Professional Documents
Culture Documents
07 31.10.2022 - October 2022 Commission Monthly Progress Report (63) Updated
07 31.10.2022 - October 2022 Commission Monthly Progress Report (63) Updated
Authorities/AOB
ADDC: LDN approvals. ADDC system does not accept online application without affection plan. Letter issued 27 June 2022 from Musanada to ADDC, stating that ADM will provide the as-built affection plans after the project Short Term Look Ahead
completion, and requested ADDC to process the LDN applications. Further LDN application submitted on 5 July 2022 rejected by ADDC on 12 July 22 due to the absence of affection plans. ADM refuse to give affection plans due to it
Tunnel Works: Monitor/follow-up progress of critical section of tunnel structural and MEP works for further mitigation of current delays.
being an infrastructure project. ADDC approval to incorporate 5 No. substations within 1 No. LDN application agreed with ADDC. Single LDN application uploaded onto ADDC system by Designer on 23 August 2022 comments again
Tunnel Finishing: Finalization of lighting and cladding proposals to be followed-up/concluded. See Procurement section for update.
received and uploaded to ADDC for approval 23 September 2022.
Progress and Acceleration: Continue to follow-up recovery of actual progress against plan. Finalize Program and basis of Payment for acceleration costs. Parsons to closely monitor progress against program for any
TRANSCO: In the 02 June 2022 meeting, TRANSCO stated that Sheikh Khalifa Bin Zayed Street was opened to traffic for National Day (02 December 2021) on condition that the previously approved rerouting of the existing DN1200
required mitigation.
and DN1600 TRANSCO waterlines are built. Parsons and IAJV costed two options which was finalized and issued to Musanada 30 June 2022. Costs with four options have been finalised and issued to Musanada. Musanada have
Landscaping to LRT Corridor (Median): Instruction to be issued for Parsons to proceed with one of three options and award of works to Contractor.
presented to EXCOM for approval to proceed with the NDRC option.
Scope Gap (Specialist Lighting and Cladding): Presentation to DCT undertaken 25 August 2022. See Procurement section for update.
ITC: All MEP materials (previously to ADM) now being submitted to ITC including critical Tunnel Lighting Control System that was previously returned with comments by ADM and was again returned with comments by ITC. Revised
Additional Scope Gap Analysis (Commission Wide): Parsons have reviewed the project additional costs with Musanada and now with Musanada Senior Management for presentation to ADEO.
Tunnel Lighting Control Submittal received from Contractor returned by PIL with comments to address all ITC comments. Monthly meetings with ITC commenced on 4 August 2022 to follow-up all pending technical submittals and to
Demolition of Warehouses (3nr) Livestock Market, Slaughterhouse and Buildings: Parsons & Musanada to continue to follow up release of remaining Demolition Permits. See Procurement section for update.
initiate ITC site inspections.
Shed 2A: Letter from AD Ports Group received 22 September 2022 for the cancellation of Shed 2A Project in Zayed Port. EI 114 prepared for signature and issued 26 September 2022 to stop with immediate effect all
AD Civil Defense: ADCD requested revalidation of FLS Design submission. On 20 July 2022, Tebodin uploaded updated FLS drawings on ADCD portal for their review. ADCD advised of comments on 4 Aug-2022 including
activities pertaining to design and construction of Shed 2A project.
Turner & Townsend
requirement for FLS Drawings to be stamped by ADCD approved FLS Consultant. Tebodin submitted their fee proposal 15 September 2022 and Musanada issued instruction to proceed 20 September 2022, for review and stamping FLS
Truck Road and Mina Link Road: Close-out documents being followed-up.
Drawings by ADPC approved consultant. Review of drawings is ongoing.
EoT#3 & Revised Program. Follow-up Contractor’s resubmittal of EoT#3 and revised program incorporating painting requirements in place of tiling and early opening of surface roads.
Abu Dhabi Police & ITC: Abu Dhabi Police want to connect the TETRA and Abu Dhabi Media networks of Mina Tunnel to the existing Sheikh Zayed Tunnel and was not in the original scope of works. The virtual environment is a new
requirement by ITC which was not in the original scope of works. Once fully costed (3 quotations) by IAJV a meeting will be held with the concerned authorities and Musanada to agree the way forward for payment of these additional 2
works. Monthly Progress Report