Mobilization Report Presentation Mastewal
Mobilization Report Presentation Mastewal
Mobilization Report
Gov’t Communication Affairs
Office Project
Table of contents
1.General Contract Information.
2.Scope of the Project
3.Major Works Items and Volume
4.Mobilization and Site Organization
5.Challenges Encountered
6.Way Forward
Gov’t Communication Affairs Office
Project
1 - General Contract Information
Client:-Ministry of Urban Development and Housing, Federal Government Buildings
Construction and Administration Bureau
Consultant:-Yohannes Abbay Consulting Architects and Engineers
Contractor :- Tekleberhan Ambaye Construction PLC.
Location:- Arada Sub-city, Woreda 09,(at ERI BEKENTU),Addis Ababa, Ethiopia
Project Amount:- ETB 1,207,195,702.89 with VAT
Project Duration:- 730 Cal days
Commencement date:- 15 days after site hand over
•
Gov’t Communication Affairs Office
Project
Ball Court
A. SUB- STRUCTURE
B. SUPPER- STRUCTURE
TOTAL B 5,496,345.29
TOTAL A+ B 6,888,966.23
Gov’t Communication Affairs Office
Project
Site Work
Bill No. Description Unit Total Amount
A. SUB- STRUCTURE
1 Excavation and Earth Work ETH. Birr 5,145,723.38
2 finishing ETH. Birr 11,903,471.66
3 Stone Masonary Work ETH. Birr 3,393,321.66
4 Steel Structure & Metal work ETH. Birr 1,936,920.00
5 Electrical site work ETH. Birr 27,552,934.00
TOTAL A 49,932,370.70
Bridges (3)
Bill No. Description unit Total Amount
A. SUB- STRUCTURE
1 Excavation and Earth Work ETH. Birr 838,134.64
2 Concrete Work ETH. Birr 11,462,442.17
3 Stone Masonary Work ETH. Birr 503,428.45
4 Steel Structure Work ETH. Birr 226,307.25
TOTAL A 13,241,112.51
Gov’t Communication Affairs Office
Project
3 - Major Work Item and Volume
Summery of Work Items with respect to the Total % tage Share
A. SUB- STRUCTURE AMOUNT % TAGE
1 Concrete Work ETH. Birr 74,676,939.18 7.11%
2 Excavation & Earth Works ETH. Birr 37,060,383.62 3.53%
3 Stone Massonary Works ETH. Birr 12,091,411.11 1.15%
TOTAL A ETH. Birr 129,208,800.48 12.31%
B. SUPER- STRUCTURE
1 Steel Structural & Metal Work ETH. Birr 318,820,247.00 30.37%
2 Electrical Installation ETH. Birr 179,392,345.00 17.09%
3 Carpentary & Joinery ETH. Birr 124,491,183.00 11.86%
4 Concrete Work ETH. Birr 105,624,674.07 10.06%
5 Finishing Work ETH. Birr 79,210,753.19 7.55%
6 Sanitary Installation ETH. Birr 57,251,454.76 5.45%
7 Mechanical Installation ETH. Birr 26,497,016.00 2.52%
8 Plastering & Pointing ETH. Birr 11,405,685.00 1.09%
9 Block Work ETH. Birr 9,262,121.00 0.88%
10 Water Proofing Works ETH. Birr 8,291,173.00 0.79%
11 Painting Works ETH. Birr 4,104,918.00 0.39%
12 Roof Work ETH. Birr 1,535,753.34 0.15%
TOTAL B ETH. Birr 920,507,256.79 87.69%
TOTAL A+B 1,049,735,459.08
15% VAT 157,460,318.86
Grand Total 1,207,195,777.94
Gov’t Communication Affairs Office Project
4 - Mobilization and Site Organization
Formation of Team and Responsibility Assigning
Team External Assigned Team Leader Responsible
No Major Activity Description Assigned Departments
Leader Advisor Sectors /Facilitator
Design Department
Contrat Adminstration Department
Machinery and Maintenance
1 Site Organization All Technical Members Ato Hailu Abrha
Procurement Department
Safety and Health Department
Human Resource
Human Resource
6 Man Power Requirement Project Team Human Resource Ato Mesele Hailu
Coordination
Project Team
Temporary Structure
– Company trucks
• Process- site selection will be carried out
• Contact and delivery chain established
• Payments will be affected through drivers.
• Cost per 16m3=5463.00 Birr
• Quality Assurance will identify quarry site for
delivery.
Gov’t Communication Affairs Office Project
2. Gravel
• Source are crushers in and around Addis Ababa
• Five potential suppliers identified.
• Price will be collected after quarry visit is carried
out for quality and potential stock.
3. Cement -
• Delivery based on consultant approval
• Major suppliers were Mugher, Mesobo cement
factories and the Supplier is also Identified.
Gov’t Communication Affairs Office Project
4. Re Bar
• SBG is the major supplier where delivery is made
from YBEL Industry Park Stock
• Other to be considered are East Steel and
Tewolde Gidey
5. Select Materials and Base Course
• Haile Caba and others by analyzing and price
evaluation
Gov’t Communication Affairs Office Project
6. Basaltic Stone
• Source- Haile Fanta is Soule supplier Located behind bole
Industrial Park
• Potential supplier at least three will be assessed and reported.
• From Site excavated rock
7. Wooden product (Eucalyptus)
• For all projects delivery is made from Mahajer Abedella
wooden materials sales shop
• Two evaluations (price, stock and credit facility parameters)
were made and the supplier wins and continues.
• Three suppliers were also included in the suppliers list as
alternative suppliers.
Gov’t Communication Affairs Office Project
Progress of Each Major Activities
6 – Human Resource
Manning for the project is identified.
Section Description/Job Title Required Number
Project Manager 1
Project Management
Secretary 1
Senior Planning Engineer 1
Planning and Monitoring
Safetey Engineer 1
Senior Office Engineer I 1
Senior Office Engineer II 3
Contract Administrator 1
Office Engineering Designer (Structural) 1
Office Engineer II (Payment) 1
Quantity Surveyor 2
Material Engineer 1
Senior Site Engineer I 1
Site Engineer II 3
Senior Surveyors 2
Surveyors III 2
Construction
General Forman 1
Structural Forman 3
Forman I 1
Forman II 2
Project Finance Section Head 1
Senior Accountant 1
Finance Junior Accountant 1
Cashier 1
Stock Data Collector 1
Project Administrator Section Head 1
Personel Clerk 1
Human Resource Admin
Clinical Nurse 1
Time Keepers 2
Material Management Section Head 1
Material Management Store Keeper I 1
Assistance Store Keepers 3
Costruction Equipment Operation and Maintenance Section
1
Construction Equipment & Machinery Head
Maintenance Equipment Data Analizer 1
Equipment Data Collector 3
Gov’t Communication Affairs Office Project