Government Communication Affairs

Office Complex Project

Mobilization Report
Gov’t Communication Affairs
Office Project
Table of contents
1.General Contract Information.
2.Scope of the Project
3.Major Works Items and Volume
4.Mobilization and Site Organization
5.Challenges Encountered
6.Way Forward
Gov’t Communication Affairs Office
Project
1 - General Contract Information
Client:-Ministry of Urban Development and Housing, Federal Government Buildings
Construction and Administration Bureau
Consultant:-Yohannes Abbay Consulting Architects and Engineers
Contractor :- Tekleberhan Ambaye Construction PLC.
Location:- Arada Sub-city, Woreda 09,(at ERI BEKENTU),Addis Ababa, Ethiopia
Project Amount:- ETB 1,207,195,702.89 with VAT
Project Duration:- 730 Cal days
Commencement date:- 15 days after site hand over

Contract signing date:- Friday, August 12, 2016


Gov’t Communication Affairs Office
Project

2 - Scope of the Project


The project Consists 3 Blocks, Ball Court, Site Work
and 3 Bridges. Covering 14,391.73 m2
Main Building (979 mil.) covers 6,164.74 m2
a) Block A (Auditorium) 4B+G+2
b) Block B (Plaza, Tower) 2B+G+16
c) Block C (Studio) 2B+G+4
Ball Court (6.88 mil.)
Site Work (49.9 mil.)
3 Bridges (13.2 mil.)
Gov’t Communication Affairs Office
Project
Main Building

Bill No. Description Unit Total Amount


A. SUB- STRUCTURE    
1 Excavation and Earth Work ETH. Birr 29,880,422.86
2 Concrete Work ETH. Birr 68,398,045.38
3 Stone Masonery Work ETH. Birr 8,194,661.00
  TOTAL A ETH. Birr 106,473,129.24
B. SUPER- STRUCTURE    
1 Concrete Work ETH. Birr 100,244,607.50
2 Block Work ETH. Birr 9,262,121.00
3 Carpentary and Joinery Work ETH. Birr 124,439,983.00
4 Steel Structural & Metal Work ETH. Birr 314,342,080.91
5 Plastering & Pointing ETH. Birr 11,405,685.00
6 Finishing Works ETH. Birr 64,126,636.24
7 Painting Works ETH. Birr 4,104,918.00
8 Roof Work ETH. Birr 1,535,753.34
9 Water Proofing Works ETH. Birr 8,291,173.00
10 Electrical Installation ETH. Birr 151,909,175.00
11 Sanitary Installation ETH. Birr 57,251,440.57
12 Mechanical Installation ETH. Birr 26,497,016.00
TOTAL B 873,410,589.56
TOTAL A+B 979,883,801.07
Gov’t Communication Affairs Office
Project

Ball Court

Bill No. Description Unit Total Amount

A. SUB- STRUCTURE    

1 Excavation and Earth Work ETH. Birr 1,196,102.74

2 Concrete Work ETH. Birr 196,518.20

  TOTAL A ETH. Birr 1,392,620.94

B. SUPPER- STRUCTURE    

1 Steel Structural & Metal Work ETH. Birr 2,315,700.00

2 Finishing Work ETH. Birr 3,180,645.29

TOTAL B 5,496,345.29

TOTAL A+ B 6,888,966.23
Gov’t Communication Affairs Office
Project
Site Work
Bill No. Description Unit Total Amount
A. SUB- STRUCTURE    
1 Excavation and Earth Work ETH. Birr 5,145,723.38
2 finishing ETH. Birr 11,903,471.66
3 Stone Masonary Work ETH. Birr 3,393,321.66
4 Steel Structure & Metal work ETH. Birr 1,936,920.00
5 Electrical site work ETH. Birr 27,552,934.00
TOTAL A 49,932,370.70
Bridges (3)
Bill No. Description unit Total Amount
A. SUB- STRUCTURE    
1 Excavation and Earth Work ETH. Birr 838,134.64
2 Concrete Work ETH. Birr 11,462,442.17
3 Stone Masonary Work ETH. Birr 503,428.45
4 Steel Structure Work ETH. Birr 226,307.25
TOTAL A 13,241,112.51
Gov’t Communication Affairs Office
Project
3 - Major Work Item and Volume
Summery of Work Items with respect to the Total % tage Share
         
A. SUB- STRUCTURE   AMOUNT % TAGE
1 Concrete Work ETH. Birr 74,676,939.18 7.11%
2 Excavation & Earth Works ETH. Birr 37,060,383.62 3.53%
3 Stone Massonary Works ETH. Birr 12,091,411.11 1.15%
  TOTAL A ETH. Birr 129,208,800.48 12.31%
B. SUPER- STRUCTURE      
1 Steel Structural & Metal Work ETH. Birr 318,820,247.00 30.37%
2 Electrical Installation ETH. Birr 179,392,345.00 17.09%
3 Carpentary & Joinery ETH. Birr 124,491,183.00 11.86%
4 Concrete Work ETH. Birr 105,624,674.07 10.06%
5 Finishing Work ETH. Birr 79,210,753.19 7.55%
6 Sanitary Installation ETH. Birr 57,251,454.76 5.45%
7 Mechanical Installation ETH. Birr 26,497,016.00 2.52%
8 Plastering & Pointing ETH. Birr 11,405,685.00 1.09%
9 Block Work ETH. Birr 9,262,121.00 0.88%
10 Water Proofing Works ETH. Birr 8,291,173.00 0.79%
11 Painting Works ETH. Birr 4,104,918.00 0.39%
12 Roof Work ETH. Birr 1,535,753.34 0.15%
  TOTAL B ETH. Birr 920,507,256.79 87.69%
    TOTAL A+B 1,049,735,459.08  
15% VAT 157,460,318.86  
Grand Total 1,207,195,777.94  
Gov’t Communication Affairs Office Project
4 - Mobilization and Site Organization
Formation of Team and Responsibility Assigning
Team External Assigned Team Leader Responsible
No Major Activity Description Assigned Departments
Leader Advisor Sectors /Facilitator
Design Department
Contrat Adminstration Department
Machinery and Maintenance
1 Site Organization All Technical Members Ato Hailu Abrha
Procurement Department
Safety and Health Department
Human Resource

Dr . Wubshet Jakale & Dr . Girmay Kahsay


Developing Master Schedule Planning and Monitoring Department
Ato Mastewal
2 External Project Team Planning and Monitoring Getahun
Internal Coordination Department
Coordination

Ato Mearg Kahsu


Design Department
3 Design Review All Project Staff Design Department Ato Fikresilassie Sifir
Contract Admin
Special sub contractors
Project Team
Coordination
Planning and Monitoring Department
Machinery and Maintenance Planning and Monitoring
4 Work Methdology Ato Hailu Abrha
Temporary Structures Department
Safety and Health Department
External Consultants
Internal Consultants
Procurement Department
Project Team
5 Procurement Procurement Department Ato Ayele Yeshitela
Coordination
Material Engineer
Gov’t Communication Affairs Office Project
4 - Mobilization and Site Organization
Formation of Team and Responsibility Assigning
Team External Assigned Team Leader Responsible
No Major Activity Description Assigned Departments
Leader Advisor Sectors /Facilitator

Human Resource
6 Man Power Requirement Project Team Human Resource Ato Mesele Hailu

Coordination
Project Team
Temporary Structure

Dr . Wubshet Jakale & Dr . Girmay Kahsay


7 Form Work Design Temporary Structure Ato Belete Wondimu
Procurement
Safety and Health Department
Project Team
Production Department

