Professional Documents
Culture Documents
Project Management
Project Management
MANAGEMENT
LEARNING
OUTCOMES
WHAT IS A
PROJECT?
Resource optimization
Along with being able to effectively estimate the important dates
along your project’s path, you can also judge the availability and
usage of your resources with high degrees of accuracy. This allows
you to assign tasks in a manner that makes full use of your team’s
capabilities while organizing work packets to seamlessly integrate
with each other.
Budget tracking
Depending on the size of your organization, you may or may not
have an accounting department assisting you on your project. Either
way however, it’s always a good idea to be keeping a close eye on
whether the project is staying within the set budget constraints,
which project management tools can do with minimal effort on your
part.
100% rule
Every level of decomposition must make up 100% of the parent level. At
least two child components are required.
Mutually exclusive
In a WBS, all components at a given level must be mutually exclusive. They must not have any
CHARACTERISTI overlap in their deliverables or work. This is intended to avoid misunderstandings and duplication of
work.
CS
Outcome-focused
The Work Breakdown Structure (WBS) must be focused on the end result of work,
i.e. deliverables, rather than the activities required to get there. Nouns, not verbs,
should be used to describe each piece. For beginners to WBS, this is a major source
of confusion.
FLOWCHART
GANTT CHART
CP
M
• Used if the duration of each activity is known
• Can be used to determine the length of time
required to complete a project.
• Can be used to control both time and project cost
2 2 2
A DAYS B D E
DAYS DAYS
A-1 A-3 A-4
3 A-2
Activity – an effort that DAYS
requires resources and takes a C
certain amount of time for Dummy – two or more activities in
completion the network that shows a precedence
relationship that represents no
passage of time.
Slack Time – the amount of time
an activity can be delayed without
delaying the project.
(3 DAYS - 2 DAYS)
1 A– 1 None 2
2 A– 2 1 3
3 A– 3 1 2
4 A- 4 2, 3 2
C B 5 5 3 A-2
DAYS
C
D B 4 5 5 5
Higher value
will prevail.
E D, C 6, 7 7
Pitch Deck 48
5. Compute the slack time associated with each activity. Identify the critical path
for the network. Critical activities are those with 0 slack time.
Slack Time = Backward pass - Forward Pass
E 7 7 0
Pitch Deck 49
Project Crashing - method for shortening the project duration by reducing the time of one or more
critical activities to lessen their normal time. It is achieved by devoting more resources thus the cost
associated with the project is increased, if cost increases then time decreases therefore time and cost are
inversely related
Cost Slope
Nt: Normal time
Crashing Objectives: Nc: Crashing time
❏ To reduce project duration Ct: Cost of activity in Nt.
❏ Minimizing cost of crashing Cc: Cost of activity in Nc.
Find the critical path and the additional cost when crashed by 2 days
2. When doing a forward pass with 2 predecessor the higher sum retains (e.g. A-3 and A-4,
2+4=6 and 8+1=9 therefore you will use the value 9 for node D )
3. When doing a backward
pass with 2 predecessor the lowest
4 days
B D
5 da difference retains (e.g. A-4 and A-5,
2 7 A-3 9 11 ys
A- s A-6 11-1=10 and 10-2=8 therefore you
ay
1
F
A- y
16 16
a
A
1d
4
0 0 4. Identify the critical path (A-C-E-F)
s
8 da
ay
ys
6d
A-2 C 2 days E
7
A-
8 8 A-5 10 10
Cost Slope: