basically an industrial location that is utilized for the generation and
distribution of electric power in mass scale.
4
Heavy Fuel Oil Based Power Plant
5
Heavy Fuel Oil Based Power Plant
Katakhali 50 MW peaking power plant
Nominal Voltage 11 KV
Frequency 50Hz
In power plant……
Fuel Types
Diesel Oil (LFO)
Furnace Oil (HFO)
Diesel Oil
• Low Viscosity
• High cost
Furnace Oil
• High Viscosity Fig-4: Fuel Supply system
• Low cost
10
Heavy Fuel Oil Based Power Plant
Cooling System
Consists of……..
Water source
Pump
Cooling Towers
12
Heavy Fuel Oil Based Power Plant
Demineralizing
Fig-7: Demineralizing
13
Heavy Fuel Oil Based Power Plant
Busbar Arrangement
Bus-Bars are copper rods or thin walled tubes and
operate at constant voltage
Bus-Bars are used as the common electrical component
Types:
Single Bus-Bar system
Single bus bar system with
sectionalization
Duplicate bus-bar system Fig-8: Busbar Arrangement
14
Heavy Fuel Oil Based Power Plant
A step-down Transformer
Used to control large value of
voltage
Used for measuring purposes
Current Transformer(C.T)
A step-up Transformer
Used to provide the input to
high voltage protection
Used for measuring purposes
16
Heavy Fuel Oil Based Power Plant
17
Heavy Fuel Oil Based Power Plant
Isolator
Fig-12: Isolators
18
Heavy Fuel Oil Based Power Plant
Lighting Arresters
19
Heavy Fuel Oil Based Power Plant
20
Barapukuria Coal
Fired Thermal Power
Station
21
Barapukuria Coal Fired Thermal Power Station
22
Barapukuria Coal Fired Thermal Power Plant
Unit # 1 = 125 MW
Unit # 2 = 125 MW
Unit # 3 = 275 MW
Total: 525 MW
23
Barapukuria Coal Fired Thermal Power Plant
Unit # 1 = 125 MW
Unit # 2 = 125 MW
Unit # 3 = 275 MW
Total: 525 MW
24
Coal Consumption
25
Barapukuria Coal Fired Thermal Power Plant (3 rd Unit)
Specifications Quantity
Technology: Sub-Critical
Used Coal : Bituminous Coal (Barapukuria Coal Mine,
GCV=6200 KCal/Kg)
Rated Main Steam Pressure : 16.7 MPa
Rated Main Steam Temperature 537oC
Rated Main Steam Flow 934 T/H
Gross Capacity 300 MW
Net Capacity 274 MW
Rated Coal Flow 110 T/H
Rated Max. Gross Efficiency 38%
Coal Per Unit Generation 0.37 Kg/KWh
Fuel Cost Per Unit Generation 4.19 Tk/KWh
26
Barapukuria Coal Fired Thermal Power Plant (3 rd Unit)
Specifications Quantity
Technology: Sub-Critical
Used Coal : Bituminous Coal (Barapukuria Coal Mine,
GCV=6200 KCal/Kg)
Rated Main Steam Pressure : 16.7 MPa
Rated Main Steam Temperature 537oC
Rated Main Steam Flow 934 T/H
Gross Capacity 300 MW
Net Capacity 274 MW
Rated Coal Flow 110 T/H
Rated Max. Gross Efficiency 38%
Coal Per Unit Generation 0.37 Kg/KWh
Fuel Cost Per Unit Generation 4.19 Tk/KWh
27
Characteristics of Coal
Rating:13.8 KV/230 KV
Type: QFS –125-2
Rated Capacity (KVA): 156250 MVA: 156.25 MVA, Oil Filled
Active Power (KW): 125000 Cooling System: ONAF
Stator voltage (KV): 13.8 Three Phase
Stator Current (A): 6537 Manufacturer : Baoding Tianwei Baodian Eectric Co. Ltd.
Rotor Current (A): 1750 (627No load)
Rotor Voltage (V): 275 (88 No load)
Speed (RPM) : 3000
Manufacturer : Shanghai Turbine Generator Co.
Ltd
29
Technical Data
For Unit 3
GENERATOR UNIT TRANSFORMER
30
FLOW DIAGRAM OF POWER PRODUCTION OF
COAL BASED THERMAL POWER STATION
HOT AIR
TRANSFORMER
COAL CONVEYER
13.8/20 KV
COAL to
CRUSHER 230 KV
MAGNETIC
COAL MINE
SEPERATOR COAL CONVEYER
31
Coal Mine
32
Fig 16 coal mine
Coal Storage
• The coal used in the
power plant are stored
here.
Why??
• Matter of protection
against coal strike or
failure of transportation
system.
33
Fig 17 coal storage
Magnetic Separator
Magnetic separator is a
device that uses a magnet
to remove impurities and
other magnetic materials.
Why it is used??
• It is used to remove the
magnetic materials that
are extracted with coal as
impurities.
• If it is not done, the
impurities will damage the
other accessories.
Fig 18 Magnetic Seperator 34
Coal Conveyer
Why??
• In order to increase the
surface exposure.
• Thus promoting rapid
combustion without using
large quality of excess air.
