Download as ppt, pdf, or txt
Download as ppt, pdf, or txt
You are on page 1of 41

LOGO

Time Calculation

PRECEDENCE DIAGRAM
LOGO
LEARNING OUTCOME

Students will be able to:


 Understand Precedence Diagram
programming technique.
 Calculate the ES, EF, LS, LF, TF and FF
in a Precedence Diagram.
LOGO
Labelling of Precedence Activity

ES Activity EF
Description

LS (Duration) LF
LOGO
AON

 ES – how SOON can the activity start?


 EF – how SOON can the activity finish?
 LS – how LATE can the activity start?
 LF – how LATE can the activity finish?

Siti Rashidah Mohd Nasir @ copyright -


Aug 2004
AON FUNDAMENTALS
A is preceded by nothing
A B C
B is preceded by A
C is preceded by B
B
A B and C are preceded by A

A ABC can all begin


at the same time
BUT ABC must be
B D completed before
D can begin
C
Siti Rashidah Mohd Nasir @ copyright -
Aug 2004
Situations in network diagram
B
A A must finish before either B or C can start

A
C both A and B must finish before C can start
B

A B
A must finish before B can start
Dummy both A and C must finish before D can start
C
8 D
LOGO
Basic Elements

 Nodes
 Represents activities .
 Lines
 Represents activity links which are used
to represent the dependencies between
activities.
 Lag Time
 Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
LOGO

 Lag Time
 Time period that separates or designates
a waiting period between 2 activities.-a
predecessor & a successor.
 Typically a positive value.
 However, if there is a need to overlap 2
activities, the lag time is assigned as a
negative value and more appropriately
called LEAD time.
LOGO

 PREDECESSOR – any activity that must be


completed b4 a given activity can be started.
 SUCCESSOR – any activity that cannot
start until a given activity has been
completed.
LOGO
AON – Use of Lags

Types :
1. Finish-to-Start Relationship (FS)
2. Start-to-Start Relationship (SS)
3. Finish-to-Finish Relationship (FF)
4. Start-to-Finish Relationship (SF)

Most commonly used are Start-to-Start


(SS), Finish-to-Finish (FF) and
combination of this two.

Siti Rashidah Mohd Nasir @ copyright -


Aug 2004
LOGO
Type of Relationship

 Finish to Start

A B

FINISH START

* Activity B must not start before Activity A has been completed


Finish-to-Start (FS)

Lag 7 B
A

Activity B must be delayed even when the preceding


activity has completed.

Example : removing formworks cannot begin until concrete


has cured for 7 days.

PM must carefully checked the lag time to reduce the risk


of being late.
Siti Rashidah Mohd Nasir @ copyright -
Aug 2004
LOGO
Type of Relationship

 Start to Start
 Applies to schedule the start of a
successor activity at the same time as or
after some lag time to the start of a
predecessor activity.
START START

A B
LOGO
SS

 Example:
 If activity A is Pour Concrete for slab &
Activity B is Level and Smooth Concrete,
• Activity B cannot start until A has started
but should begin immediately after the
start of A.
• Therefore, SS relationship between A and
B is assigned a lag time equals zero.
SS = O
Start-to-Start (SS)

SS=Lag 3 Q
P

Activity Q cannot begin until 3 days after activity P begins.

Example : pipes laying project.

SS=3 days SS=5 days


Trench Lay pipe Refill

Siti Rashidah Mohd Nasir @ copyright -


Aug 2004
LOGO
SS with lag

Install Insulation

Install & Finish dry wall


SS = 1
LOGO
Type of Relationship

 Finish to Finish

A B
Finish-to-Finish (FF)

FF=Lag 3 Q
P

Activity Q cannot be completed any earlier than 3 days


after P is complete.
Finish of Q depend on finish of P.

Example : testing of equipment.


Note : this is not FS because testing of subcomponents
can begin before the full installation is completed.

FF=3 days
Installation Testing
Siti Rashidah Mohd Nasir @ copyright -
Aug 2004
LOGO
Type of Relationship

 Start to Finish

A B
Start-to-Finish (SF)

Lag 3 B
A

Activity B cannot end until 3 days after A has started.

