Professional Documents
Culture Documents
ACC2125 L3 Flexed Budget, Interpreting Variances Controllability Principle 2021-22
ACC2125 L3 Flexed Budget, Interpreting Variances Controllability Principle 2021-22
Flexed Budgets
Drury Chapter 16
Reasons for Variances
It is important to understand the possible reasons for cost
variances.
Cupcakes Ltd makes a standard pack of 4 cupcakes with the following
cost information for direct materials, actual production is 100 packs of
cupcakes.
Standard Cost information:
Direct material 0.5kg @ £2 per kg = £1 per unit
Actual Cost data:
Direct material 0.55kg @ £1.80 per kg = £0.99 per unit
Think!
Cupcake Ltd has used more kgs than planned to What could have
produce the pack of cupcakes and has paid less caused these
per kg of direct material than planned. variances?
Controllable variances &
uncontrollable variances
There are many reasons why variances can occur.
Some are common sense such as wastage of materials by having
more substandard raw materials or increases in price causing the
actual to be more expensive than predicted. In the real world
having calculated all of the variances withoutinvestigating the
reasons would be apointless exercise as the variances are used
to control operations and know when activities are diverging from
budget. If this investigation showed that the original budget was
unrealistic then it would be normal practice to reforecast the
results for the year.
Why would we do this? To get a meaningful standard to
compare to
Flexed Budgets and Budgetary
Control
A budget is set at for a single level of activity – e.g. 10,000 units of
output. If the actual levels differ from budget, then comparing the actual
results with the original budget is not going to give meaningful
variances.
The standard unit costs will give the expected variable costs per unit
from which the contribution or standard gross margin can be calculated.
By knowing the budgeted unit selling price and predicted sales volume
the sales variances can also be calculated.
Fixed budget is set prior to the control period and not subsequently
changed in response to changes in activity, costs or revenues.
Effect of Volume on variable costs
Think!
High proportion of fixed
costs in modern
companies, these do
not vary with output
Jade plc budgets to sell 40,000 units per month for £50 per unit.
Actual sales in the month for the 37,000 units were £1,924,000
Drury p441
SALES VARIANCES
These variances explain the difference between theORIGINAL BUDGET and the Actual
results achieved.
-3,000 units (37,000 -40,000) x £16 per unit(£50 SSP - £34 VC)= 48,000 (A)
26,000 (F )
Example 2
Materials
Usage Variance
Flexed Budget Quantity at Budgeted Price 37,000x6kg @ £4.00 888,000
Actual Quantity at Budgeted Price 227,000 kg @ £4.00 908,000
20,000 (A)
Price
Actual Volume at Budgeted Price 227,000kg @ £4.00 908,000
Actual Volume at Actual Price 227,000kg @ £3.90 885,300
22,700 (F) 2,700(F)
Labour
Efficiency
Flexed Budget Hours @ Budgeted Rate 37,000 hrs @ £7.00 259,000
Actual Hours @ Budgeted Rate 35,600 hrs @£7.00 249,200
9,800 (F)
Rate
Actual Hours @ Budgeted Rate 35,600 hrs @£7.00 249,200
Actual Hours @ Actual Rate 35,600 hrs @£7.30 259,880
10,680 (A) 880(A)
Example 2
Variable Overhead
Efficiency
Flexed Budget Hours @ Budgeted Rate 37,000 hrs@ £3 111,000
Actual Hours @ Budgeted Rate 35,600 hrs @£3 106,800
4,200 (F)
Rate
Actual Hours @ Budgeted Rate 35,600 hrs @£3 106,800
Actual Hours @ Actual Rate 35,600 hrs @£3.303 117,600
10,800(A) 6,600(A)
Fixed Overhead
Expenditure Variance Production
Overheads
Flexed Budgeted Cost ( = Original Budget Fixed OHD) 200,000
Actual Cost 210,000
10,000 (A)
Expenditure Variance Admin Overheads
Flexed Budgeted Cost ( = Original Budget Fixed OHD) 45,000
Actual Cost 50,000
5,000 (A) 15,000(A)
SUMMARY OF VARIANCES
Jade plc budgets to sell 40,000 units per month for £50 per unit.
Actual sales in the month for the 37,000 units were £1,924,000
Standard Cost = SP * SQ
Actual Cost = AP * AQ
Standard Cost = SR * SH
Actual Cost = AR * AH
Adverse rate variance Paid more per hour worked than expected
a. Used more highly skilled labour than planned, paid higher rate per hour
b. Negotiated pay rates / bonuses higher than expected
c. Unexpected overtime to meet order deadlines
Labour rates are often not
Which of these reasons is controlled by the production
under control of production manager and are affected by
manager? general pay conditions and
economic factors.
Direct Labour Efficiency Variance
Labour Rate Higher / lower grade labour employed. Wage decreases / increases
Use of more / less skilled labour.
Managers should be held responsible for costs over which they exercise
control
If manager can only control the quantity but not the price/ rate paid, then can
only be held responsible for usage
Usage variance