Professional Documents
Culture Documents
PSOC
PSOC
EE6603-POWER SYSTEM
OPERATION AND
CONTROL
UNIT – I
INTRODUCTION
UNIT-I 1. 1
Paavai Institutions Department of EEE
CONTENTS
TECHNICAL TERMS
1. INTRODUCTION
1.1. SYSTEM LOAD VARIATION
1.1.1. System load characteristics
1.1.1.1. Connected Load
1.1.1.2. Maximum Demand
1.1.1.3. Demand Factor
1.1.1.4. Average Load
1.1.1.5. Load Factor
1.1.1.6. Diversity Factor
1.1.1.7. Plant Capacity Factor
1.1.1.8. Plant Use Factor
1.1.2. Load curves
1.1.3. Load-duration curve
1.1.4..load factor
1.1.5. Diversity factor
1.2. RESERVE REQUIREMENTS
1.2.1. Installed reserves
1.2.2. Spinning reserves
1.2.3. Cold reserves
1.2.4. Hot reserves
1.3. OVERVIEW OF SYSTEM OPERATION
1.3.1. Load forecasting
1.3.2. Unit commitment
1.3.3. Load dispatching
1.4. OVERVIEW OF SYSTEM CONTROL
1.4.1. Governor Control
1.4.2. Load frequency control
1.4.3. Economic dispatch control
UNIT-I 1. 2
Paavai Institutions Department of EEE
UNIT-I 1. 3
Paavai Institutions Department of EEE
TECHNICAL TERMS
Load curve: The curve drawn between the variations of load on the power station with
Reference to time
Daily load curve: The curve drawn between the variations of load with reference to various
time period of day
Monthly load curve: The obtained from daily load curve.
Yearly load curve: The obtained from monthly load curve which is used to find annual load
factor.
Connected load: The sum of continuous ratings of all the equipments connected to supply
systems.
Maximum demand: The greatest demand of load on the power station during a given period.
Demand factor: The ratio of maximum demand to connected load.
Average demand: The average of loads occurring on the power station in a given period
(day or month or year).
Load factor: The ratio of average load to the maximum demand during a given period.
Diversity factor: The ratio of the sum of individual maximum demand on power station.
Capacity factor: The ratio of actual energy produced to the maximum possible energy that
could have been produced during a given period.
Plant use factor: The ratio of units generated to the product of plant capacity and the number
of hours for which the plant was in operation.
Load duration curve: When the load elements of a load curve are arranged in the order of
descending magnitudes the curve then
Load management: As generator capacity has increased in price (to as much as $1000 per
kilowatt) and as the fuel shortages put an extra squeeze on them, many electric utilities are
finding it worthwhile to try to „slave‟ the load peaks. This is referred to as load management.
Function of AVR: The basic role of the AVR is to provide constancy of the generator
terminal voltage during normal, small and slow changes in the load.
Optimal dispatch: Optimal dispatch is the state that the power system is in prior to any
contingency
UNIT-I 1. 4
Paavai Institutions Department of EEE
1. INTRODUCTION:
Power system operations have the responsibility to ensure that adequate power is
delivered to the load reliably and economically, in order to ensure adequate delivery
of power
demand. The electric energy system can be operated at the desired operating level by
maintaining frequency, voltage and security. The real and reactive power generated is
controlled automatically.
Power stations:
1. Steam plant
2. Hydro power plant
3. Nuclear power plant
4. Diesel power plant
UNIT-I 1. 5
Paavai Institutions Department of EEE
4. Agriculture
5. Others - street lights, traction.
Domestic:
Lights, fans, domestic appliances like heaters, refrigerators, air conditioners,
mixers, ovens, small motors etc.
Demand factor = 0.7 to 1.0; Diversity factor = 1.2 to 1.3; Load factor = 0.1 to
0.15
Commercial:
Lightings for shops, advertising hoardings, fans, AC etc.
Demand factor = 0.9 to 1.0; Diversity factor = 1.1 to 1.2; Load factor = 0.25 to
0.3
Industrial:
Small scale industries: 0-
20kW
Medium scale industries: 20-
100kW
Large scale industries: above
100kW
Industrial loads need power over a longer period which remains fairly uniform
throughout the day
For heavy industries:
Demand factor = 0.85 to 0.9; Load factor = 0.7 to 0.8
Agriculture:
Supplying water for irrigation using pumps driven by motors
Demand factor = 0.9 to 1; Diversity factor = 1.0 to 1.5; Load factor = 0.15 to
0.25
Other Loads:
Bulk supplies, street lights, traction, government loads which have their own
peculiar characteristics
1.1.1. System load characteristics
Connected load
Maximum demand
Average load
Load factor
Diversity factor
Plant capacity factor
UNIT-I 1. 6
Plant use factor
1.1.1.1. Connected
Load:
Paavai Institutions Department of EEE
Average load
Maximum demand
Load Factor=
If the plant is in operation for T hours
��� �� � �� ��
Load Factor=
� ���𝑇
������� ��������𝑇
�� ������
1.1.1.7. Plant Capacity Factor:
It is the ratio of actual energy produced to the maximum possible energy that could have been
produced during a given period.
��� � � � � ��� �� �� 𝑃� � �� � ��
Plant Capacity Factor=
������� ������� ����
����� ���� ���� ��������
1.1.1.8. Plant Use Factor:
It is the ratio of kWh generated to the product of plant capacity and the number of hours for
which the plant was in operation.
UNIT-I 1. 7
Paavai Institutions Department of EEE
UNIT-I 1. 8
Paavai Institutions Department of EEE
The load duration curve gives the data in a more presentable form
The area under the load duration curve is equal to that of the corresponding load curve
The load duration curve can be extended to include any period of time
1.1.4. Load factor
The ratio of average load to the maximum demand during a given period is known as
load factor.
Load factor = (average load)/ (maximum demand)
1.1.5. Diversity factor
The ratio of the sum of individual maximum demand on power station is known as
diversity factor.
Diversity factor = (sum of individual maximum demand)/(maximum
demand).
UNIT-I 1. 10
Paavai Institutions Department of EEE
Excitation
system and Field current
control
Electrical Power
Speed/power
UNIT-I 1. 13
Paavai Institutions Department of EEE
PROBLEMS
1. A power supply is having the following loads:
Type of load Maximum Diversity factor of Demand factor
demand(kw) group
Domestic 10,000 1.2 0.8
Commercial 30,000 1.3 0.9
Industrial 50,000 1.35 0.95
If the overall system diversity factor is 1.5, determine (a) the maximum demand, (b)
connected load of each type.
Solution:
(a)Total maximum demand of loads=10000+30000+50000=90000 kw
System diversity factor=1.5
Maximumdemand=Total demand/system diversity factor
=90000/1.5=60000 kw
(b)Connected load of each type
Domestic load:
Diversity factor of domestic load=Maximum domestic demand/maximum domestic load
demand
=12000/0.8=15000 kw
(c)Commercial load:
Connected commercial demand=Maximum demand/demand factor for commercial load
=39000/0.9=43333.33 kw
(d)Industrial load:
Connected industrial load=Maximum demand/demand factor of industrial load
=67500/0.95=71052.63 kw
2. A generating station has a maximum demand of 400 MW.The annual load factor is
60% and capacity factor is 50%.Find the reserve capacity of the plant.
Solution:
Energy generated per annum=Maximum demand*load factor*hours in a year
=400*0.
6*8760
=2102.4*103
MWhr
QUESTION BANK
PART A
1. What is the objective of power system operation and
control?
2.
What is load curve and load duration curve?
3.
Define load factor & diversity factor.
4.
Define spinning reserve, Cold reserve & hot reserve.
5.
6. Define Maximum Demand & demand factor.
State the purpose of system generation control.
7.
8. State the differences between P-f and Q-|V| controls.
9. What is meant by load frequency control?
What is daily, Weekly, Annual load curve?
10. Define load and list out the types of loads.
11. What is Average demand?
12. What is Capacity factor?
PART-B
1. A generating station has the following daily load cycle:
UNIT-I 1. 15
Paavai Institutions Department of EEE
5. Briefly discuss the classification of loads and list out the important Characteristics of various
types of loads.
6. Explain the need for voltage and frequency regulation in power system.
7. Explain the system voltage control and security control.
UNIT-I 1. 16
Paavai Institutions Department of EEE
UNIT –II
SYSTEM OPERATION
UNIT-II 2. 1
Paavai Institutions Department of EEE
CONTENTS
TECHNICAL TERMS
2. INTRODUCTION
UNIT-II 2. 2
Paavai Institutions Department of EEE
TECHNICAL TERMS
Btu (British thermal unit): A standard unit for measuring the quantity of heat energy
equal to the quantity of heat required to raise the temperature of 1 pound of water by 1
degree Fahrenheit.
Capacity: The amount of electric power delivered or required for which a generator,
turbine, transformer, transmission circuit, station, or system is rated by the
manufacturer.
Combined Cycle Unit:
An electric generating unit that consists of one or more combustion turbines and one
or more boilers with a portion of the required energy input to the boiler(s) provided by
the exhaust gas of the combustion turbine(s).
Demand: The rate at which energy is delivered to loads and scheduling points by
generation, transmission, and distribution facilities.
Demand (Electric): The rate at which electric energy is delivered to or by a system,
part of a system, or piece of equipment, at a given instant or averaged over any
designated period of time.
Demand-Side Management: The planning, implementation, and monitoring of
utility activities designed to encourage consumers to modify patterns of electricity
usage, including the timing and level of electricity demand. It refers only to energy
and load-shape modifying activities that are undertaken in response to utility-
administered programs. It does not refer to energy and load-shape changes arising
from the normal operation of the marketplace or from government-mandated energy-
efficiency standards. Demand-Side Management (DSM) covers the complete range of
load-shape objectives, including strategic conservation and load management, as well
as strategic load growth.
Deregulation: The elimination of regulation from a previously regulated industry or
sector of an industry.
Electric Service Provider: An entity that provides electric service to a retail or end-
use customer.
Energy: The capacity for doing work as measured by the capability of doing work
(potential energy) or the conversion of this capability to motion (kinetic energy).
Energy has several forms, some of which are easily convertible and can be changed to
another form useful for work. Most of the world's convertible energy comes from
UNIT-II 2. 3
Paavai Institutions Department of EEE
fossil fuels that are burned to produce heat that is then used as a transfer medium to
mechanical or other means in order to accomplish tasks. Electrical energy is usually
measured in kilowatthours, while heat energy is usually measured in British thermal
units.
Energy Charge: That portion of the charge for electric service based upon the
electric energy (kWh) consumed or billed
Outage: The period during which a generating unit, transmission line, or other facility
is out of service.
Forced Outage: The shutdown of a generating unit, transmission line or other
facility, for emergency reasons or a condition in which the generating equipment is
unavailable for load due to unanticipated breakdown.
Fuel: Any substance that can be burned to produce heat; also, materials that can be
fissioned in a chain reaction to produce heat.
UNIT-II 2. 4
Paavai Institutions Department of EEE
2. INTRODUCTION
Accurate models for electric power load forecasting are essential to the operation and
planning of a utility company. Load forecasting helps an electric utility to make important
decisions including decisions on purchasing and generating electric power, load switching,
and infrastructure development. Load forecasts are extremely important for energy
suppliers,ISOs, financial institutions, and other participants in electric energy generation,
transmission, distribution, and markets.
Load forecasts can be divided into three categories: short-term fore-casts which are
usually from one hour to one week, medium forecasts which are usually from a
week to a
year, and long-term forecasts which are longer than a year.
The forecasts for different time horizons are important for different operations within
a utility company. The natures of these forecasts are different as well. For example,
for a
particular region, it is possible to predict the next day load with an accuracy of
approximately
1-3%. However, it is impossible to predict the next year peak load with the similar
accuracy
since accurate long-term weather forecasts are not available. For the next year peak
forecast,
it is possible to provide the probability distribution of the load based on historical
weather
observations. It is also possible, according to the industry practice, to predict the so-
called
weather normalized load, which would take place for average annual peak weather
conditions
or worse than average peak weather conditions for a given area. Weather normalized
load is
the load calculated for the so-called normal weather conditions which are the average
of the
weather characteristics for the peak historical loads over a certain period of
time. The
duration of this period varies from one utility to another. Most companies take the last
25-30
years of data. Load forecasting has always been important for planning and opera-
tional
decision conducted by utility companies. However, with the deregulation of the
energy
UNIT-II industries, load forecasting is even more important. With supply and demand2. 5
fluctuating and
the changes of weather conditions and energy prices increasing by a factor of ten or
more
Paavai Institutions Department of EEE
The time factors include the time of the year, the day of the week, and the hour of the day.
There are important differences in load between weekdays and weekends. The load on
different weekdays also can behave differently. For example, Mondays and Fridays being
adjacent to weekends, may have structurally different loads than Tuesday through Thursday.
This is particularly true during the summer time. Holidays are more difficult to forecast than
non-holidays because of their relative infrequent occurrence.
Weather conditions influence the load. In fact, forecasted weather parameters are the most
important factors in short-term load forecasts. Various weather variables could be
considered
for load forecasting. Tem-perature and humidity are the most commonly used
load
UNIT-II 2. 6
Paavai Institutions Department of EEE
predictors.
Among the weather variables listed above, two composite weather variable functions, the
THI (temperature-humidity index) and WCI (wind chill index), are broadly used by utility
companies. THI is a measure of summer heat discomfort and similarly WCI is cold stress
in
winter.
Most electric utilities serve customers of different types such as residential, commercial,
and industrial. The electric usage pattern is different for customers that belong to different
classes but is somewhat alike for customers within each class. Therefore, most utilities
distinguish load behavior on a class-by-class basis.
For example, presented an additive model that takes the form of predicting load as the
function of four components:
where L is the total load, L n represents the “normal” part of the load, which is a set of
standardized load shapes for each “type” of day that has been identified as occurring
throughout the year, Lw represents the weather sensitive part of the load, Ls is a special event
UNIT-II 2. 7
Paavai Institutions Department of EEE
component that create a substantial deviation from the usual load pattern, and Lr is a
completely random term, the noise.
End-use models focus on the various uses of electricity in the residential, commercial, and
industrial sector. These models are based on the principle that electricity demand is derived
from customer’s demand for light, cooling, heating, refrigeration, etc.
UNIT-II 2. 8
Paavai Institutions Department of EEE
Ideally this approach is very accurate. However, it is sensitive to the amount and quality of
end-use data. For example, in this method the distribution of equipment age is important for
particular types of appliances. End-use forecast requires less historical data but more in-
formation about customers and their equipment.
Econometric models. The econometric approach combines economic theory and statistical
techniques for forecasting electricity demand. The approach estimates the relationships
between energy consumption (de-pendent variables) and factors influencing consumption.
The relation-ships are estimated by the least-squares method or time series methods.
One of the options in this framework is to aggregate the econometric approach, when
consumption in different sectors (residential, commercial, industrial, etc.) is calculated as a
function of weather, economic and other variables, and then estimates are assembled using
recent historical data. Integration of the econometric approach into the end-use approach
introduces behavioral components into the end-use equations.
Statistical model-based learning. The end-use and econometric methods require a large
amount of information relevant to appliances, customers, economics, etc. Their application is
complicated and requires human participation. In addition such information is often not
available regarding particular customers and a utility keeps and supports a pro-file of an
“average” customer or average customers for different type of customers. The problem arises
if the utility wants to conduct next-year forecasts for sub-areas, which are often called load
pockets. In this case, the amount of the work that should be performed increases proportion-
ally with the number of load pockets. In addition, end-use profiles and econometric data for
different load pockets are typically different. The characteristics for particular areas may be
different from the average characteristics for the utility and may not be available.
We compared several load models and came to the conclusion that the following
multiplicative model is the most accurate
where L(t) is the actual load at time t, d(t) is the day of the week, h(t) is the hour of the day, F
(d, h) is the daily and hourly component, w(t) is the weather data that include the temperature
UNIT-II 2. 9
Paavai Institutions Department of EEE
and humidity, f (w) is the weather factor, and R(t) is a random error.
In fact, w (t) is a vector that consists of the current and lagged weather variables. This
reflects the fact that electric load depends not only on the current weather conditions but also
on the weather during the previous hours and days. In particular, the well-known effect of the
so-called heat waves is that the use of air conditioners increases when the hot weather
continues for several days.
One of the earliest applications of on-line centralized control was to provide a central
facility, to operate economically, several generating plants supplying the loads of the system.
Modern integrated systems have different types of generating plants, such as coal fired
thermal plants, hydel plants, nuclear plants, oil and natural gas units etc. The capital
investment, operation and maintenance costs are different for different types of plants.
During operation of the plant, a generator may be in one of the following states:
UNIT-II 2. 10
Paavai Institutions Department of EEE
UNIT-II 2. 11
Paavai Institutions Department of EEE
The incremental cost is the product of incremental fuel rate and fuel cost (Rs / Btu or $ /Btu).
The curve in shown in Fig. 4. The unit of the incremental fuel cost is Rs / MWh or $ /MWh.
UNIT-II 2. 12
Paavai Institutions Department of EEE
In general, the fuel cost Fi for a plant, is approximated as a quadratic function of the
generated output PGi.
Fi = ai + bi PGi + ci PG2 Rs / h --------------------------------- (4)
The incremental fuel cost is a measure of how costly it will be produce an increment of
power. The incremental production cost, is made up of incremental fuel cost plus the
incremental cost of labour, water, maintenance etc. which can be taken to be some percentage
of the incremental fuel cost, instead of resorting to a rigorous mathematical model. The cost
curve can be approximated by a linear curve. While there is negligible operating cost for a
hydel plant, there is a limitation on the power output possible. In any plant, all units normally
operate between PGmin, the minimum loading limit, below which it is technically infeasible
to operate a unit and PGmax, which is the maximum output limit.
Figure 2.5 shows the configuration that will be studied in this section.
This system consists of N thermal-generating units connected to a single bus-bar serving a
received electrical load Pload input to each unit, shown as F I,represents the cost rate of the
unit. The output of each unit, Pi, is the electrical power generated by that particular unit. The
total cost rate of this system is, of course, the sum of the costs of each of the individual units.
The essential constraint on the operation of this system is that the sum of the output powers
must equal the load demand.Mathematically speaking, the problem may be stated very
concisely. That is, an objective function, F T, is equal to the total cost for supplying the
indicated load. The problem is to minimize FT subject to the constraint that the sum of the
UNIT-II 2. 13
Paavai Institutions Department of EEE
powers generated must equal the received load. Note that any transmission losses are
neglected and any operating limits are not explicitly stated when formulating this problem.
That is,
------------------------------------------ (6)
This is a constrained optimization problem that may be attacked formally using advanced
calculus methods that involve the Lagrange function. In order to establish the necessary
conditions for an extreme value of the objective function, add the constraint function to the
objective function after the constraint function has been multiplied by an undetermined
multiplier. This is known as the Lagrange function and is shown in Eq(7)
------------------------------------------------ (7)
The necessary conditions for an extreme value of the objective function result when we
take the first derivative of the Lagrange function with respect to each of the independent
variables and set the derivatives equal to zero. In this case,there are N+1 variables, the N
values of power output, Pi, plus the undetermined Lagrange multiplier, λ. The derivative of
the Lagrange function with respect to the undetermined multiplier merely gives back the
constraint equation. On the other hand, the N equations that result when we take the
partial derivative of the Lagrange function with respect to the power output values one at a
time give the set of equations shown as Eq. 8.
----------------------------------------------- (8)
UNIT-II 2. 14
Paavai Institutions Department of EEE
When we recognize the inequality constraints, then the necessary conditions may be
expanded slightly as shown in the set of equations making up Eq. 9
--------------------------------------------- (9)
Several of the examples in this chapter use the following three generator units.
EXAMPLE 2.1
Suppose that we wish to determine the economic operating point for these three units
when delivering a total of 850 MW. Before this problem can be solved,the fuel cost
of each
unit must be specified. Let the following fuel costs are in effect.
Unit 1: Coal-fired steam unit: Max output = 600 MW Min output = 150 MW
Input-output curve:
Unit 3: Oil-fired steam unit: Max output = 200 MW, Min output = 50 MW
Input-output curve:
Then
UNIT-II 2. 15
Paavai Institutions Department of EEE
If one goes about the solution exactly as done here, the results are
This solution meets the constraint requiring total generation to equal 850 MW, but units 1 and
3 are not within limit. To solve for the most economic dispatch while meeting unit limits,
suppose unit 1 is set to its maximum output and unit 3 to its minimum output. The dispatch
becomes
UNIT-II 2. 16
Paavai Institutions Department of EEE
Next, calculate the incremental cost for units 1 and 3 to see if they meet the conditions.
Note that the incremental cost for unit 1 is less than λ, so unit 1 should be at its maximum.
However, the incremental cost for unit 3 is not greater than ,λ so unit 3 should not be forced
to its minimum. Thus, to find the optimal dispatch, allow the incremental cost at units 2 and 3
to equal λ as follows.
UNIT-II 2. 17
Paavai Institutions Department of EEE
------------------ (10)
The same procedure is followed in the formal sense to establish the necessary
conditions for a minimum-cost operating solution, The Lagrange function is shown in
Eq.11.
In taking the derivative of the Lagrange function with respect to each of the individual
power
outputs, Pi, it must be recognized that the loss in the transmission network, Ploss is a
function
of the network impedances and the currents flowing in the network. For our purposes,
the
currents will be considered only as a function of the independent variables Pi and
the load
Pload taking the derivative of the Lagrange function with respect to any one of the N
values of
Pi results in Eq. 11. collectively as the coordination equations.
----------------------------------- (11)
It is much more difficult to solve this set of equations than the previous set with no
losses since this second set involves the computation of the network loss in order to
establish
the validity of the solution in satisfying the constraint equation. There have been two
general
approaches to the solution of this problem. The first is the development of a
mathematical
expression for the losses in the network solely as a function of the power output of
each of
the units. This is the loss-formula method discussed at some length in
Kirchmayer’s
Economic Operation of Power Systems. The other basic approach to the solution of
this
problem is to incorporate the power flow equations as essential constraints in the
formal
UNIT-II 2. 18
establishment of the optimization problem. This general approach is known as the
optimal
power flow.
Paavai Institutions Department of EEE
incremental cost levels and combinations of units. That is, we will now establish a set of
logical rules that would enable us to accomplish the same objective as we have just done with
ruler and graph paper. The actual details of how the power output is established as a function
of the incremental cost rate are of very little importance.
We could, for example, store tables of data within the computer and interpolate
between the stored power points to find exact power output for a specified value of
incremental cost rate. Another approach would be to develop an analytical function for the
power output as a function of the incremental cost rate, store this function (or its coefficients)
in the computer, and use this to establish the output of each of the individual units.
UNIT-II 2. 20
Paavai Institutions Department of EEE
Example: 2.3
Given the generator cost functions found in Example 2.1, solve for the economic
dispatch of generation with a total load of 800 MW.Using α = 100 and starting from P 10= 300
MW, P2 0 = 200 MW, and P3 0=300 MW, we set the initial value of λ. equal to the average of
the incremental costs of the generators at their starting generation values. This value is
9.4484.The progress of the gradient search is shown in Table 3.2. The table shows that the
iterations have led to no solution at all. Attempts to use this formulation
will result in difficulty as the gradient cannot guarantee that the adjustment to the generators
will result in a schedule that meets the correct total load of 800 MW.A simple variation of
this technique is to realize that one of the generators is always a dependent variable and
remove it from the problem. In this case, we pick P 3 and use the following:
Note that this function stands by itself as a function of two variables with no
load-generation balance constraint (and no λ). The cost can be minimized by
a gradient method and in this case the gradient is:
\
Note that this gradient goes to the
zero vector when the incremental
cost at generator 3 is
equal to that at generators 1 and 2.
The gradient steps are performed in
the same manner as
previously, where:
UNIT-II 2. 21
Paavai Institutions Department of EEE
------------------------------------ (12)
Each time a gradient step is made, the generation at generator 3 is set to 800 minus the sum of
the generation at generators 1 and 2. This method is often called the “reduced gradient”
because of the smaller number of variables.
UNIT-II 2. 22
Paavai Institutions Department of EEE
---------------------------------------- (15)
The earlier equation, 15, can be used to find the participation factor for each unit as follows
--------------------------------------- (16)
The computer implementation of such a scheme of economic dispatch is straightforward. It
might be done by provision of tables of the values of FY as a function of the load levels and
devising a simple scheme to take the existing load plus the projected increase to look up these
data and compute the factors. somewhat less elegant scheme to provide participation factors
would involve a repeat economic dispatch calculation at. The base-point economic generation
values are then subtracted from the new economic generation values and the difference
divided to provide the participation factors. This scheme works well in computer
implementations where the execution time for the economic dispatch is short and will always
give consistent answers when units reach limits, pass through break points on piecewise
linear incremental cost functions, or have nonconvex cost curves.
EXAMPLE 2.4
Starting from the optimal economic solution found in Example 2A; use the participation
factor method to calculate the dispatch for a total load of 900 MW.
UNIT-II 2. 23
Paavai Institutions Department of EEE
Both the load frequency control and the economic dispatch issue commands to change
the power setting of each turbine-governor unit. At a first glance it may seem that these two
commands can be conflicting. This however is not true. A typical automatic generation
control strategy is shown in Fig. 5.5 in which both the objective are coordinated. First we
compute the area control error. A share of this ACE, proportional to αi , is allocated to each
of the turbine-generator unit of an area. Also the share of unit- i , γi X Σ( PDK - Pk ), for the
deviation of total generation from actual generation is computed. Also the error between the
economic power setting and actual power setting of unit- i is computed. All these signals are
then combined and passed through a proportional gain K i to obtain the turbine-governor
control signal.
UNIT-II 2. 24
Paavai Institutions Department of EEE
having sufficient generation to meet the load.Not only must the reserve be sufficient to make
up for a generation-unit failure, but the reserves must be allocated among fast-responding
units and slow-responding units. This allows the automatic generation control system to
restore frequency and interchange quickly in the event of a generating-unit outage. Beyond
spinning reserve, the unit commitment problem may involve various classes of “scheduled
reserves” or “off-line” reserves. These include quick-start
diesel or gas-turbine units as well as most hydro-units and pumped-storage hydro-units that
can be brought on-line, synchronized, and brought up to full capacity quickly. As such, these
units can be “counted” in the overall reserve assessment, as long as their time to come up to
full capacity is taken into account. Reserves, finally, must be spread around the power system
to avoid transmission system limitations (often called “bottling” of reserves) and to allow
various parts of the system to run as “islands,” should they become electrically disconnected.
UNIT-II 2. 26
Paavai Institutions Department of EEE
Up to a certain number of hours, the cost of banking will be less than the cost of cooling, as is
illustrated in Figure 5.3.Finally, the capacity limits of thermal units may change frequently,
due to maintenance or unscheduled outages of various equipment in the plant; this must also
be taken
2.3.4 Other Constraints
2.3.4.1 Hydro-Constraints
Unit commitment cannot be
completely separated from
the scheduling of hydro-
units. In this
text, we will assume that
the hydrothermal
scheduling (or
“coordination”) problem
can be
separated from the unit
commitment problem. We,
of course, cannot assert
flatly that our
treatment in this fashion
will always
result in an optimal solution.
UNIT-II 2. 27
Paavai Institutions Department of EEE
-----------------------------------------(19)
For the total period of M intervals, the maximum number of possible combinations is (2N -
l)M, which can become a horrid number to think about.
For example, take a 24-h period (e.g., 24 one-hour intervals) and consider systems with 5, 10,
20, and 40 units. The value of (2N - 1)24 becomes the following.
UNIT-II 2. 28
Paavai Institutions Department of EEE
N (2N - 1)24
5 6.2 ×1035
10 1.73×1072
20 3.12×10144
40 Too big
These very large numbers are the upper bounds for the number of enumerations required.