Example : Testing of Concrete

Lag 3 Testing to check


Casting of concrete
on quality

Siti Rashidah Mohd Nasir @ copyright -


Aug 2004
LOGO
Types of Task Relationships
 FS – Finish Start

Finish Start

• SS – Start Start

Start Start

• FF – Finish Finish

Finish Finish23
LOGO

 Logical relationship in Precedence is


more flexible and versatile compared to
CPM.
 In CPM, logical relationship shows that an
activity must be completed before you
can proceed with the following activities.
Only F-S relationships.
LOGO
Forward & Backward Calculation

 Forward pass
 Determine ES & EF.

 Backward pass
 Determine LS & LF.
LOGO
Advantages of Precedence
Diagram Over CPM
 No usage of Dummy.
 Ease of changing logic and adding additional
activities.
 Planning could be done with less activities.
 Code or activity number need not be changed
when logic was to be changed.
 Permits other relationships such as FF and SS
whereby CPM only does FS relationship.
 Allow for time lag quantities.
LOGO
CONTINUOUS PRECEDENCE
DIAGRAM

Continuous PD
 A continuous duration means that once
an activity begins, it must be worked on
continuously until it is finished.
Q.1
LOGO
TRY THIS
LOGO
FORWARD
LOGO
BACKWARD
LOGO
CRITICAL PATH
LOGO
Float Calculation

 Total Float (TF)


 Same as CPM calculation for TF
 Late Start – Early Start (LS – ES)
OR
 Late Finish – Early Finish (LF – EF)
LOGO
TOTAL FLOAT (LS-ES) @ (LF-EF)
LOGO
Float Calculation

 Free Float (FF)


 For FF calculation, there is no single
formula to calculate FF.
 Reason being that there are 4
relationships in the Precedence Diagram
Method (PDM).
 Based on the Lowest Float of relationship
with successor.
 Therefore, each relationship going to
successors are evaluated.
LOGO
Float (or Slack)
•Total Float – the total amount of time that a
scheduled activity (or milestone) may be delayed or
extended without delaying the project end date or
violating a schedule constraint. (LS-ES @ LF-EF)

•Free Float – the amount of time that a scheduled


activity (or milestone) can be delayed without
delaying the start of the next activity in the network.
(ES act B – EF act A)
•Negative Float – the amount of time that by which a
critical activity (or milestone) misses a required date.

40
Q.3

B FF=3
FS
5 =2
G
SS=4 E 10
3

C I
A
6 5
2

SS=3 F H
8 2
D
4

FF=6
Q.4

2 B 7 FF=3
FS
5 =2
5 G 15
SS=4 9 E 12 10
3

2 C 8
18
I 23

0 A 2
6 5
2

SS=3 8 F 16 16
H 18

8 2
4 D8
4

FF=6
Q.4

2 B 7 FF=3
FS
5 5 10
=2
5 G 15
SS=4 9 E 12 10
8 18
12 3 15
18 23

2 C 8 I
0 A 2
5
0 2 2 5 6 18 23

11

SS=3 8 F 16 16
H 18

8 8 16 2
16 18
4 D8
4 4 8

FF=6
Q.3

B FF=3
FS
5 =2
G
SS=4 E 10
3

C I
A
6 5
2

SS=3 F H
8 2
D
4

FF=6
LOGO
Q.6 Factory Project Foundation

Activity Precedence Duration Constraints


Precedence Relationship
Establish site (A) - 10 - -

Site clearance A 6 A SS6


(B) FF
Piling (C) B 10 B SS4
FF6
Pile cap & C 8 C SS6
ground beam (D) FF2

Represent the above table in a Precedence Diagram.


* Calculate the ES, EF, LS, LF, TF & FF for each activities.
* Assume working days are from Monday to Saturday. Sunday
will be an off day. Public holiday will remain as working day.
* Project will begin on 1/ 7/ 2009.
LOGO
Q. 7 FACTORY PROJECT

ACTIVITIES PRECEDENCE DURATION CONSTRAINTS


PRECEDENCE RELATIONSHIP
Set up site (A) - 5 - -
Site clear (B) A 6 A SS2
FF3
Drainage con (C) A 4 - -
Piling (D) B 8 B SS4
FF4
Main Drainage (E) C 8 - -
Caps & g/beam (F) D 10 D SS5
FF4
G. Flr drainage (G) E, B 10 E SS4
FF3
Erect steel work(H) F 5 - -
Grd Flr Slab(I) G, H 8 - -

You might also like