SUPER SPECIALTY BLOCK

at
Assam Medical College, Dibrugarh
(PMSSY -III Scheme)

PROGRESS REVIEW MEETING


21.09.2018, at NHM Office ,Guwahati , Assam
Front Elevation

Assam Medical College, Dibrugarh, Assam under PMSSY-III


Project Details in brief
Name of the Project Construction of Super Specialty Block at
Dibrugarh under PMSSY-III
Tendered value of the project 73.12 Crores
Name of the Contractor M/s KMV Projects Ltd., Hyderabad
No of Floors G+5
Date of Award 12.08.2016
Duration of project 18 months
Date of Start 03.09.2016
Scheduled date of completion 02.03.2018
Targeted date of completion December-2018
No of Beds 240
SALIENT FEATURES/HIGHLIGHTS OF THE PROJECT – G + 5 FLOORS, AREA = 17759 SQM.

SL. FLOOR FACILITY


Cardiology, Urology, Dialysis-12 beds, X-ray room, Ultrasound, ECG,
GROUND FLOOR Pharmacy, Sample collection room, Staff room etc.
1

Pediatrics Surgery , Neurology, Neurosurgery, endoscopy, enchrnology


2 FIRST FLOOR Urology Wards – 29 Beds
CTVS – 20 Beds, Pediatrics – 20 Beds, Neurosurgery – 40 Beds
3 SECOND FLOOR

4 THIRD FLOOR CTVS – 20 Beds, Pediatrics – 20 Beds, Neurosurgery – 40 Beds

5 FOURTH FLOOR ICU’S – 52 BEDS

6 FIFTH FLOOR OT’S – 05 NOS., Cath lab , ICU – 12 Beds, Pre OP-8 beds, Post OP-10 beds

TERRACE
7 AHU’S

SERVICE Block
8 Ground Floor ESS, HVAC, MGPS.
Site Plan
Ground Floor Plan
First Floor Plan
Second Floor Plan
Third Floor Plan
Fourth Floor Plan
Fifth Floor Plan
Terrace Floor Plan
Physical Progress : 57.00%

Financial Progress :47.00%

Total value of work executed


as on date : 35.00 Crores
Current Status of major activity
Sl No. Activities Floors Status

A. RCC Work All Floors 98% Completed except ramp roof slab

B Brick Work
1. Gr Floor 90% completed
2. 1st Floor 95% completed
3. 2nd Floor 95% completed
4. 3rd Floor 95% completed
5. 4th Floor completed
6. 5th Floor completed
7. Above Terrace 30% completed

C. Internal Plastering Work


1. Gr Floor Work yet to start
2. 1st Floor 95% completed
3. 2nd Floor 95% completed
4. 3rd Floor 95% completed

5. 4th Floor 35% completed

6. 5th Floor completed

7. Above Terrace Yet to start.

D. External Plastering Work All Floors 25% completed


Current Status of major activity

Sl No Activities Floors Status


E. Electrical Works All floors Internal conduiting works completed. Wiring yet to start

F. Plumbing Works

1. Gr Floor Yet to start.

2. 1st Floor 70% completed (CI & CPVC Works)

3. 2nd Floor 40% completed (CI & CPVC Works)

4. 3rd Floor 20% completed (CI works)

5. 4th Floor Yet to start.

6. 5th Floor Yet to start.

G. Internal fire-fighting works All floors 95% completed

H. HVAC Works

1. Gr Floor 50% of ducting & piping work completed

2. 1st Floor 90% of ducting & piping work completed

3. 2nd Floor 90% of ducting work completed.

4. 3rd Floor 90% of ducting work completed.

5. 4th Floor Work started

6. 5th Floor Yet to start.


Current Status of major activity

Sl No Activities Floors Status


I. Flooring (Tile + Granite)
1. Gr Floor Yet to start.

2. 1st Floor •Vitrified dado 90% complete


• Vitrified flooring 90% complete
• Granite flooring yet to start.

3. 2nd Floor •Vitrified dado 80% complete


• Vitrified flooring 70% complete
• Granite flooring yet to start.

4. 3rd Floor • Vitrified dado 80% complete


• Vitrified flooring 60% complete
• Granite flooring yet to start.

5. 4th Floor • Vitrified dado 10% complete


• Vitrified flooring yet to start
• Granite flooring yet to start.

6. 5th Floor • Vitrified dado 70% complete


• Vitrified flooring yet to start
• Granite flooring yet to start.
Current Status of major activity

Sl No Activities Floors Status

J. False Ceiling All floors Work yet to start

K. Painting Works (Internal) All floors Work yet to start

L. Installation & Fixing of Electrical and All floors Yet to start.


Sanitary Fixtures

M. Lifts (5 nos) & Dumbwaiter (2 nos) Yet to start.

N. Service Block (Civil Works) Structure and brickwork completed

O. Under Ground Tank (Civil Works) Structure and brickwork completed

P. ETP (20 KLD)/ STP (185 KLD) Work in Process. 20 % RCC completed

Q. External Development Yet to start


Status of furniture and development of IT infrastructure
Sl Description Letter Amount Observations
No

1. Furniture for Super Informed to Principal, AMC Rs. 5.34 Crores Plan layout submitted to
specialty block, AMC, vide our letter dated AMC vide our letter dated
Dibrugarh 19/06/18 & 23/08/18 23/08/18.
Consent/observations
awaited from AMC.

2. IT development Informed vide our letter Tentative cost of Rs. 10.00


08/12/2017 Crores for the overall works

(a) HIMS (Hospital • The committee of AMCH


Management and opined that HIMS cost being
information system) exuberant, so cost as
proposed may be curtailed to
(b) PACS (Picture archiving a reasonable extent.
and communication
system) •Hospital building has a
functioning HIMS with
required infrastructure so the
existing HIMS may be
(c) QMS (Queue upgraded and extended to
management system) the super specialty block.
(d) LAN & WiFi
Status of Local Authority approvals/Assistance Required from State
Government
Sl No Description Status

1. Approval of drawings from Approval received


development authority

2. Provisional NOC from Fire department Approval received

3. Electrical load Sanction (1500 KVA) Approval received

4. Permanent Water Supply Approval awaited

5. Electrical estimate to release


connection from local Electricity Estimate received.
Board
Site Encumbrance

SL No Descriptions

1. One Medical shop, Sanjeevani Drug Store still exists which is hindering the
external development works. After pursuing the matter with client, it has been informed
that Court-stay order has beenobtained by the shop keeper. Client is pursuing to vacate
the same and referred this matter to their Legal advisor. (Expected clearance by end of
Sep’18).

Informed to AMC vide our letter dated 31/10/17,16/01/18 & 24/04/18,


PHOTOGRAPHS
.
.
.
.
.
.
.
.
.