Professional Documents
Culture Documents
6c. Chapter 5 (Part 4) - Precedence Diagram
6c. Chapter 5 (Part 4) - Precedence Diagram
Time Calculation
PRECEDENCE DIAGRAM
LOGO
LEARNING OUTCOME
ES Activity EF
Description
LS (Duration) LF
LOGO
AON
A
C both A and B must finish before C can start
B
A B
A must finish before B can start
Dummy both A and C must finish before D can start
C
8 D
LOGO
Basic Elements
Nodes
Represents activities .
Lines
Represents activity links which are used
to represent the dependencies between
activities.
Lag Time
Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
LOGO
Lag Time
Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
Typically a positive value.
However, if there is a need to overlap 2
activities, the lag time is assigned as a
negative value and more appropriately
called LEAD time.
LOGO
Types :
1. Finish-to-Start Relationship (FS)
2. Start-to-Start Relationship (SS)
3. Finish-to-Finish Relationship (FF)
4. Start-to-Finish Relationship (SF)
Finish to Start
A B
FINISH START
Lag 7 B
A
Start to Start
Applies to schedule the start of a
successor activity at the same time as or
after some lag time to the start of a
predecessor activity.
START START
A B
LOGO
SS
Example:
If activity A is Pour Concrete for slab &
Activity B is Level and Smooth Concrete,
• Activity B cannot start until A has started
but should begin immediately after the
start of A.
• Therefore, SS relationship between A and
B is assigned a lag time equals zero.
SS = O
Start-to-Start (SS)
SS=Lag 3 Q
P
Install Insulation
Finish to Finish
A B
Finish-to-Finish (FF)
FF=Lag 3 Q
P
FF=3 days
Installation Testing
Siti Rashidah Mohd Nasir @ copyright -
Aug 2004
LOGO
Type of Relationship
Start to Finish
A B
Start-to-Finish (SF)
Lag 3 B
A
Finish Start
• SS – Start Start
Start Start
• FF – Finish Finish
Finish Finish23
LOGO
Forward pass
Determine ES & EF.
Backward pass
Determine LS & LF.
LOGO
Advantages of Precedence
Diagram Over CPM
No usage of Dummy.
Ease of changing logic and adding additional
activities.
Planning could be done with less activities.
Code or activity number need not be changed
when logic was to be changed.
Permits other relationships such as FF and SS
whereby CPM only does FS relationship.
Allow for time lag quantities.
LOGO
CONTINUOUS PRECEDENCE
DIAGRAM
Continuous PD
A continuous duration means that once
an activity begins, it must be worked on
continuously until it is finished.
Q.1
LOGO
TRY THIS
LOGO
FORWARD
LOGO
BACKWARD
LOGO
CRITICAL PATH
LOGO
Float Calculation
40
Q.3
B FF=3
FS
5 =2
G
SS=4 E 10
3
C I
A
6 5
2
SS=3 F H
8 2
D
4
FF=6
Q.4
2 B 7 FF=3
FS
5 =2
5 G 15
SS=4 9 E 12 10
3
2 C 8
18
I 23
0 A 2
6 5
2
SS=3 8 F 16 16
H 18
8 2
4 D8
4
FF=6
Q.4
2 B 7 FF=3
FS
5 5 10
=2
5 G 15
SS=4 9 E 12 10
8 18
12 3 15
18 23
2 C 8 I
0 A 2
5
0 2 2 5 6 18 23
11
SS=3 8 F 16 16
H 18
8 8 16 2
16 18
4 D8
4 4 8
FF=6
Q.3
B FF=3
FS
5 =2
G
SS=4 E 10
3
C I
A
6 5
2
SS=3 F H
8 2
D
4
FF=6
LOGO
Q.6 Factory Project Foundation