37
Fig 21 coal control room
Boiler
38
Fig 22 boiler
Boiler Proper
1. Boiler Drum
2. Water Wall
3. Super Heater
4. Re-Heater
5. Economizer
6. Coal Burner
7. Oil Burner
39
Boiler Auxiliary
1. FD Fan
2. ID Fan
3. PA Fan
4. Coal Mill
5. Seal Air Fan
6. Scan Fan
7. Air Pre heater
40
Turbine
The dry and superheated steam is fed
to the steam turbine.
Fig 23 turbine 41
Turbine Blades
Fig 24 generator
43
Electrical Arrangement
46
Fig 27: control room
Gas turbine based power plant
Baghabari power station is one of the largest
power station in Bangladesh. It is situated in
Sirajganj district. It is a gas turbine power plant
whose total generation capacity, 171 MW is
generated by two units. Unit-1 generates 100
MW and unit-2 generates 71 MW. It is a base
load power plant which is regulated by
Bangladesh power development board (BPDB).
The Alstom Company built 71 MW unit in 1991
and Bharat Heavy Electrical Ltd. built 100 MW
in 2001.
Compressor needs 60% of consumption power to operate itself. Compressor pressurizes the air and transfers that
50
to the combustion chamber.
Gas turbine based power plant
Combustion Chamber:
When combustion chamber gets the compressed air, gas and air is started to burn in the combustion
chamber. Here, the gas is natural gas. During this combustion, the ratio of air and gas is 10:1 and huge
amount of heat is produced. In combustion chamber, there are 14 burners and each burner have an igniter.
By spraying fuel into the air, igniter ignites it and generates a high-temperature flow.
Frame size 9 9
Version E B
Generated voltage 11 KV 11 KV
54
GAS TURBINE BASED POWER
PLANT
Auxiliary System:
The auxiliary system of a power plant is mainly used to
maintain the plant. The auxiliary components of system
are described in next section.
An auxiliary transformer is used to supply power to
auxiliary equipments of a power plant. It is a step down
transformer. Power station always gets power from own
system as well as from the grid. If the power plant is shut
down, plant takes power from the grid to protect the whole
system. In Baghabari power plant, a 3-phase 11/0.4 KV
transformer is used to supply auxiliary power to system.
Fig 35:Auxiliary Transformer of Baghabari gas turbine
There also two instrument transformers that are connected power plant
with its substation for protection. These are,current
Transformer (CT) and potential Transformer (PT).
55
GAS TURBINE BASED POWER
PLANT
Control System :Control system is
the most essential part for any power plant.
Faults and abnormalities are detected by
control system. During the startup period of
the power plant, it is monitored for avoiding
any uncertain situation. Each system has two
modes, one is auto and the other is manual.
Automatic control system is mainly
programmable logic (PLC) based system.
When any kinds of fault occur, control
system detects this fault automatically
Hydraulic oil system is used to maintain the oil pressure. It contains inlet guide van (IGV), gas control
valve (GCV), atomizing air system and trip circuit. If the hydraulic oil pressure decreases to the
minimum limit then auxiliary hydraulic pump automatically operates.
Jacking Oil System
Jacking oil system is used in 71 MW unit which operates in turbine shaft. It consists of two pump, ac
and dc. When ac pump fails then dc pump starts automatically. To avoid the thermal shock, rotor rotates
slowly up to 24 hours even after the system shuts down.
Lube Oil System
Lubricating oil is another auxiliary system. Lubricating oil is supplied by three types of pumps, these
are main lube oil pump, auxiliary lube oil pump and emergency lube oil pump.
57
GAS TURBINE BASED POWER
PLANT
Main lube oil pump operates in running condition. Emergency lube oil pump operates when pressure falls.
Fig 37: Lubricating oil tank of Baghabari gas turbine power plant
58
GAS TURBINE BASED
POWER PLANT
61
GAS TURBINE BASED POWER PLANT
63
GAS TURBINE BASED POWER
PLANT
Tap changing machine:
It is use to change the
secondary voltage or
output voltage by
changing the position of
tapping.
64
GAS TURBINE BASED POWER
PLANT
Current Transformer:
●A step-up Transformer
●Used to provide the input to
high voltage protection
●Used for measuring
purposes
65
GAS TURBINE BASED POWER
PLANT
Current Transformer:
●A step-up Transformer
●Used to provide the input to
high voltage protection
●Used for measuring
purposes
66
GAS TURBINE BASED POWER
PLANT
Potential Transformer:
1.A step-down
Transformer
2.Used to control large
value of voltage
3.Used for measuring
purposes
67
GAS TURBINE BASED POWER
PLANT
Heavy Fuel Oil Based
Power Plant
SF6 Circuit Breaker
Sulphur Hexaflouride
(SF6) Circuit Breakers
SF6 gas…
●Electro-negative
●High electron affinity
Fig 48 Circuit breaker
68
GAS TURBINE BASED POWER
PLANT
Isolator:
●designed to open a circuit
under no load.
●desired to disconnect a
part of the system for
general maintenance and
repairs.
●Always opened after
Circuit Breaker and closed
before Circuit Breaker Fig 49 Isolator
69
GAS TURBINE BASED POWER
PLANT
Busbar arrangement:
1.It is used to connect the load
side and generation side ata
single point
2.Three phase busbar connection
is used.
3.Each phase has 2 wires to
connect with the national grid.
71
Thank You
72