Professional Documents
Culture Documents
Lec 2 SC 430 - Delivery of Construction Projects
Lec 2 SC 430 - Delivery of Construction Projects
Lecture No 2:
Construction Project Delivery
Options
THE STARTING POINT
• A need for a project has been identified:
Questions:
– Where will the money be obtained to pay for the
project?
– How will the project be procured (purchased,
implemented)?
– If finance is available - the Owner can proceed to
decide on the procurement method.
The starting point in project
NOTE:
The owner should Avoid frequent changes of mind since
it costs more and cause delays!
Option 1: All work in-house
• The Owner does the feasibility study;
• This is followed by preliminary designs and estimates
• Owner then uses own expertise to prepare detailed
design;
• S/he uses in-house staff to construct/erect the facility
• Use the erected facility for own purposes.
• Main Disadvantages:
– Lack of accountability.
– Poor quality and budgetary control;
Option 2: Design in-house and
erection by a contractor
• The Owner does the feasibility study;
• This is followed by preliminary designs and
estimates done by the owner;
• Owner then uses own expertise to prepare
detailed design;
• S/he uses an established contractor to carry out
the construction/erection;
Option 2: Design in-house and
erection by a contractor
• Owner supervises work performed by the
contractor
• Contractor hands over constructed facility when
construction is completed to the satisfaction of
the owner.
• Main disadvantage:
– Lack of accountability for design;
– Lack of quality control mechanism for
design.
Option 3: Initial design brief in-house, design by
a consultant and erection by main contractor
• The Owner prepares the project brief
(or can be assisted by a consultant);
• This is followed by preliminary designs and estimates
done by a Consultant;
• Owner then uses the prepared detailed design to select a
contractor to construct;
• Consultant supervises work performed by the contractor
• Contractor hands over constructed facility when
construction is completed to the satisfaction of the
Consultant.
Option 3: Initial design brief in-house, design by a
consultant and erection by main contractor cont…
Main disadvantage:
• May be time consuming.
This is the method that is known as the traditional
method which is used very often
NOTE:
• Main attention in the course will be centered on this
method.
Option 4: Design and Build
• Under this method of contracting, the owner
awards a single contract to the design-builder to
design and construct the Work.
• Thus, the design-builder undertakes responsibility
for both the design and construction of the project.
• The Owner prepares the project brief
(or can be assisted by a consultant);
• Client prepares preliminary estimate based on
prelim. designs; (or appoints a Consultant to
prepared prelim. Designs);
Option 4: Design and Build
• Client supervises the erection to ensure that
performance requirements are met;
(or may appoint a Consultant to do so);
• Final project accepted on the basis of performance tests
by Consultant or Client;
Option 4: Design and Build
Main advantages:
Selection flexibility.
Team Concept.
Single point of accountability for design and
construction.
Enables fast-track delivery (construction
begins before design is complete), saving time.
Facilitates alternative financing methods.
Eliminates Owner concern with cost overruns.
Design and Build
Disadvantages:
No check and balance between architect and
builder.
Owner must select a team rather than the best
architect and best builder.
Difficult to control quality because design/build
team must
Only meet minimum criteria standards.
Method 5: Design and Manage
by a project manager
In this option the Owner
• Prepares the project brief (or can be assisted
by a consultant);
• Appoints a Project Manager to carry out the
design (or obtains design services from other
firms);
• Then appoints various contractors to perform
different aspects of the project.
• S/he remain responsible for the project design
and construction/installation/erection.
Method 5: Design and Manage
by a project manager
Main Disadvantage:
– If the PM is not good the project can fail
very easily.
– Costs may increase beyond budget.
Advantage:
• Speed
Method 6: Raising the finance, design, and
construction operation by a single contractor
• Client may prepare a project brief and invite
contractors
• Contractor performs detailed feasibility study;
• Contractor raises funds for the project;
• Appoints consultant to perform detailed Design;
• Implements construction to completion;
• Starts operating the constructed facility
-say a bridge which s/he Then charges for
crossing;
• Operates the facility until the return on
investment is obtained;
Method 6: Raising the finance, design, and
construction operation by a single contractor
• Advantage:
– Client does not use his/her own funds for the
project;
• Disadvantage:
– Client has little control unless by means of
legislation or special agreements;
Summary
• There are many other combinations of the
above delivery methods.
• Government policy is now discouraging the use
of methods:
– 1-all in-house – design and erect;
– 2-Design in-house and erection by
contractor.
PPA 2004 and PPA2011
• The Public Procurement Act 2011 (PPA 2011) is
based mainly on the traditional method of
appointment of consultant and then appointment
of contractor.
• However, it allows for other methods of
delivery within the Public Private Partnership
(PPP) Concept.
• Regulations and standard documents for the
same are widely available.
• It also includes a preference margin for
domestic consultants in order to encourage them
PPA 2004
• Covers supply of goods, construction,
professional (consultant services), and non-
consultant services.
• Applies for all public institutions;
• Not following the PPA 2011 is breaking the
law;
• It is necessary for both public and private
sector to understand as it governs the
procedures that must be used in procurement.
PPA 2011 Framework
PPA 2011
Guidelines
PPA 2004 Framework
• This public procurement framework shall be
used as the default framework for this course .