Professional Documents
Culture Documents
PAK Transformer Study 15Nov2019NREL v2
PAK Transformer Study 15Nov2019NREL v2
Overloaded Transformers
RE-ENERGISING THE OVERLOADED TRANSFORMERS
Ian Baring-Gould | November 2019
Pakistan Transformer Overloading Study
RE-ENERGISING THE OVERLOADED TRANSFORMERS
2
Summary
• Background
• Purpose
• Electric Power System: Overview
• Power Transformer : Example Case Study
• Methodology: System Sizing
• Desktop Design: Openwind | Helioscope
• Benefits/Conclusions
3
Background: Regional Transformer Study
47 (Overloaded Transformers)
Transformer: Overloading and Loss of Life
• Ambient temperature
• Hot-spot temperature (h)
• % of Insulation life
=A.
• Per Unit Life
=C
70 69 8
8
60 7
6
50 6
No of Transformers
5
40
4
30
3
3
20 17
2
12
10 7
5 5 5 1
3 3 3 3 3
1
0
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
0
0
12
16
24
26
10
14
18
20
22
Hour of Day
% Overloading
8
Electric Power System: Overview
Year 2017
Year 2018
https://www.aimspress.com/article/10.3934/energy.2017.4.691/fulltext.html
Methodology: Case Study
• Site Selection: QUESCO -> Transformer stations
• HOMER and REopt optimization: System Sizing
– Excess load over (90% nameplate capacity)
• Desktop design using Openwind and Helioscope
• Next iterations on real load data: Data request on progress
– Local constraints, land availability
– Environmental consideration – seasonal flash flood zone
• Time series analysis – for effectiveness of design
• Overload mitigate – metrics and comparison of various
scenarios.
• Detailed integration analysis – TBD
Case Study Sites
• Khanozai: 132 KV Station
• Two 20 MVA Transformers loaded over 150%
• Muslim Bagh: 132 KV Stations
• One Transformer loaded above 125%
12
Case Study: 132 KV Khanozai
• Station: Khanozai; Two transformers loaded above 150 %
• Transformer: T-2, Make: PEL, Capacity: 20 MVA, 174 %
• Load Type: Community or Commercial Type (Assumed)
• Time of overload: 11:00 am (October 2018)
• Design load: Excess load over 90% of Transformer capacity
• Excess Peak Load = 16.8 MW
Khanozai: 132 KV Station
I)
P hase
Site (
rm
in d Fa
W
600 6
400 4
200 2
0 0
0 5 10 15 20 25
Hour of the Day
System Sizing: Khanozai
• Threshold for design load = 90% of nameplate capacity
T-1 (HEC): 20/26 MVA- 61% Overload = 14.2 MW
T-2(PEL): 20/26 MVA - 74% Overload = 16.8 MW
• Initial design: based on summary of October 2018
o 10 Wind Turbine Generators: GE 1.5 MW sle
o 8 MWp Solar PV: Two Phases I and II
o 2 MWh/ 1MW BESS: Energy Storage
1800 8
1600 7
Load (kW)| GHI(W/m^2)
1400
6
400 2
200 1
0 0
0 5 10 15 20 25
400 180
353
350 160
120
250
# of Hours/ year
# of Hours/Year
225
100
200 184 173
143 80
150
111
109 60
98
100 84
40
50 39
25
4 2 20
0
0.5 MW 1 MW 2 MW 5 MW 10 MW 15 MW 16.8 0
MW 1 3 5 7 9 11 13 15 17 19 21 23
System Sizing: 132 KV Khanozai: T-2(PEL)
• System Size: Phase I
– 5 x 1.5 MW GE sle
– 3.8 MWp Solar
– 1 x 1MW/2MWh Storage
• Design philosophy
o Wind Speed : 6.05 m/s @50m
and 6.51 @ 65m Hub Height – Mitigate Overloading
Combiner Poles: 12
String size: 5 – 19
DC Nameplate: 3.81 MW
AC Nameplate: 3.06 MW
Storage: DES at Medium voltage
• Peak Shaving
• Load shifting
• Frequency regulation
• Voltage regulation
• Back-up power
• Distribution upgrade
investment deferral
23
Result for Khanozai: T-2 (PEL)
• Load Type: Community (Assumed)
– Overloaded for 34.16 days (820 hours) a year: Business-As-Usual
– RE with no storage 16.37 days (393 hours) a year
– RE with storage (1MW/2MWh) 9.87 days (237 hours) a year
• Life Saving: RE-energized Power Transformer
– Decreased overloading and its intensity
– % Loss of life (before): 2.66/year; % Loss of life (after): 0.34/year
– Enhance life over lifetime (20 years) : 46.4% 9.28 years
• Economics: Preliminary COE ~ $ 0.107
– Asymptotic nature: A balance between storage size and economics
– Value addition from saving the asset at risk and energy services.
24
Opportunity and challenges
• Prescreening of one DISCO:
Quetta AEB completed, but there
are a large numbers of
transformers across Pakistan,
specifically in locations with known
strong solar and wind resources
• Potentials and opportunities at
other DISCOs/AEBs
• Local counterpart will take a lead
on to explore opportunities for
Sindh Province: wind corridor; The
Karachi Electric (K-Electric) and
others
• Pros and cons of “RE-energising
the Overloaded Transformers”
Benefits/Conclusions
• 100’s of Millions of dollars of assets are at risk by the continued
overloading of Pakistan’s transformers. Benefits of mitigating this
challenge are:
Delay capital expenditures (i.e. transformer replacements) by years (in
some cases a decade)
RE Investing in strategic locations will save millions of dollars
Delay O&M annual expenditures
Improve Reliability of the transmission system by:
31
Regional Transformer Case Study
Power Transformer:
QESCO Fleet Subset