Ato Mearg Kahsu


8 Production Production Department Ato Yonas Feleke
Procurement
Coordination
Planning and Monitoring Department
Coordination Planning and Monitoring Ato Mastewal
9 Quantification
Department Getahun
Project Team
Contract Admin
Machinery and Maintenance
Machinery and
10 Machinery Coordination Ato Daniel G/Kidan
Maintenance
Project Team
Coordination
Sub Contractors Identification and Planning and Monitoring Department Ato Mastewal
11 Coordination
Selection Getahun
Project Team
Procurement
Gov’t Communication Affairs Office Project
Progress of Each Major Activities
1- Site Organization
 Temporary Facilities are Identified and Listed.
 Temporary Facilities Boq. And Resource Identification on
Progress.
 Site and Building Corner points Surveying Setting out
Completed.
 Detail actual contour of the site is on Progress.
 Clearing of Site Using Laborers is on Progress.
 Agreement for Temporary Office(63m2),385birr/m2 Rent
around site is made.
 Additional rental Space for temporary facilities around site
is requested.
Gov’t Communication Affairs Office Project
Progress of Each Major Activities
2 – Developing Master Schedule
External Master Schedule
 Finished and Submitted.
Internal Schedule
 It is on progress and it will be completed after 10days on
October 10,2016.
Target Cost
 On progress
3 – Design Review
 On progress by Edna Consulting Firm and TACON Design
Dep’t.
 Temporary Facilities Redesign with respect to space around
site is to be considered.
Gov’t Communication Affairs Office Project
Progress of Each Major Activities
4 – Work Methodology
 On Progress and it will be Finalized after one Week (October
8,2016.
5 – Procurement
 Major Sub Structure work Materials Market Assessment
and Requirements
1. Sand
– Suppliers:-
• Four suppliers are listed and signed Agreement which is
delivering the same for running projects in Addis Ababa.
• Unit price of these suppliers-500 Birr /M3
• Cost per 16m3=8000.00 Birr
• Quality assurance will act on site for approval of materials
delivered by suppliers
Gov’t Communication Affairs Office Project

– Company trucks
• Process- site selection will be carried out
• Contact and delivery chain established
• Payments will be affected through drivers.
• Cost per 16m3=5463.00 Birr
• Quality Assurance will identify quarry site for
delivery.
Gov’t Communication Affairs Office Project

2. Gravel
• Source are crushers in and around Addis Ababa
• Five potential suppliers identified.
• Price will be collected after quarry visit is carried
out for quality and potential stock.
3. Cement -
• Delivery based on consultant approval
• Major suppliers were Mugher, Mesobo cement
factories and the Supplier is also Identified.
Gov’t Communication Affairs Office Project

4. Re Bar
• SBG is the major supplier where delivery is made
from YBEL Industry Park Stock
• Other to be considered are East Steel and
Tewolde Gidey
5. Select Materials and Base Course
• Haile Caba and others by analyzing and price
evaluation
Gov’t Communication Affairs Office Project

6. Basaltic Stone
• Source- Haile Fanta is Soule supplier Located behind bole
Industrial Park
• Potential supplier at least three will be assessed and reported.
• From Site excavated rock
7. Wooden product (Eucalyptus)
• For all projects delivery is made from Mahajer Abedella
wooden materials sales shop
• Two evaluations (price, stock and credit facility parameters)
were made and the supplier wins and continues.
• Three suppliers were also included in the suppliers list as
alternative suppliers.
Gov’t Communication Affairs Office Project
Progress of Each Major Activities
6 – Human Resource
 Manning for the project is identified.
Section Description/Job Title Required Number

Project Manager 1
Project Management
Secretary 1
Senior Planning Engineer 1
Planning and Monitoring
Safetey Engineer 1
Senior Office Engineer I 1
Senior Office Engineer II 3
Contract Administrator 1
Office Engineering Designer (Structural) 1
Office Engineer II (Payment) 1
Quantity Surveyor 2
Material Engineer 1
Senior Site Engineer I 1
Site Engineer II 3
Senior Surveyors 2
Surveyors III 2
Construction
General Forman 1
Structural Forman 3
Forman I 1
Forman II 2
Project Finance Section Head 1
Senior Accountant 1
Finance Junior Accountant 1
Cashier 1
Stock Data Collector 1
Project Administrator Section Head 1
Personel Clerk 1
Human Resource Admin
Clinical Nurse 1
Time Keepers 2
Material Management Section Head 1
Material Management Store Keeper I 1
Assistance Store Keepers 3
Costruction Equipment Operation and Maintenance Section
1
Construction Equipment & Machinery Head
Maintenance Equipment Data Analizer 1
Equipment Data Collector 3
Gov’t Communication Affairs Office Project

• The following 21 Manpower are Ready for transfer.