Fortunately, the constraints on the units and the load-capacity relationships of typical utility
systems are such that we do not approach these large numbers. Nevertheless, the real
practical barrier in the optimized unit commitment problem is the high dimensionality of the
possible solution space. The most talked-about techniques for the solution of the unit
commitment problem are:
1. Priority-list schemes,
2. Dynamic programming (DP),
3. Lagrange relation (LR).
UNIT-II 2. 30
Paavai Institutions Department of EEE
The imposition of a priority list arranged in order of the full-load averagecost rate would
result in a theoretically correct dispatch and commitment only if:
initial conditions are easily specified and the computations can go forward in time as
long as
Paavai Institutions Department of EEE
Where
Fcost(K, I ) = least total cost to arrive at state ( K , I )
Pcost(KI, ) = production cost for state ( K ,I )
Scost(K - 1, L: K , I)= transition cost from state (K - 1, L) to state ( K , I )
State (K, 1) is the Zth combination in hour K. For the forward dynamic programming
approach, we define a strategy as the transition, or path, from one state at a given hour to a
state at the next hour.
Note that two new variables, X and N, have been introduced in Figure 2.11
X = number of states to search each period
N = number of strategies, or paths, to save at each step
These variables allow control of the computational effort (see below Figure).For complete
enumeration, the maximum number of the value of X or N is 2n – 1
UNIT-II 2. 32
Paavai Institutions Department of EEE
UNIT-II 2. 33
Paavai Institutions Department of EEE
----------------------- (21)
2. Unit limits:
3. Unit minimum up- and down-time constraints. Note that other constraints can easily be
formulated and added to the unit commitment problem. These include transmission
security constraints (see Chapter 1 l), generator fuel limit constraints, and system air
quality constraints in the form of limits on emissions from fossil-fired plants, spinning
reserve constraints,etc.
4. The objective function is:
------------------------- (22)
We can then form the Lagrange function similar to the way we did in the economic dispatch
problem:
---------------------------- (23)
UNIT-II 2. 34
Paavai Institutions Department of EEE
Example:2.5
The costs of
two units at
the busses
connected
through a
transmission
line are (with
P1and P2
in MW):
IC1=15+0.1
25 P1;
IC2=20+0.0
DPL/dP2
5 P2, If = ITL2 =0; where, PL=B11P12; i.e., B11= PL/ P12 = 15.625/1252 = 10-3 MW-1
125
MW is-3 2
Thus,
transmitted P1 so that dPL/dP1= ITL1 = 2(10 ) P1 MW
PL=10 -3
from unit-1
Hence
to the we have,
load at bus-2,
IC1 = 15+0.125 P1 = λ (1-ITL1) = 24 {1 - 2(10-3) P1} and
at which the
unit-2 is
IC2 = 20+0.05 P2 = λ (1-ITL2) = λ = 24
present, a
line loss of
Solving, we get, P1=52 MW and P2= 80 MW.
15.625 MW
is incurred.
Total loss = Total Generation – Total Load = (P1+P2) – PLoad
Find the
required
generation
for each of
the units and
the power
received by
the load
when the
system
lambda is
Rs.24.0 per
MWHr. Use
Penalty
Factor
method.
Solution:
With unit-2 not contributing to the line loss, it is due to the unit-1 alone, and hence,
UNIT-II 2. 35
Paavai Institutions Department of EEE
QUESTION BANK
PART- A
Participation factor method to calculate the economic dispatch for load is reduced to 550MW?
5. Consider three units,
a. 2
C1=561+7.92P1+0.00156P1
2
b. C2=310+7.85P2+0.00194P2
c. C3=780+7.97P3+0.00482P32
UNIT-II 2. 36
Paavai Institutions Department of EEE
UNIT-II 2. 37
Paavai Institutions Department of EEE
UNIT –III
SYSTEM
CONTROL –
REAL
POWER –
FREQUENCY
CONTROL
UNIT-3 3. 1
Paavai Institutions Department of EEE
CONTENTS
TECHNICAL TERMS
3.1 INTRODUCTION
3.2 LOAD FREQUENCY CONTROL
3.3 Q-V CONTROL LOOPS
3.4 P-F CONTROL LOOPS
3.4.1 Primary ALFC
3.4.2 Secondary ALFC
UNIT-3 3. 2
Paavai Institutions Department of EEE
TECHNICAL TERMS
Control area: Most power systems normally control their generators in unison. The
individual control loops have the same regulation parameters. The individual generator
turbines tend to have the same response characteristics then it is possible to let the control
loop in the whole system which then would be referred to as a control area.
Prime Mover: The engine, turbine, water wheel, or similar machine that drives an
electric generator; or, for reporting purposes, a device that converts energy to electricity
directly (e.g., photovoltaic solar and fuel cell(s)).
Retail Wheeling: The process of moving electric power from a point of generation across
one or more utility-owned transmission and distribution systems to a retail customer.
Revenue: The total amount of money received by a firm from sales of its products and/or
services, gains from the sales or exchange of assets, interest and dividends earned on
UNIT-3 3. 3
Paavai Institutions Department of EEE
investments, and other increases in the owner's equity except those arising from capital
adjustments.
Real power: The real power in a power system is being controlled by controlling the
driving torque of the individual turbines of the system.
UNIT-3 3. 4
Paavai Institutions Department of EEE
3.1. INTRODUCTION
UNIT-3 deriving an error signal from the deviations in the specified tie-line power flows to the 3. 5
neighboring utilities and adding this signal to the control signal of the load-frequency
control
Paavai Institutions Department of EEE
that one of the following alternatives be considered for keeping the system in operating
condition:
I. Starting fast peaking units.
2. Load shedding for unimportant loads, and
3. Generation rescheduling.
It is apparent from the above that since the voltage specifications are not stringent.
Load frequency control is by far the most important in power system control.
the shaft is sensed and compared with a reference, and the feedback signal is utilized to
increase or decrease the power generated by controlling the inlet valve to turbine of steam or
water as the case may be
Speed Governing Mechanism
The speed governing mechanism includes the following parts.
Speed Governor:
It is an error sensing device in load frequency control. It includes all the elements that
are directly responsive to speed and influence other elements of the system to initiate
action.
Governor Controlled Valves:
They control the input to the turbine and are actuated by the speed control
mechanism.
Speed Control Mechanism:
It includes all equipment such as levers and linkages,servomotors, amplifying devices
and relays that are placed between the speed governor and the governor controlled
valves.
Speed Changer:
It enables the speed governor system to adjust the speed of the
turbogenerator unit
while in operation.
The pilot valve v operates to increase or decrease the opening of the steam inlet valve
V. Let XB and Xc be the changes in the position of the pilot valve v and control valve V
responding to a change in governor position. X A due to load. When the pilot valve is closed
XB= 0 and Xc == 0, (Le.,) the control valve is not completely closed, as the unit has to
supply its no-load losses. Let be the no-load angular speed of the turbine. As load is applied,
the speed falls and through the linkages the governor operates to move the piston P
downwards along with points A and B. The pilot valve v admits soil under n and lifts it up so
that the input is increased and speed rise. If the link B e is removed then the pilot valve comes
UNIT-3 3. 8
Paavai Institutions Department of EEE
to rest only when the speed returns to its original value. An "isochronous" characteristic will
be obtained with such an arrangement where speed is restored to its preload-disturbance
value.
With the link Be, the steady state is reached at a speed slightly lower than the no load
speed giving a drooping characteristic for the governor system. A finite value of the
steady
state speed regulation is obtained with this arrangement. For a given speed changer
position,
the per unit steady state speed regulation is defined by
Steady state speed regulation =
No-Nr/N
Where No = Speed at no - load
N r = Rated speed
N = Speed at rated
3.6 AUTOMATIC load FREQUENCY CONTROL
LOAD
The ALFC is to control the frequency deviation by maintaining the real power
balance in the system. The main functions of the ALFC are to i) to maintain the
steady
frequency; ii) control the tie-line flows; and iii) distribute the load
participating
among the generating units. The control (input) signals are the tie-line deviation ∆Ptie
(measured from the tie- line flows), and the frequency deviation ∆f (obtained by
measuring the angle deviation ∆δ). These error signals ∆f and ∆Ptie a r e amplified,
mixed and transformed to a real power signal, which then controls the valve position.
Depending on the valve position, the turbine (prime mover) changes its output power to
establish the real power balance. The complete control schematic is shown in Fig3.3
UNIT-3 3. 9
Paavai Institutions Department of EEE
For the analysis, the models for each of the blocks in Fig2 are required. The
generator and the electrical load constitute the power system. The valve and the hydraulic
amplifier represent the speed governing system. Using the swing equation, the
generator can be Using the swing equation, the generator can be modeled by
2𝐻� 2
∆δ
�
= ∆Pm − ∆Pe
�
Expressing
� the speed deviation in pu
� ∆w 1
��
∆Pm − ∆Pe
=2𝐻
UNIT-3 3. 10
Paavai Institutions Department of EEE
UNIT-3 3. 11
Paavai Institutions Department of EEE
All the individual blocks can now be connected to represent the complete ALFC loop as
We have
The generator is synchronized to a network of very large size. So, the speed or
frequency will be essentially independent of any changes in a power output of the
generator
ie, ∆F(s) =0
(i)Controlled case:
Let us assume that we made a step change of the magnitude ∆P c of the speed changer
∆PG (stat) = ∆
(ii)Uncontrolled case
Let us assume that the load suddenly increases by small amount ∆P D.Consider
there is no external work and the generator is delivering a power to a single load.
UNIT-3 3. 12
Paavai Institutions Department of EEE
Therefore
∆PG(s) = 1/(1+sTG)(1+sTt)[-∆F/sR]
When the generator is connected to infinite bus (∆f = 0, and ∆V = 0), then ∆Pm = ∆Pref .
If the network is finite, for a fixed speed changer setting (∆Pref = 0), then
∆Pm = (1/R)∆f or∆f=RPm.
3.6.2 Concept of AGC (Supplementary ALFC Loop)
The ALFC loop shown in Fig3.8 is called the primary ALFC loop. It achieves
the primary goal of real power balance by adjusting the turbine output ∆Pm to
match the
change in load demand ∆PD. All the participating generating units contribute to
the
change in generation. But a change in load results in a steady state frequency
deviation
∆f. The restoration of the frequency to the nominal value requires an additional
control
loop called the supplementary loop. This objective is met by using integral
controller
which makes the frequency deviation zero. The ALFC with the supplementary loop is
generally called the AGC. The block diagram of an AGC is shown in Fig3.9. The
main
objectives of AGC a r e i) to regulate t h e frequency (using b o t h
primary a n d
supplementary controls); ii) and to maintain the scheduled tie-line flows. A
secondary
objective of the AGC is to distribute the required change in generation
UNIT-3 the
among 3. 13
connected generating units economically (to obtain least operating
costs).
Paavai Institutions Department of EEE
`Now we are going to study the effect of a disturbance in the system derived above.
Both loss of generation and loss of load can be simulated by imposing a positive or negative
step input on the variable Pload. A change of the set value of the system frequency f0 is not
considered as this is not meaningful in real power systems. From the block diagram in Figure
3.9 it is straightforward to derive the transfer function between
UNIT-3 3. 14
Paavai Institutions Department of EEE
In order to calculate an equivalent time constant Teq, Tt is put to 0. This can be done since
for realistic systems the turbine controller time constant Tt is much smaller than the time
constant
−∆PD
∆f=∆ω1=∆ω2=β1+β2 where
β1= D1+1/R1
β2= D2+1/R2
UNIT-3 3. 16
Paavai Institutions Department of EEE
∆f= -∆PD1/ β1 + β2
β2
∆P12= -∆PD1
β1+β2
Where, 1 and 2 are the composite frequency response characteristic of Area1 and Area 2
respectively. An increase of load in area1 by ∆PD1 results in a frequency reduction in both
areas and a tie-line flow of ∆P12. A positive ∆P12 is indicative of flow from Area1 to Area
2 while a negative ∆P12 means flow from Area 2 to Area1. Similarly, for a change in Area 2
load by ∆PD2, we have
∆f= -∆PD2/ β1 + β2
β1
∆P12= -∆PD2
β1+β2
UNIT-3 3. 17
Paavai Institutions Department of EEE
UNIT-3 3. 18
Paavai Institutions Department of EEE
Assumption in Analysis:
The following assumptions are made in the analysis of the two area system:
1. The overall governing characteristic of the operating units in any area can be represented
by
a linear curve of frequency versus generation.
2. The governors in both the areas start acting simultaneously to changes in their respective
areas.
3. Supplementary control devices act after the initial governor response is over
The following time instants are defined to explain the control sequence:
To=is the instant when both the areas are operating at the scheduled frequency and
Tie=line interchange and load change takes place.
tl = the instant when governor action is initiated at both A and B.
t2 =the instant when governor action ceases.
UNIT-3 3. 19
Paavai Institutions Department of EEE
Case 3: Load change occurs in A and the controller in B acts first. The initial governor
response which begins at the instant t1 ceases at t2. The tie line controller in B begins and
completes its action before the frequency regulator at A takes control. During this period of
control action, i.e. t3-t4 by the tie line regulator the frequency decreases further than it was at
the end of the governor action period while the tie line power schedule is maintained.
UNIT-3 3. 21
Paavai Institutions Department of EEE
UNIT-3 3. 22
Paavai Institutions Department of EEE
The point of intersection of both the characteristics is the only point of operation
where the system, frequency and tie line schedule can be maintained at the normal values. As
in the previous control strategy, all the four possible cases of operation are discussed. Let
UNIT-3 3. 23
Paavai Institutions Department of EEE
area A be equipped with a flat frequency controller and area B be provided with a tie-line
bias controller
Consider two inter connected areas as shown in figure operating at the same frequency fl
while a power Power flow from area I to area 2
let V1 and V 2 be the voltage magnitudes
𝛿 1, 𝛿 2 voltage phase angles at the two ends of the tie-line
While P flows from area I to area 2 then,
Where X is the reactance of the line. If the angles change by f1o1, and f102 due to load
changes in areas I and 2 respectively. Then, the tie-line power changes by
UNIT-3 3. 24
Paavai Institutions Department of EEE
UNIT-3 3. 25
Paavai Institutions Department of EEE
Note that both K and ro2 are positive. From the roots of the characteristic equation we
notice that the system is stable and damped. The frequency of the damped oscillations is
given by ��𝑜 Since Hand f o are constant, the frequency of oscillations depends
upon the regulation parameter R. Low R gives high K and high damping and vice versa
.We thus conclude from the preceding analysis that the two area system, just as in the case
of a single area system in the uncontrolled mode, has a steady state error but to a lesser extent
and the tie
line power deviation and frequency deviation exhibit oscillations that are damped out later.
UNIT-3 3. 26
Paavai Institutions Department of EEE
QUESTION BANK
PART A
PART-B
1. What are the components of speed governor system of an alternator? Derive its transfer
function with an aid of a block diagram &explain.
2. Two Synchronous generators operating in parallel .Their capacities are 300MW & 400MW.
The drop characteristics of their governor are 4% &5% from no load to full load .Assuming
that the generators are operating at 50HZ at no load, how would be a load of 600MW shared
between them. What will be the system frequency at this load? Assume free governor
actions.
3. Derive the transfer function model and draw the block diagram for a single control area
provided with governor system. From the transfer function derive the expression for steady
state
frequency error for a step load change. (OR)Explain the static & dynamic response of single
area
system.
4. Derive & explain for the transfer function of two area load frequency control system
modelling with static and dynamic response of uncontrolled case
5. Derive & explain for the two area load frequency control with tie line bias control
6. Develop the state variable model of a single area system and state the advantages of
a model
UNIT-3 3. 27
Paavai Institutions Department of EEE
UNIT-IV
SYSTEM
CONTROL
REACTIVE POWER
VOLTAGE CONTROL
UNIT-IV 4. 1
Paavai Institutions Department of EEE
CONTENTS
TECHNICAL TERMS
4.1 INTRODUCTION
4.2 REACTIVE POWER
4.3 GENERATION
AND
4.3.1 Synchronous Generator
ABSORPTION OF
REACTIVE
4.3.2 Synchronous Compensator
POWER
4.3.3 Capacitance and Inductive Component
4.4 METHODS OF VOLTAGE CONTROL
4.4.1 Reactors
4.4.2 Shunt Capacitor Series
4.4.3 Capacitor Synchronous
4.4.4 Compensator Static VAR
4.4.5 Compensator
4.5 TYPES OF SVC
4.6 APPLICATION OF STATIC VAR COMPENSATOR
4.7 EXCITATION SYSTEM REQUIREMENTS
4.8 ELEMENTS OF EXCITATION SYSTEM
4.9 TYPES OF EXCITATION SYSTEM
4.9.1 Static Excitation System
4.9.2 Brushless Excitation System
4.9.3 AC Excitation System
4.9.4 Excitation System
4.10 RECENT DEVELOPMENT AND FUTURE TRENDS
4.11 MODELING OF EXCITATION SYSTEM
4.12 STEADY STATE PERFORMANCE EVALUATION
4.13 DYNAMIC RESPONSE OF VOLTAGE REGULATOR
CIRCUIT
UNIT-IV 4. 2
Paavai Institutions Department of EEE
TECHNICAL TERMS
Regulator: Process and amplifies input control signals to alevel and form appropriate
for control of the exciter. This includes both regulating and excitation system
stabilizing function.
Power Exchange: The entity that will establish a competitive spot market for electric
power through day- and/or hour-ahead auction of generation and demand bids.
Exciter: provides dc power to the synchronous machine field winding constituting the
power stage of the excitation system.
Prime Mover: The engine, turbine, water wheel, or similar machine that drives an
electric generator; or, for reporting purposes, a device that converts energy to
electricity directly (e.g., photovoltaic solar and fuel cell(s)).
Regulation: The governmental function of controlling or directing economic entities
through the process of rulemaking and adjudication
Reserve Margin (Operating): The amount of unused available capability of an
electric power system at peak load for a utility system as a percentage of total
capability.
Restructuring: The process of replacing a monopoly system of electric utilities with
competing sellers, allowing individual retail customers to choose their electricity
supplier but still receive delivery over the power lines of the local utility. It includes
the reconfiguration of the vertically-integrated electric utility.
Power system stabilizer: Provides an additional input signal to the regulator to damp
power system oscillation;
Revenue: The total amount of money received by a firm from sales of its products
and/or services, gains from the sales or exchange of assets, interest and dividends
earned on investments, and other increases in the owner's equity except those arising
from capital adjustments.
Substation: Facility equipment that switches, changes, or regulates electric voltage.
Demand (Electric): The rate at which electric energy is delivered to or by a system,
part of a system, or piece of equipment, at a given instant or averaged over any
designated period of time.
