2014 IVD Plant Business-Narong-Chong
2014 IVD Plant Business-Narong-Chong
GB-Labotron
IVD Plant Business
Proposal
GenBody Inc.
Manufacture
GenBody Land Fund
Inc. In Labor
Thailand
Uncut sheets
Cash invest. Cutting
RTD. HIV 1/2, Dipstick type 500 test / day 800 test / day 1.000 test / day
RTD. HCV, Dipstick type 500 test / day 800 test / day 1.000 test / day
RTD. HBsAg, Dipstick type 500 test / day 800 test / day 1.000 test / day
RTD. Syphilis, Dipstick type 500 test / day 800 test / day 1.000 test / day
Total amount 330,000 test / year 513,000 test / year 660,000 test / year
MFT Process.
Dispensing & Dry
From Raw
Materials Lamination Manual
Cutting
Assembling
Pressing
Storage
Manufacturing Room
• Objective: Assembly, pouch packing
• Dehumidified room (<20% humidity)
• Requested area: 40 m2
MFT room
-Dehumidifier: 1ea
-Rotary cutter: 1ea
-Guillotine cutter: 1ea
-Desicated cabinet: 1ea
-Conveyor & presser: 2ea
Assembling Assembling
Pouching
Sealing
Path Box 1
Manufacturing Room 2
• Objective: Pouch sealing, marking
• Dehumidified room (<20% humidity)
• Requested area: 20 m2
-Sealer: 2ea
-Marking machine: 1ea
-Conveyor: 1ea
Labeling (Marking)
Path Box 2
Manufacturing Room 3
• Objective: Boxing, Labeling, Liquid
handling
• Requested area: >100 m2
Path Box 2
MFT room 3
Equipments
-Experimental Table: 1 ea
-Reagent stack: 1 ea
-Refrigerator: 1 ea
-Cold chamber: 1 ea
-Pipette: 10, 100, 200,
1000ul
(2 sets)
-Mini-centrifuge
-Circulating water bath
-Camera: 1 ea
-Other labware
Storage Room
• Objective: Storage of finished products
• Requested area: >200 m2
Equipments
-Racks
Infrastructure
1. Basic units
Item Details Q'ty Price(US$) Remarks 3. Ground
Desks 4 4. Building and basic facilities
Tables 4
chairs 8
telephone 10
fax 2
Large printer 1
printer 4 ~15000
Office
bookcase 5
cabinet 5
computor 8
drinkable
1
water
etc gown, nameplate ….
Air conditioner 6 ~15000
glassware
Labware plasticware
etc ~5000 pipettes…
Others 5000
Total US$~45,000
2. Stationary equipments
Cold chamber Jeiotech 1 6000
Refrigrator LG 2 2250
Distiled water system anywhere 1 1500
Mili-Q water purification system Milipore 1 7500
Deep feezer Sanyo 1 22500 90,000$
Total US$39,750
MFT Instruments
Manufacturing machines
For the production of 2,000 tests/day 480,000 tests/year (240 working days)
Equipments
*Note: for the manufacture from raw materials, we need 3-line dispensor, dry incubator, laminator.
for the manufacture from uncut sheets, we don’t need these 3 machines.
264.500$
Expected labors & its cost
For the production of 2,000 tests/day 480,000 tests/year (240 working days)
Employee 8
Team leader 1
QC manager 1
Managing director - - -
Total ??/yr
200,000$/year
Total investment required
For the production of 2,000 tests/day 480,000 tests/year (240 working days)
Total 855,000/yr
Items transferring order
HIV 1/2, HBsAg, HCV, Syphilis,
1st
Step Dengue IgG/IgM, Dengue NS1 Ag
Routine item
HAV IgG/IgM
Chlamydia
Rotavirus
To be a global leader !
Adenovirus
Lepto IgG/IgM
Tsutsugamushi Ab
Hantavirus Ab
JEV IgG/IgM
Typhoid Ag
Typhoid IgG/IgM
*Chikungonia Ab
*Chagas Ab
*Developing items
GenBody Inc. as stockholder
Return
Dispensing & Dry
Return
Manual Lamination
Return