Gov’t Communication Affairs Office Project

Progress of Each Major Activities


7 – Form work and scaffolding
 Design of formwork for all block for footing, foundation column,
suspended slab and beams, elevation column is finalized
 Footing to grade beam already steel panels are secured from Gotera
store and Gambella project, for intermediate beams, steel panel from
gambella project, mekelle university and yayo project will be
demobilized.
 The methodology, single props with beam forming head and steel
panels for intermediate beams, and steel props with shuttering panel for
slabs at least for two slabs for each block.
 These materials will be transported from gambella, judge, Yayo and
Bahirdar
 One store keeper and one formwork and scaffolding supervisor will be
assigned.
Gov’t Communication Affairs Office
Project
Demand of temporary structures
 The estimation is for two slabs of each block
s/n ITEM UOM QUANTITY TO REMARK
DELIVER

1 Steel panel M2 3827.2 Different size


2 Timber beam pcs 11824 Different length
3 Single props with Pcs 8177
accessories
4 Tripod Pcs 3902
5 Shuttering panel M2 6531.25 Different size
6 Universal panel m2 2640 Available only 164m2
7 Circular column mold pcs 13 Different diameters
8 Beam forming head pcs 2500 Designed sample to
be made
ABN SCANDINAVIA OFFER
Gov’t Communication Affairs Office
Project
Progress of Each Major Activities
8 – Production and plant
The estimated quantity of HCB, Selected Material and
Aggregate is communicated.
 Batching plant rent or Buy assessment is under progress
 Aggregate will be supplied through purchase
 HCB will be supplied from Ybel production site
Gov’t Communication Affairs Office
Project
Progress of Each Major Activities
9 – Quantification
• Team formation for actual Quantification is under
progress.
• Sanitary, Electrical, Mechanical and also Civil
works quantification will be done after completion
of team formation and office facilities are fulfilled.
• Rebar quantification and optimization will be
done.
Gov’t Communication
Gov’t Affairs
Communication Office
Affairs Project
Office
Project
Progress of Each Major Activities
Equipm ent Qty. Acquisition type
10 – MachineryExcavator 4
Loader 1 O wned
W ill be decided based on
Dumptruck hauling distance
Tower Crane 1 O wned
Mobile Crane 2 O wend
Truck mounted concrete
pump 53m 1 owend
Trailler Mounted concrete
pump 3 owend
O wned avail. Check/ if not
plate compactor 4 procure
Roller 8-12 tone 1 Rental - 450 birr/hr
Walkbehind roller 1 O wned
Bar cutter 4 Procure
Bar Bender 4 Procure
Truck mixer 4 O wned
Tower light 4 O wned
Gov’t Communication Affairs Office
Project
Progress of Each Major Activities
11 – Subcontractor Identification and Selection
Gov’t Communication Affairs Office
Project
5 – Challenges encountered
External
• Work Permit is not Finalized
• No AutoCAD Drawing
• No Enough space for site organization
• No official boundary coordinates
• Discrepancy between drawing and BOQ on
concrete grade and AR and ST discrepancy
• Missed detailing and No detail for sum structures
• Drafting errors on elevation labeling and axis
Gov’t Communication Affairs Office
Project
5 – Challenges encountered
Internal
• Additional Assignments
• Less Attention of close follow up
• Most Project Staffs are Junior and engaged
on existing projects assignment
• Unavailability of Senior QS
• Unavailability of office and office facilities
Gov’t Communication Affairs Office
Project
6 – Way Forward
• Decision on Formwork Supply
• Finalizing Work Methodology
• Insuring External Space for site organization
• Design Clarifications
• Close Flow up to Finalize the work permit
• Finalize Internal Quantity, Target Cost and
Schedule