UNIT-IV 4. 3
Paavai Institutions Department of EEE
4.1. INTRODUCTION
There has been a very large effort to understand reactive power and voltage control
issues in power systems in the last 15 years .While this work has produced a
significant
volume of results that explain various phenomena and propose potential
solutions to
problems, much of it has not been taken to the stage of useful application software and
hardware in actual power systems. In addition, there remain serious issues of how
traditional
controls impact the interaction between the flow of real and reactive power on a
system level
when an objective Might be to maximize real power transfer capabilities. There has
been a
strong temptation to try and separate the voltage/MVAR problems with the angle/MW
problems. While this separation is valuable because it allows decoupling that might be
useful
in some computational algorithms and in understanding fundamental phenomena, this
separation cannot be made when systems are stressed to their physical limitations. On
the
contrary, the interaction between real and reactive power (and voltage
magnitudes and
4.2. REACTIVE POWER
angles) becomes very complex under these extreme conditions. This chapter begins
with anReactive power is an odd topic in AC (Alternating Current) power systems, and it's
introduction to reactive
usually explained power
with vector and howoritphase-shift
mathematics relates tosine
voltage control.However,
wave graphs. This is
followed
a non- by
several examples
math verbal that illustrate
explanation problems
is possible. which
Note that remainpower
Reactive in the
onlyoperations
becomes
environment of
important when
electric powerload"
an "electrical systems.
or a home appliance contains coils or capacitors. If the electrical
load
behaves purely as a resistor, (such as a heater or incandescent bulb for example,) then
the
device consumes "real power" only. Reactive power and "power factor" can be
ignored, and
it can be analyzed using an AC version of Ohm's law. Reactive power is simply this:
when a
coil or capacitor is connected to an AC power supply, the coil or capacitor stores
electrical
energy during one-fourth of an AC cycle. But then during the next quarter-cycle, the
coil or
capacitor dumps all the stored energy back into the distant AC power supply.
UNIT-IVIdeal coils and capacitors consume no electrical energy, yet they create a significant 4. 4
electric current. This is very different from a resistor which genuinely consumes
electrical
Paavai Institutions Department of EEE
then electrical energy will periodically return to the power plant, and it will flow back and
forth across the power lines. This leads to an extra current in the power lines, a current which
heats the power lines, but which isn't used to provide energy to the appliance. The coil or
capacitor causes electrical energy to begin "sloshing" back and forth between the appliance
and the distant AC
Generator. Electric companies must install heavier wires to tolerate the excess current,
and they will charge extra for this "unused" energy. This undesired "energy sloshing"
effect
can be eliminated. If an electrical load contains both a coil and capacitor, and if their
resonant
frequency is adjusted to exactly 60Hz, then the coil and capacitor like magic will
begin to
behave like a pure resistor. The "energy sloshing" still occurs, but now it's all
happening
between the coil and capacitor, and not in the AC power lines. So, if your appliance
contains
a large coil induction motor, you can make the motor behave as a pure resistor, and
reduce
the current in the power lines by connecting the right value of capacitance across the
motor
coil. Why is reactive power so confusing? Well, the math is daunting if not entirely
obscure.
And the concept of "imaginary power" puts many people off. But this is not
the
4.3.only
GENERATION AND ABSORPTION OF REACTIVE POWER
problem. Unfortunately
4.3.1. Synchronous most of us are taught in grade school that an electric current is
Generators:
a flow
Synchronous machines can be made to generate or absorb reactive power depending
of energy, and that energy flows back and forth in AC power lines. This is completely
wrong. upon the excitation (a form of generator control) applied. The ability to supply
reactive power
In fact the energy flows constantly forward, going from source to load. It's only the
charges is determined by the short circuit ratio.
4.3.2.
of the Synchronous Compensators:
metal wires which flow back
and forth.
Certain smaller generators, once run up to speed and synchronized to the system, can
be declutched from their turbine and provide reactive power without producing real power.
4.3.3. Capacitive and Inductive Compensators:
These are devices that can be connected to the system to adjust voltage levels .A
capacitive compensator produces an electric field thereby generating reactive power An
inductive compensator produces a magnetic field to absorb reactive power. Compensation
UNIT-IV 4. 5
Paavai Institutions Department of EEE
devices are available as either capacitive or inductive alone or as a hybrid to provide both
generation and absorption of reactive power.
1. Overhead lines and underground cables, when operating at the normal system voltage, both
produce strong electric fields and so generate reactive power.
2. When current flows through a line or cable it produces a magnetic field which absorbs
reactive power.
3. A lightly loaded overhead line is a net generator of reactive power while a heavily loaded
line is a net absorber of reactive power.
4. In the case of cables designed for use at 275 or 400kV the reactive power generated by the
electric field is always greater than the reactive power absorbed by the magnetic field and so
cables are always net generators of reactive power.
5. Transformers always absorb reactive power.
UNIT-IV 4. 6
Paavai Institutions Department of EEE
limit. However, they give rise to additional problems like high voltage transients, sub-
synchronous resonance, etc. Shunt capacitors are used for reactive compensation. Simplicity
and low cost are the chief considerations for using shunt capacitor. Further, for expanding
systems additions can be made. Fig. shows the connected of shunt capacitors through the
tertiary of a transformer.
UNIT-IV 4. 7
Paavai Institutions Department of EEE
2. If the voltage drop is the limiting factor, series capacitors are effective; also to some extent
the voltage fluctuations can be evened.
3. If the total line reactance is high, series capacitors are very effective and stability is
improved.
4. With series capacitors the reduction in line current is small, hence if the thermal
considerations limits the current, little advantage is from this, so shunt compensation is to be
used.
A great advantage of the method is the flexible operation for all load
conditions. Being a rotating machine, its stored energy is useful for riding through transient
disturbances, including voltage drops.
Figure4.4:Synchronous Compensator
4.4.5. Static VAR compensators:
In Recent years reactive compensation of charging power is made feasible with the
application of 3-phase, thyristor, and power controller circuits with automatic
control
functions.
UNIT-IV 4. 8
Paavai Institutions Department of EEE
The term static var compensator is applied to a number of static var compensation
devices for use in shunt reactive control. These devices consist of shunt connected, static
reactive element (linear or non linear reactors and capacitors) configured into a var
compensating system. Some possible configurations are shown in above Figure. Even though
the capacitors and reactors in are shown in figure connected to the low voltage side of a
down transformer, the capacitor banks may be distributed between high and low voltage
buses. The capacitor bank often includes, in part, harmonic filters which prevent the
harmonic currents from flowing in the transformer and the high voltage system. Filters for the
5th and 7th harmonics are generally provided. The thyristor controlled reactor (TCR) is
operated on the low voltage bus. In another form of the compensator illustrated in Figure the
reactor compensator is connected to the secondary of a transformer.
windings. The delta connected tertiary winding will effectively compensate the triple
harmonics. The capacitor bank is normally subdivided and connected to the substation bus
bar via one circuit breaker per sub bank. The regulator generates firing pulses for the thyristor
network in such a way that the reactive power required to meet the control objective at the
primary side of the compensator is obtained. The reactor transformer has a practically linear
characteristic from no load to full load condition. Thus, even under all stained over voltages;
hardly any harmonic content is generated due to saturation. The transformer core has non
ferromagnetic .Gaps to the required linearity.
The current flowing in the inductance would be different in each half cycle, varying
with the conduction angle such that each successive half cycle is a smaller segment of a sine
wave. The fundamental component of inductor current is then reduced to each case. Quick
control can be exercised within one half cycles, just by giving a proper step input to the firing
angle control Static var compensators when installed reduce the voltage swings at the rolling
mill and power system buses in drive system applications. They compensate for the average
reactive power requirements and improve power factor.
Electric arc furnaces impose extremely difficult service requirements on electrical
power systems since the changes in arc furnace load impedance are rapid. Random and
non
symmetrical. The three phases of a static var compensator can be located
independently so
that it compensates for the unbalanced reactive load of the furnace and the thyristor
controller
will respond quickly in order to minimize the voltage fluctuations or voltage flicker
seen by
the
system.
UNIT-IV 4. 11
Paavai Institutions Department of EEE
Thus, the furnace characteristics are made more acceptable to the power system by the static
var compensator. Above figure shows the application of the static var compensator to an arc
furnace installation for reactive power compensation at the HV bus level.
UNIT-IV 4. 12
Paavai Institutions Department of EEE
Regulator: Process and amplifies input control signals to a level and form appropriate for
control of the exciter. This includes both regulating and excitation system stabilizing
function.
Power system stabilizer: provides an additional input signal to the regulator to damp
power system oscillation.
Limiters and protective circuits: These include a wide array of control and protective
function which ensure that the capability limits of the exciter and synchronous generator
are not exceeded.
Figure 4.9: Schematic picture of a synchronous machine with excitation system with
several control, protection, and supervisory functions.
UNIT-IV 4. 13
Paavai Institutions Department of EEE
power plant’s auxiliary power system, normally containing batteries. In the latter case,
the synchronous machine can be started against an unenergised net, “black start”. The
batteries are usually charged from the net.
UNIT-IV 4. 14
Paavai Institutions Department of EEE
UNIT-IV 4. 15
Paavai Institutions Department of EEE
When the exciter is operated at rated speed at no load, the record of voltage as function of
time with a step change that drives the exciter to its ceiling voltage is called the exciter build
up curve. Such a response curve is show in Figure.4.14
UNIT-IV 4. 16
Paavai Institutions Department of EEE
SCR
Response Conventional
exciter
ratio Exciter
In general the present day practice is to use 125V excitation up to IOMVA units and
250V systems up to 100MVA units. Units generating power beyond IOOMVA have
excitation system voltages variedly. Some use 350V and 375V system while some go up to
500V excitation system.
voltage. Therefore, the voltage control system is also called as excitation control
system or automatic voltage regulator (AVR).
For the alternators, the excitation is provided by a device (another machine or a
static device) called exciter. For a large alternator the exciter may be required to supply a
field current of as large as 6500A at 500V and hence the exciter is a fairly large
machine. Depending on the way the dc supply is given to the field winding of the alternator
(which is on the rotor), the exciters are classified as: i) DC Exciters; ii) AC Exciters;
and iii) Static Exciters. Accordingly, several standard block diagrams are developed by
the IEEE working group to represent the excitation system. A schematic of an
excitation control system is shown in Fig4.16
UNIT-IV 4. 19
Paavai Institutions Department of EEE
The control loop must regulate the output voltage VI so that the error is made equal to
zero. It is also imperative that the response must be reasonably fast, yet not cause any
instability problem.
The performance of the AVR loop is measured by its ability to regulate the
terminal voltage of the generator within prescribed static accuracy limit with an
acceptable speed of response. Suppose the static accuracy limit is denoted by Ac in
UNIT-IV 4. 20
Paavai Institutions Department of EEE
percentage with reference to the nominal value. The error voltage is to be less than
(Ac/100)∆|V|ref.
From the block diagram, for a steady state error voltage ∆e;
=1- ∆ [V]ref
∆e=1- ∆ [V]ref
= 1- ∆ [V]ref
= ∆ [V]ref
= ∆ [V]ref
Larger the overall gain of the forward block gain K smaller is the steady state error. But too
large a gain K cans instability.
UNIT-IV 4. 21
Paavai Institutions Department of EEE
The response depends upon the roots of the characteristic eqn. 1 + G(S) = o.
As there are three time constants, we may write the three roots as S1, S2 and S3. A typical
root locus plot is shown in Figure
From the plot, it can be observed that at gain higher than Kc the control loop becomes ln
stable.
UNIT-IV 4. 22
Paavai Institutions Department of EEE
QUESTION BANK
PART- A
PART-B
1. Derive the relation between voltage, power
& reactive power at a node for applications
in
2.
power system control.
3.
Discuss generation and absorption of reactive power.
4.
Discuss about the various methods of voltage control.
5.
Explain different types of static VAR compensators with a phasor diagram.
6.
Explain the A.C and D.C excitation system.
Draw the circuit diagram for a typical excitation system and derive the transfer
function model and draw the block diagram (OR) Draw the diagram of a typical
automatic voltage regulator (AVR) & develop its block diagram representation. (OR)
7.
the typical brushless AVR with static and dynamic performance of AVR loop.
Explain the injection of reactive power by switched capacitors to maintain acceptable
voltage profile & to minimize transmission loss in a power system.
UNIT-IV 4. 23
Paavai Institutions Department of EEE
UNIT – V
COMPUTER CONTROL OF
POWER SYSTEMS
UNIT-V 5. 1
Paavai Institutions Department of EEE
CONTENTS
TECHNICAL TERMS
5.1. INTRODUCTION:
5.2. ENERGY CONTROL CENTRE
5.2.1. Functions of Control Centre:
5.2.2. ECC Components
5.2.3. Operation of control centre
5.3. SUPERVISORY CONTROL AND DATA ACQUISITION (SCADA)
5.3.1. Functions of SCADA Systems
5.3.2. Communication technologies
5.3.2.1. SCADA requires communication between Master control station and Remote
control station
5.4. ENERGY MANAGEMENT SYSTEM (EMS)
5.4.1. Functionality Power EMS
5.4.2. Power System Data Acquisition and Control
5.5. NETWORK TOPOLOGY DETERMINATION
5.6. STATE ESTIMATION
5.6.1. Power System Variables
5.7. SECURITY ANALYSIS & CONTROL
5.7.1. Security Control Function
5.7.2. System Security
5.7.3. Security Assessment
UNIT-V 5. 2
Paavai Institutions Department of EEE
TECHNICAL TERMS
Energy Control Centre: Monitors the information continuously for the entire power system
Normal State: Total demand met by satisfying all the operating constraints
Alert State: System is in alert state if security level falls below certain level
Emergency State: Equality constraints are unchanged. This state is reached either directly
from the normal state or via the alert state
Extremis State: Occurs in the absence of any corrective action in time
Monitoring system: monitoring provides up to date information about the power system.
SCADA system: supervisory control and data acquisition system, allows a few operators to
monitor the generation and high voltage transmission systems and to take action to correct
overloads.
Distribution factors: Line outage distribution factor, generation outage distribution factor.
State estimation: State estimation is the process of assigning a value to an unknown system
statevariable based on measurements from that system according to some criteria.
Likelihood criterion: The objective is to maximize the probability that estimate the state
variable x,is the true value of the state variable vector (i.e, to maximize the P(x)=x).
Must run constraint: Some units are given a must run status during certain times of the year
for reason of voltage support on the transmission network.
Post contingency: The state of the power system after a contingency has occurred.
UNIT-V 5. 3
Paavai Institutions Department of EEE
5.1. INTRODUCTION:
Operation in plans with automated control systems work mainly in a central control
room. In olden plants, the controls for the equipment are not centralized and the switch
board
operators control the flow of electricity from a central point, whereas, auxiliary
equipment
operation work throughout the plant, operating and monitoring valves, switches and
gauges.
Electric power systems have grown in size and complexity. Their power generation,
transmission and distribution methods and equipment have constantly improved in
performance and reliability. The power industry in nuclear plant was among the first to
use
analog controls for turbine generators and introduced the use of on-line digital control
computers. These advances were often needed because of the enormous growth in
megawatt
requirements of the power systems.
The satisfactory operating state is given by the following conditions: Frequency
within operating range, bus voltage magnitude with in specified range, current flows
on all
5.2. ENERGY CONTROL CENTRE
transmission lines within ratings, transformers and generators operate within their
The energy control center (ECC) has traditionally been the decision-center for the
ratings,
electric transmission and generation interconnected system. The ECC provides the
and no load shedding anywhere in the system.
functions
necessary for monitoring and coordinating the minute-by-minute physical and
economic
operation of the power system. In the continental U.S., there are only three
interconnected
regions: Eastern, Western, and Texas, but there are many control areas, with each
control
area having its own ECC.
Maintaining integrity and economy of an inter-connected power system requires
Most areas today
significant have a decision-making.
coordinated two-level hierarchy
Soofone
ECCs
of with the Independent
the primary functionsSystem
of the
ECC is to
Operator (ISO) performing the high-level decision-making and the transmission owner ECC
monitor
performing and regulatedecision-making.
the lower-level the physical operation of the interconnected grid.
A high-level view of the ECC is illustrated.Where we can identify the substation, the
remote terminal unit (RTU), a communication link, and the ECC which contains the energy
UNIT-V 5. 4
Paavai Institutions Department of EEE
management system (EMS). The EMS provides the capability of converting the data received
from the substations to the types of screens observed.
In these notes we will introduce the basic components and functionalities of the ECC. Note
that there is no chapter in your text which provides this information.
OPF
Display Alarms
We distinguish EMS from distribution management systems (DMS). Both utilize their own
SCADA, but for different functions. Whereas EMS/SCADA serves the high voltage bulk
transmission system from the ECC, the DMS/SCADA serves the low voltage, distribution
system from a distribution dispatch center. We are addressing in these notes the
EMS/SCADA.
UNIT-V 5. 6
Paavai Institutions Department of EEE
A. 3 level control
1. Turbine –governor to adjust generation to balance changing load-instantaneous
control.
2. AGC (called load frequency control (LFC)) maintains frequency and net power
interchange.
3. Economic Dispatch Control (EDC) distributes the load among the units such that fuel
cost is minimum.
B. Primary Voltage control
1. Excitation control
2. Transmission voltage control, SVC, Shunt capacitors, transformer taps…
Relays located within the RTU, on command from the ECC, open or close selected
control circuits to perform a supervisory action. Such actions may include, for example,
opening or closing of a circuit breaker or switch, modifying a transformer tap setting, raising
or lowering generator MW output or terminal voltage, switching in or out a shunt capacitor or
inductor, and the starting or stopping of a synchronous condenser.
Information gathered by the RTU and communicated to the ECC includes both analog
information and status indicators. Analog information includes, for example, frequency,
voltages, currents, and real and reactive power flows. Status indicators include alarm signals
(over-temperature, low relay battery voltage, illegal entry) and whether switches and circuit
UNIT-V 5. 7
Paavai Institutions Department of EEE
breakers are open or closed. Such information is provided to the ECC through a periodic scan
of all RTUs. A 2 second scan cycle is typical.
UNIT-V 5. 8
Paavai Institutions Department of EEE
Protection functions:
Substation protection functions includes the monitoring of events like start, trip
indication and relay operating time and setting and reading of relay parameters.
Protection of bus bars. Line feeders, transformers, generators.
Protection monitoring (status, events, measurements, parameters, recorders)
Adaptive protection by switch-over of the active parameter set.
The earliest form of signal circuit used for SCADA telemetry consisted of twisted pair
wires; although simple and economic for short distances, it suffers from reliability problems
due to breakage, water ingress, and ground potential risk during faults.
UNIT-V 5. 9
Paavai Institutions Department of EEE
Computer Indicatin
g
Quantity Transducer A/D Telemeter Telemeter meter
to be converter transmitte receiver
telemetere r D/A Recordin
d converter g
Signal circuit (wire meter
line, PLC, microwave,
etc.)
Figure 5.2: Block Diagram of Telemetering System
Improvements over twisted pair wires came in the form of what is now the most
common, traditional type of telemetry mediums based on leased-wire, power-line carrier, or
microwave. These are voice grade forms of telemetry, meaning they represent
communication channels suitable for the transmission of speech, either digital or analog,
generally with a frequency range of about 300 to 3000 Hz.
5.3.2.1. SCADA requires communication between Master control station and Remote
control station:
UNIT-V 5. 10
Paavai Institutions Department of EEE
A more recent development has concerned the use of fiber optic cable, a technology capable
of extremely fast communication speeds. Although cost was originally prohibitive, it has now
decreased to the point where it is viable. Fiber optics may be either run inside underground
power cables or they may be fastened to overhead transmission line towers just below the
lines. They may also be run within the shield wire suspended above the transmission lines.
One easily sees that communication engineering is very important to power system
control. Students specializing in power and energy systems should strongly consider taking
communications courses to have this background. Students specializing in communication
should consider taking power systems courses as an application area.
UNIT-V 5. 11
Paavai Institutions Department of EEE
The EMS is a software system. Most utility companies purchase their EMS from one
or more EMS vendors. These EMS vendors are companies specializing in design,
development, installation, and maintenance of EMS within ECCs. There are a number of
EMS vendors in the U.S., and they hire many power system engineers with good software
development capabilities.
During the time period of the 1970s through about 2000, almost all EMS software
applications were developed for installation on the control centers computers. An attractive
alternative today is, however, the application service provider, where the software resides on
the vendor‟s computer and control center personnel access it from the Internet. Benefits from
this arrangement include application flexibility and reliability in the software system and
reduced installation cost.
One can observe from Figure 3 that the EMS consists of 4 major functions: network model
building (including topology processing and state estimation), security assessment, automatic
generation control, and dispatch. These functions are described in more detail in the
following subsections.
UNIT-V 5. 12
Paavai Institutions Department of EEE
UNIT-V 5. 13
Paavai Institutions Department of EEE
• Logging: Logs all operator entry, all alarms, and selected information.
• Load shed: Provides both automatic and operator-initiated tripping of load in response to
system emergencies.
• Trending: Plots measurements on selected time scales.
Since the master station is critical to power system operations, its functions are
generally distributed among several computer systems depending on specific design. A dual
computer system configured in primary and standby modes is most common. SCADA
functions are listed below without stating which computer has specific responsibility.
UNIT-V 5. 14
Paavai Institutions Department of EEE
The first and second objectives are met by monitoring an error signal, called area
control error (ACE), which is a combination of net interchange error and frequency error and
represents the power imbalance between generation and load at any instant. This ACE must
be filtered or smoothed such that excessive and random changes in ACE are not translated
into control action. Since these excessive changes are different for different systems, the filter
parameters have to be tuned specifically for each control area.
The filtered ACE is then used to obtain the proportional plus integral control signal.
This control signal is modified by limiters, deadbands, and gain constants that are tuned to
the particular system. This control signal is then divided among the generating units under
control by using participation factors to obtain unit control errors (UCE).
These participation factors may be proportional to the inverse of the second derivative
of the cost of unit generation so that the units would be loaded according to their costs, thus
meeting the third objective. However, cost may not be the only consideration because the
different units may have different response rates and it may be necessary to move the faster
generators more to obtain an acceptable response. The UCEs are then sent to the various units
under control and the generating units monitored to see that the corrections take place. This
control action is repeated every 2 to 6 s. In spite of the integral control, errors in frequency
and net interchange do tend to accumulate over time. These time errors and accumulated
interchange errors have to be corrected by adjusting the controller settings according to
procedures agreed upon by the whole interconnection. These accumulated errors as well as
ACE serve as performance measures for LFC.
The main philosophy in the design of LFC is that each system should follow its own
load very closely during normal operation, while during emergencies; each system should
contribute according to its relative size in the interconnection without regard to the locality of
the emergency. Thus, the most important factor in obtaining good control of a system is its
inherent capability of following its own load. This is guaranteed if the system has adequate
regulation margin as well as adequate response capability. Systems that have mainly thermal
generation often have difficulty in keeping up with the load because of the slow response of
the units.
UNIT-V 5. 16
Paavai Institutions Department of EEE
The topology of the network is determined before the determination of system states using
state estimation. Network topology is done by a network configuration that establishes the
configuration of the power system network based on the telemetric breaker and switch status.
• In order to run the state estimator, we must know how the transmission lines are
connected to the load and generation buses
• Network topology program
– The program that reconfigures the electrical model
UNIT-V 5. 17
Paavai Institutions Department of EEE
L= Line index
I= bus index
= change in megawatt power flow on line l when a change in generation occurs at bus i
= change in generation at bus i
The ali factor represents the sensitivity of the flow on line l to a change in generation at bus i.
Distribution factors:
be the change in MW injection at jth bus
be the change in MW flow in ith line
UNIT-V 5. 18
Paavai Institutions Department of EEE
Since loads and generation change continuously, the power system never attains a
steady state. For the purpose of mathematical analysis, however, a steady state operating
point over a short interval of time may be considered where the changes in system variables
are within reasonable limits.
Security monitoring is the on line identification of the actual operating conditions of a power
system. It requires system wide instrumentation to gather the system data as well as a means
for the on line determination of network topology involving an open or closed position of
circuit breakers. A state estimation has been developed to get the best estimate of the status
.the state estimation provides the database for security analysis shown in fig.5.6.
Data acquisition:
1. To process from RTU
2. To check status values against normal value
3. To send alarm conditions to alarm processor
4. To check analog measurements against limits.
Alarm processor:
1. To send alarm messages
2. To transmit messages according to priority
UNIT-V 5. 20
Paavai Institutions Department of EEE
Status processor:
1. To determine status of each substation for proper connection.
Reserve monitor:
1. To check generator MW output on all units against unit limits
State estimator:
1. To determine system state variables
2. To detect the presence of bad measures values.
3. To identify the location of bad measurements
4. To initialize the network model for other
programs
UNIT-V 5. 21
Paavai Institutions Department of EEE
Contingency analysis.
Optimal power flow.
Security enhancement-existing overload using corrective control action.
Preventive action.
Short circuit analysis.
generators, and
Paavai Institutions Department of EEE
state: the current state if executing the real-time network sequence; a postulated state if
executing a study sequence. Sequence means sequential execution of programs that perform
the following steps:
1. Determine the state of the system based on either current or postulated conditions.
2. Process a list of contingencies to determine the consequences of each contingency on the
system in its specified state.
3. Determine preventive or corrective action for those contingencies which represent
unacceptable risk.
Security control requires topological processing to build network models and uses large-scale
AC network analysis to determine system conditions. The required applications are grouped
as a network subsystem that typically includes the following functions:
• Topology processor: Processes real-time status measurements to determine an electrical
connectivity (bus) model of the power system network.
• State estimator: Uses real-time status and analog measurements to determine the „„best‟‟
estimate of the state of the power system. It uses a redundant set of measurements; calculates
voltages, phase angles, and power flows for all components in the system; and reports
overload conditions.
• Power flow: Determines the steady-state conditions of the power system network for a
specified generation and load pattern. Calculates voltages, phase angles, and flows across the
entire system.
• Contingency analysis: Assesses the impact of a set of contingencies on the state of the
power system and identifies potentially harmful contingencies that cause operating limit
violations.
Optimal power flow: Recommends controller actions to optimize a specified objective
function (such as system operating cost or losses) subject to a set of power system operating
constraints.
• Security enhancement: Recommends corrective control actions to be taken to alleviate an
existing or potential overload in the system while ensuring minimal operational cost.
• Preventive action: Recommends control actions to be taken in a “preventive” mode before a
contingency occurs to preclude an overload situation if the contingency were to occur.
• Bus load forecasting: Uses real-time measurements to adaptively forecast loads for the
electrical connectivity (bus) model of the power system network.
UNIT-V 5. 23
Paavai Institutions Department of EEE
• Transmission loss factors: Determines incremental loss sensitivities for generating units;
calculates the impact on losses if the output of a unit were to be increased by 1 MW.
• Short-circuit analysis: Determines fault currents for single-phase and three-phase faults for
fault locations across the entire power system network.
UNIT-V 5. 24
Paavai Institutions Department of EEE
1. Normal state
2. Alert state
3. Emergency state
4. Extremis state
5. Restorative state
Normal state:
A system is said to be in normal if both load and operating constraints are satisfied .It is one
in which the total demand on the system is met by satisfying all the operating constraints.
Alert state:
A normal state of the system said to be in alert state if one or more of the postulated
contingency states, consists of the constraint limits violated. When the system security level
falls below a certain level or the probability of disturbance increases, the system may be in
alert state .All equalities and inequalities are satisfied, but on the event of a disturbance, the
system may not have all the inequality constraints satisfied. If severe disturbance occurs, the
system will push into emergency state. To bring back the system to secure state, preventive
control action is carried out.
Emergency state:
The system is said to be in emergency state if one or more operating constraints are violated,
but the load constraint is satisfied .In this state, the equality constraints are unchanged. The
system will return to the normal or alert state by means of corrective actions, disconnection of
faulted section or load sharing.
Extremis state:
When the system is in emergency, if no proper corrective action is taken in time, then it goes
to either emergency state or extremis state. In this regard neither the load or nor the operating
constraint is satisfied, this result is islanding. Also the generating units are strained beyond
their capacity .So emergency control action is done to bring back the system state either to
the emergency state or normal state.
Restorative state:
From this state, the system may be brought back either to alert state or secure state .The latter
is a slow process. Hence, in certain cases, first the system is brought back to alert state and
then to the secure state .This is done using restorative control action.
UNIT-V 5. 25
Paavai Institutions Department of EEE
QUESTION BANK
PART A
UNIT-V 5. 26